Pinckney v. Dambmann Bros., & Co.

19 A. 450, 72 Md. 173, 1890 Md. LEXIS 15
CourtCourt of Appeals of Maryland
DecidedMarch 18, 1890
StatusPublished
Cited by12 cases

This text of 19 A. 450 (Pinckney v. Dambmann Bros., & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pinckney v. Dambmann Bros., & Co., 19 A. 450, 72 Md. 173, 1890 Md. LEXIS 15 (Md. 1890).

Opinion

McSherry, J.,

delivered,the opinion of the Court.

On the tenth of June, 1886, the appellees purchased from the appellant three thousand tons of Dorchester mine, South Carolina, rock phosphate, at five dollars and fifty cents per ton, delivered on board the buyers’ vessels at Charleston, to be paid for in cash, or, at buyers’ option, by note at four months; and they agreed to-remove the rock between September the first, 1886, and April the thirtieth, 1887. On the 24th of December, 1886, the appellees purchased from the appellant “three cargoes” of the same phosphate at four dollars and seventy-five cents per ton, delivered on board the buyers’ vessels at Charleston, to be paid for in cash, or, at buyers’ option by note at four months; the “rock to be removed on completion of present contract, say between May and December, 1887.” The second contract was not performed, and [178]*178the appellees claiming that the appellant had broken,it, sued out a foreign attachment to recover the damages alleged to have been sustained by them. The appellant subsequently appeared, gave bond, by which the attachment was dissolved, and pleaded non assumpsit and never indebted. The trial resulted in a judgment against him, and he has taken this appeal.

The questions presented by the record may be reduced to four, viz., first, whether there was a breach of the contract of December 24, on the part of the appellant; secondly, assuming that there has been, whether that contract is sufficiently definite in its terms to support the pending action. The third relates to the admissibility of evidence, and the fourth was raised by way of objection to the instruction granted at the instance of the appellees.

In considering the first question, it becomes necessary to go somewhat fully into the facts, because upon them its solution mainly depends. It may, we think, be fairly inferred from the face of the two contracts, that it was the intention of both buyers and seller that deliveries under these agreements should not be made concurrently. The express terms of the second provided that the rock sold under it was to be removed upon the completion of the first, ‘‘say between May and December, 1887. ” The first contract distinctly limited the time within which the appellees were at liberty to send their vessels to Charleston for the phosphate; and the limit there fixed was April 30th, 1887. The appellees failed to remove all of the three thousand tons by that date. They subsequently sent their vessels to Charleston for the remainder of the three thousand tons, and the appellant loaded three of those vessels after the thirtieth of April, under the contract of June 10th, 1886. This was a waiver of the appellees’ failure to remove the rock between September the first, 1886, and April the thirtieth, [179]*1791887. Bollman vs. Burt, 61 Md., 415. The last shipment under that contract was on the -- day of May, 1888. The time for shipment under the first contract was accordingly, by both of the parties to it, as evidenced by their acts, extended far beyond April 30th, 1887.

It is now insisted that this extension of the time for the completion of the first contract deferred the period for demanding deliveries under the second, inasmuch as these deliveries were fixed to begin upon the completion of the first contract. Did, then, the extension of the first contract carry with it an extension of the second ? If no reference had been made in the second contract to the ending of the first, and if the limits named in the second be considered fixed and definite, then, undoubtedly, the terms “between May and December, 1887,” excluded both termini — both May and December, — and the time for the performance of the second contract expired on and with the thirtieth of November, 1887. Revere vs. Leonard, 1 Mass., 91; Kendall vs. Kingsley, 120 Mass., 95. But the words, “rock to be removed on completion of present contract, say between May and December, 1887,” do not imply in this case that the limits thus designated, between May and December were absolute; because the parties themselves have indicated that they did not intend those limits to be inflexible. McConnell vs. Murphy, L. R., 5 P. C. A., 203. Keeping in view the evident design of the buyers and seller when the contracts were made, that they were not to be executed concurrently, but in succession, there is little, if any, reason to doubt, when the correspondence between the parties is examined, what the mutual understanding of those parties was with respect to the meaning of the words imposing a limit for deliveries under the contract of December 24th, 1886. Without transcribing that correspondence, which began on November 10th, 1887, and ended on the 12th of May, 1888, it is sufficient at this point to say, that it had its [180]*180origin in an effort on the part of the appellees to secure lower prices than the rates named in the two contracts, in consideration of the surrender by the buyers of their option to settle by notes at four months. Throughout nearly the whole correspondence, both contracts are spoken of as outstanding or subsisting, though the time originally fixed for the completion of the first one had expired six and a half months before the letter of November the tenth, the beginning of the correspondence, was written. The parties failed to agree upon satisfactory terms as to cash settlements under both contracts, though they did agree as to the first one; and on December the second, after the expiration of the estimated limit named in the contract of December 24th, 1886, the appellees wrote to the appellant, and said: “Regarding the modification of the two existing contracts, we beg to state, that we decline to further discuss the matter; we will take the balance of first contract at your own figures, of $4.60 cash, and let the second contract stand on its own merits. When the time comes for the settlement of deliveries on account of the second contract, we will then, as it may suit us, pay cash or ipake use of the note option. ” To this the appellant, on December 5th, replied: “ To come to practical matters, we will load your vessels at $4.60 cash on this contract, and as you so desire, will postpone the discussion of the other contract for the present.” Here is a clear and distinct recognition of the fact that both contracts were then, according to the understanding of all the parties, subsisting and in force, even though the estimated limit named for the full completion of the last one had actually passed. If the appellant thought at that time, as he thinks now, that the second contract expired when the period between May and December had elapsed, and that the completion of the first had nothing to do with the performance of the second, it was his plain duty to [181]*181have said so in unambiguous terms. Manifestly, he ought not to have treated it as subsisting and outstanding, if he did not consider that it was so. And he could only have treated it as then subsisting by assuming that the period for its performance depended on the completion of the first agreement. It results, then, that the extension of the first contract, upon the completion of which the second was to begin, carried with it, in accordance with the expressed intention of the parties, as evidenced by the letters from which extracts have been quoted, an extension of the time when deliveries under the contract of December 24th were to begin.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prince George's County v. Collington Crossroads, Inc.
299 A.2d 792 (Court of Appeals of Maryland, 1973)
Abuc Trading & Sales Corp. v. Jennings
135 A. 166 (Court of Appeals of Maryland, 1926)
Martin Fertilizer Co. v. Thomas & Co.
109 A. 458 (Court of Appeals of Maryland, 1920)
Lowy v. Rosengrant
71 So. 439 (Supreme Court of Alabama, 1916)
Shoop v. Fidelity & Deposit Co.
91 A. 753 (Court of Appeals of Maryland, 1914)
Gude & Walker v. Bailey Co.
61 S.E. 135 (Court of Appeals of Georgia, 1908)
Potomac Bottling Works v. A. H. Barber & Co.
63 A. 1068 (Court of Appeals of Maryland, 1906)
Cable Co. v. Wasegizig
90 N.W. 24 (Michigan Supreme Court, 1902)
Hartlove v. William Fait Co.
43 A. 62 (Court of Appeals of Maryland, 1899)
Cole v. Hines
32 L.R.A. 455 (Court of Appeals of Maryland, 1895)
Bagby v. Walker
27 A. 1033 (Court of Appeals of Maryland, 1893)
McGrath v. Gegner
26 A. 502 (Court of Appeals of Maryland, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
19 A. 450, 72 Md. 173, 1890 Md. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pinckney-v-dambmann-bros-co-md-1890.