Port Of Jacksonville Maritime Ad Hoc Committee, Inc. v. United States Coast Guard

788 F.2d 705, 1986 U.S. App. LEXIS 24883
CourtCourt of Appeals for the Eleventh Circuit
DecidedMay 6, 1986
Docket85-3178
StatusPublished

This text of 788 F.2d 705 (Port Of Jacksonville Maritime Ad Hoc Committee, Inc. v. United States Coast Guard) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Port Of Jacksonville Maritime Ad Hoc Committee, Inc. v. United States Coast Guard, 788 F.2d 705, 1986 U.S. App. LEXIS 24883 (11th Cir. 1986).

Opinion

788 F.2d 705

PORT OF JACKSONVILLE MARITIME AD HOC COMMITTEE, INC. and
Jacksonville Shipyards, Inc., Plaintiffs-Appellants,
v.
The UNITED STATES COAST GUARD and Jacksonville
Transportation Authority, Defendants-Appellees.

No. 85-3178.

United States Court of Appeals,
Eleventh Circuit.

May 6, 1986.

Thomas M. Baumer, Jacksonville, Fla., for plaintiffs-appellants.

Robert C. Gobleman, James E. Cobb, Jacksonville, Fla., for Jacksonville Transp. Auth.

John E. Lawlor, III, Asst. U.S. Atty., Jacksonville, Fla., for Coast Guard.

Robert L. Klarquist, Appellate Sect./Land & Natural Resources Div. Jacques B. Gelin, Dept. of Justice, Washington, D.C., for U.S.

Appeal from the United States District Court for the Middle District of Florida.

Before GODBOLD, Chief Judge, KRAVITCH, Circuit Judge, and SIMPSON, Senior Circuit Judge.

GODBOLD, Chief Judge:

This case was brought to challenge an action of the United States Coast Guard. Our review is governed by the Administrative Procedure Act, 5 U.S.C. Sec. 701 et seq.

The Port of Jacksonville Maritime Ad Hoc Committee and Jacksonville Shipyards appeal from the district court's summary judgment granted on motions of the United States Coast Guard and Jacksonville Transit Authority (JTA). We affirm.I. BACKGROUND

Congress has delegated to the Secretary of Transportation the power to approve the building of bridges over navigable waters of the United States. 33 U.S.C. Sec. 525 (1982). Pursuant to this delegation the secretary, through the Coast Guard, has promulgated regulations governing the issuance of bridge-building permits. In 33 C.F.R. 115.10(a) the Coast Guard has mandated that "[s]pecific time limitations are [to be] inserted in all [bridge-building] permits for the commencement of construction and completion thereof." The Coast Guard has formulated its own internal interpretation of the phrase "commencement of construction." Paragraph 1-C2.d-4 of its Bridge Administration Manual, COMDTINST-M16590.5 provides:

Commencement of construction is normally considered to be the date upon which work actually commences on the site of the proposed bridge, its approaches or ancillary works, including work in the water such as filling in, dredging, or other work authorized by the Corps of Engineers which is related to the bridge project. However, in cases where construction will be carried out under a construction contract with performance guaranteed by a bond or other surety, the date of the contract shall be the date of commencement.

This interpretation has never been published in the Federal Register.

On July 11, 1979 the Coast Guard granted JTA a permit to construct the "Dame Point" bridge across the St. John's River in Jacksonville, Florida.1 The permit, as required by 33 C.F.R. 115.10(a), contained a date by which construction had to commence or else the permit would expire. This date was July 11, 1984, and the required completion date was July 11, 1988. For over four and one-half years after the issuance of this permit JTA took no action toward commencing construction. On March 7, 1984 JTA informed the Coast Guard that it intended to advertise a construction contract for the driving and test loading of one of the permanent piles of the bridge, to be located on the shore. In its letter the JTA requested that the Coast Guard "concur" in JTA's position that (1) the construction of this pile would constitute "commencement of construction" under the Coast Guard's interpretation of that phrase, and (2) that the award of a bonded contract for the driving and test loading of the one pile would satisfy the Coast Guard's interpretation. The Coast Guard responded to this inquiry with a letter on April 9 that merely paraphrased its interpretation of "commencement of construction." This response did not indicate whether either the construction of the pile or the award of a contract with a performance bond to construct the pile would fall within this interpretation.

On April 25 the Coast Guard placed a memorandum in its internal file on the St. Johns bridge noting that the pile would remain part of the permanent structure of the bridge and that "this event [the driving of the pile] would constitute timely commencement of bridge construction."

On June 11 JTA entered into a contract, with a performance bond, for the construction and test loading of the pile, and the Coast Guard was advised of the contract three days later. The pile was driven June 25, 16 days before the permit was to expire.

On July 10, 1984 appellants sent a letter to the Coast Guard asking it to state whether construction had commenced and, if so, whether various factors set out in the letter had been taken into account by the Coast Guard in making a determination that construction had commenced. The Coast Guard replied by letter of July 25, paraphrasing paragraph 1-C-2.d-4 of the Bridge Administration Manual and stating that the driving and pile load test constituted the commencement of construction.

The appellants filed suit in United States District Court, MD Florida, contesting the Coast Guard's determination that the driving of the test pile constituted commencement of construction. The district court granted the Coast Guard's and JTA's motions for summary judgment on the ground that the Coast Guard's action in determining that the driving of the piling was the commencement of construction was not arbitrary and capricious. In making this ruling the district court relied solely on the date, June 25, on which the pile actually was put into place. The court, like the Coast Guard, did not address the question of whether the execution of the June 11 contract fell within the Coast Guard's interpretation of "commencement of construction."

II. DISCUSSION

A court reviewing a decision of an administrative agency must uphold the judgment of the agency unless a review of the administrative record discloses that the decision was "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law." 5 U.S.C. Sec. 706(2)(A); see also Bowman Transportation v. Arkansas-Best Freight System, Inc., 419 U.S. 281, 284, 95 S.Ct. 438, 441, 42 L.Ed.2d 447 (1974); Tackitt v. Prudential Insurance Co., 758 F.2d 1572, 1575 (11th Cir.1985). In employing this deferential standard of review, however, a court does not rubber stamp the action of the agency; rather, it must satisfy itself that the agency has "articulate[d] a 'rational connection between the facts found and the choice made.' " Burlington Truck Lines v. U.S.,

Related

Cite This Page — Counsel Stack

Bluebook (online)
788 F.2d 705, 1986 U.S. App. LEXIS 24883, Counsel Stack Legal Research, https://law.counselstack.com/opinion/port-of-jacksonville-maritime-ad-hoc-committee-inc-v-united-states-coast-ca11-1986.