Polish v. Johnson's Service Co.

218 F. Supp. 387, 1963 U.S. Dist. LEXIS 6944
CourtDistrict Court, E.D. Pennsylvania
DecidedMarch 13, 1963
DocketCiv. A. No. 25593
StatusPublished
Cited by3 cases

This text of 218 F. Supp. 387 (Polish v. Johnson's Service Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Polish v. Johnson's Service Co., 218 F. Supp. 387, 1963 U.S. Dist. LEXIS 6944 (E.D. Pa. 1963).

Opinion

VAN DUSEN, District Judge.

This case, brought by the Trustee in Bankruptcy of a plumbing and heating contractor against a subcontractor who had contracted with such plumbing and heating contractor to install temperature controls in a high school building, was tried to the court on February 26, 27 and 28, 1963. The Trustee claims that such subcontractor received an overpayment, to part of which the Trustee is entitled, in securing from the owner the full amount owed to such subcontractor by the bankrupt at the time of the adjudication in bankruptcy.

On December 5, 1955, the bankrupt contracted (P-8) with “HIS EXCELLENCY, MOST REVEREND JOHN F. [388]*388O’HARA, C.S.C., Archbishop of Philadelphia,” to furnish and install all plumbing and heating work in a new high school for the Roman Catholic Archdiocese of Philadelphia, to be known as Monsignor Bonner High School, and to be built in Drexel Hill, Upper Darby, Delaware County, Pa. The high school was to be built on real estate owned by the Roman Catholic Archdiocese of Philadelphia (hereinafter referred to as “Archdiocese”). The above-mentioned contract of December 5, 1955, provided for a consideration of $217,000. to be paid for the above-described plumbing and heating work. The following typewritten Article XIX appears at the end of the printed form of contract used in preparing the contract of December 5, 1955 (P-8):

“Owner accepts an alternate proposal suggested by Contractor whereby Johnson Service Pneumatic controls are used instead of Minneapolis Electric controls at a deduction in cost of $5,500.00.”

Certain parts of the work to be done under the above contract of December 5, 1955 (P-8) were subcontracted by the bankrupt, including the installation of a temperature regulation system. The contract for this system was entered into with Johnson Service Company (a Wisconsin corporation), defendant, with the understanding that the “valves, dampers, pan and grid humidifiers furnished * * shall be installed by others free of expense to” the defendant (D-3). This temperature regulation system, together with necessary electrical wiring, was to be installed for a price of $6,000.

On or about August 9, 1957, the bankrupt, being in a precarious financial condition, stopped work on the job site in Upper Darby. A few days subsequent to that date, defendant wrote a letter dated August 9, 1957, to the Archdiocese, with copies to the attorneys for the Archdiocese, the bankrupt, the architect, the surety company on the performance bond of the bankrupt, and others. This letter (P-2) enclosed a statement showing that, although bills for progress payments had been submitted by the deféndant to the bankrupt in the total amount of $5,292. on or before August 6, 1957, only $1638. (representing the first bill submitted in May of 1956) had been paid, leaving a balance due of $3,654. The letter contained this wording, among others:

“We wish to advise you as indicated upon our statement these items run back as far as June 1956 and our terms of payment are 30 da.vs net. We also wish to advise you that under our company policy we cannot complete this job until payment is received or guarantee of payment made by your organization.
“We would appreciate your cooperation in this matter by forwarding necessary remittance or remittance from Penn Plumbing & Heating Company or guarantee of payment from the Archdiocese of Philadelphia for the stipulated amount.
“We wish to reiterate that our company policy prohibits finishing contract work on which payments are not received.”

The Archdiocese answered the above letter from defendant dated August 9, 1957, by a letter of August 16, 1957 (P-3), stating “ * * * we could not make payment to you * * * without an assignment from” the bankrupt. “Our performance bond guarantees completion only. Under the circumstances, we cannot comply with your request.” On August 21, 1957, the defendant wrote the bankrupt (P-4), saying:

“ * * * we are therefore looking directly to your company for payment of this amount due or as stated above we do not wish to inconvenience anyone concerned, but request that necessary arrangements be made for payment upon this contract.”

On August 30, 1957, the bankrupt filed a voluntary petition in bankruptcy in this court (Cause No. 25148) and was adjudicated a bankrupt on the same day.

[389]*389Shortly after receipt of the letter of August 9 (about August 14), Sabin and Company (a plumbing and heating contractor) was consulted by the Archdiocese and asked to complete installation of the temperature controls in the Bonner High School. At that time, the contract (D-3) undertaken by the defendant had been completed to the point of installing the pipe heads in the walls of the 18 rooms of the high school where thermostats were to be located. The thermostats had not yet been installed. Sabin and Company reported to the Archdiocese that the thermostats which could be fitted on the pipe heads already installed were only available from the defendant and the cost of removing the 18 pipe heads, installing pipe heads usable with other thermostats, and the procurement of thermostats from a competitor of defendant would be substantial.1

A conference called by the Archdiocese was held on September 13,1957, at which representatives of the architects, Sabin and Company, defendant, and of the Archdiocese (including the attorney for the Archdiocese), among others, were present. At this meeting, the representatives of the defendant again emphasized that the policy of their company prevented them from doing any further work on the high school building unless the balance due under the contract by the bankrupt and the defendant was guaranteed by the Archdiocese or paid. At this conference, the urgency of completion of the temperature control system in the high school was discussed by those present.2 It was clear to those present, including the representatives of the defendant, that the Archdiocese would have to have the work completed almost immediately due to the possibility of cold weather in late September or early October. It was also made clear at this meeting that even if an alternative thermostatic control and pipe head for such alternative control were installed, there was a possibility that other parts of the heating system already installed under defendant’s supervision might not work. Defendant gave a one-year free service contract on all jobs completed, but it would not give such free service if the pipe head and thermostat of a competitor were installed. There was no assurance that any competitor would give a guarantee or service contract if its pipe head and thermostat control were installed in the system designed for defendant’s product, even though it was quite possible that the system would work with an alternative pipe head and thermostat.

On October 7, 1957, there was another meeting at the offices of the Archdiocese, at which the representatives of Sabin and Company reported that they could not do any further work on the heating system until the thermostats were installed. The architect recommended that these thermostats be procured from the defendant. Under these circumstances, the attorneys for the Archdiocese were authorized to prepare a writing, to be executed by the defendant, which would recite the circumstances under which the Archdiocese should guarantee payment of the amount [390]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayerson v. Washington Manufacturing Co.
58 F.R.D. 377 (E.D. Pennsylvania, 1972)
Polish v. Johnson Service Co.
333 F.2d 545 (Third Circuit, 1964)
Polish v. Johnson Service Company
333 F.2d 545 (Third Circuit, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
218 F. Supp. 387, 1963 U.S. Dist. LEXIS 6944, Counsel Stack Legal Research, https://law.counselstack.com/opinion/polish-v-johnsons-service-co-paed-1963.