Placeway Construction Corp. v. United States

36 Cont. Cas. Fed. 75,808, 19 Cl. Ct. 484, 1990 U.S. Claims LEXIS 35, 1990 WL 12078
CourtUnited States Court of Claims
DecidedFebruary 9, 1990
DocketNo. 382-87C
StatusPublished
Cited by6 cases

This text of 36 Cont. Cas. Fed. 75,808 (Placeway Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Placeway Construction Corp. v. United States, 36 Cont. Cas. Fed. 75,808, 19 Cl. Ct. 484, 1990 U.S. Claims LEXIS 35, 1990 WL 12078 (cc 1990).

Opinion

OPINION

LYDON, Senior Judge:

This government contract case comes before the court on the motion of plaintiff Placeway Construction Corporation (Place-way) to reconsider and vacate the court’s decision in Placeway Construction Co. v. United States, 18 Cl.Ct. 159 (1989), filed September 8, 1989. Plaintiff brings this motion, filed January 18, 1990, pursuant to Rules 59 and 60, and specifically on the grounds of newly discovered evidence set forth in Rule 60(b).1

Plaintiff seeks relief from the court’s decision to grant defendant’s motion to dismiss plaintiff’s contract claims without prejudice. The court granted defendant’s motion to dismiss plaintiff’s claims on the ground that the court lacked jurisdiction to entertain any of plaintiff’s claims, since they were not the subject of a final decision issued by a contracting officer (CO), and on the additional ground that, since two of plaintiff’s claims were subject to the certification requirement of the Contract Disputes Act (CDA), the court lacked jurisdiction to entertain these claims since they were not properly certified.2 Plaintiff’s motion for reconsideration does not address the issue of the jurisdictional requirement [486]*486that the claims be the subject of a CO’s final decision, although plaintiff acknowledges the certification requirement by informing the court that it has now certified all of its claims and has resubmitted them to the CO.

BACKGROUND

In 1983, Placeway entered into a construction contract with the United States Coast Guard to build brick family housing units on Governor’s Island, New York. After various modifications, the contract was substantially completed by plaintiff in December 1984, about six months after the scheduled completion date. In May 1986, Placeway submitted claims to the CO for the balance due under the contract, and for additional compensation to which plaintiff claims it is entitled. None of these claims was certified under the CDA. In September 1986, the CO denied all of plaintiff’s claims. Plaintiff subsequently filed suit on these claims in this court on June 26, 1987.

The court issued its judgment dismissing plaintiff’s claims for lack of jurisdiction on September 8, 1989. In its decision, the court condensed plaintiff’s six counts in its complaint to three claims: a balance due claim of $297,226.12; an additional work claim of $287,047.89; and an extended overhead claim of $119,585.91. The court found the balance due claim to be a government claim, since the CO refused to pay plaintiff the balance due under the contract until all delay claims of certain other contractors against the government were submitted and evaluated. The CO apparently believed that the contract delays suffered by these other contractors were caused by plaintiff’s delays in performing its contract. The court found that the government intended to set off amounts it owed plaintiff with amounts plaintiff was found to owe it. Therefore, the court found, and plaintiff does not deny, that the CO’s decision denying plaintiff’s claims was not a final decision under the CDA. The court explained that “[i]n the absence of a CO’s final decision on the set-off amount, the court is without jurisdiction to entertain Count II [the balance due claim] of plaintiff’s complaint.” Placeway Construction, supra, 18 Cl.Ct. at 165.

Therefore, although the court held that Placeway’s balance due claim was actually a government claim, and thus did not require certification, nevertheless the claim was not the subject of a CO’s final decision, which effectively precluded the court from exercising jurisdiction over the claim. With regard to plaintiff’s other two claims, the court found both the lack of certification and the lack of a final decision precluded the court from exercising jurisdiction over these claims.

DISCUSSION

Plaintiff supports its motion for reconsideration under Rule 60(b) by submitting the affidavit of its attorney, Vincent J. Zichello, who contends that he has obtained newly discovered evidence “after great difficulty,” and that he obtained this evidence a few days prior to January 16, 1990, the date of his affidavit. Plaintiff attached Exhibits A through E to the Zichello affidavit as proof of the “newly discovered” evidence.

Plaintiff’s affidavit and exhibits pertain to the claims of Kokolakis, a contractor, against the government, including a claim for delays purportedly caused by plaintiff. Plaintiff now contends that the Kokolakis claim had already been submitted to, and decided by, the CO prior to the court’s decision in this case. Plaintiff blames the CO for failing to bring this information to the attention of plaintiff and the court. This “newly discovered” evidence, plaintiff contends, shows that “everything this court believed was prerequisite had in fact already occurred.” This statement reflects plaintiff’s apparent misapprehension of portions of the court’s opinion.

The court stated in its decision that all delay claims by contractors against the government must be resolved before plaintiff’s claims can be resolved by the CO. Plaintiff admits, however, that it has in fact obtained information regarding the claim of only one contractor, Kokolakis. Nevertheless, plaintiff argues that “it is not for want of trying” that it has been [487]*487unable to obtain any documentation regarding the delay claim of another contractor-claimant, Velez. Plaintiff apparently believes that there are only two potential contractor-claimants, but gives no reason for this belief. Plaintiff argues, however, that this litigation should be resolved without waiting for the resolution of the Velez claim, since plaintiff has been told, apparently by the government, that the Velez contract is currently the subject of a criminal investigation. Plaintiff maintains that it would be “grossly unfair to hold up Placeway’s contract balance, indefinitely.”

The Zichello affidavit concludes by informing the court that plaintiff submitted all its claims to the CO, with CDA certification, on October 31, 1989, and has received no response as yet. Plaintiff also filed, on October 31, 1989, an appeal of the court’s decision to the Court of Appeals for the Federal Circuit (docket no. 90-5017).

-A-

As an initial matter, the court must consider how to proceed on plaintiff’s Rule 60(b) motion for reconsideration of the judgment, in view of the fact that this motion is preceded by plaintiff’s timely filed appeal to the Federal Circuit, which is still pending. In this regard, the Claims Court has observed that “[a]s a general proposition, once final judgment is entered and a timely appeal has been filed, the trial court loses jurisdiction over the case except to act in aid of the appeal or to correct clerical errors____ Without jurisdiction, this court is without power to grant relief under Rule 60(b).” Yachts America, Inc. v. United States, 8 Cl.Ct. 278, 280 (1985); affd, 779 F.2d 656 (Fed.Cir.1985), cert. denied sub nom. Wilson v. United States, 479 U.S. 832, 107 S.Ct. 122, 93 L.Ed.2d 68 (1986) (citing Ced’s Inc. v. United States, 745 F.2d 1092, 1095 (7th Cir.1984), cert. denied, 471 U.S. 1015, 105 S.Ct. 2017, 85 L.Ed.2d 299 (1985); Nicol v. Gulf Fleet Supply Vessels, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Q Integrated Companies, LLC v. United States
131 Fed. Cl. 125 (Federal Claims, 2017)
Madison Services, Inc. v. United States
94 Fed. Cl. 501 (Federal Claims, 2010)
Ciaccio v. Secretary of Health & Human Services
27 Fed. Cl. 202 (Federal Claims, 1992)
Information Systems & Networks Corp. v. United States
38 Cont. Cas. Fed. 76,346 (Court of Claims, 1992)
Widdoss v. United States
24 Cl. Ct. 547 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,808, 19 Cl. Ct. 484, 1990 U.S. Claims LEXIS 35, 1990 WL 12078, Counsel Stack Legal Research, https://law.counselstack.com/opinion/placeway-construction-corp-v-united-states-cc-1990.