Pike Co. v. Universal Concrete Prods., Inc.
This text of 284 F. Supp. 3d 376 (Pike Co. v. Universal Concrete Prods., Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
ELIZABETH A. WOLFORD, United States District Judge
INTRODUCTION
This action is but one of many legal disputes currently pending between the *383parties, arising out of construction activities on property owned by Marist College ("Marist") in Poughkeepsie, New York. This dispute involves the contractual rights and obligations between plaintiff The Pike Company, Inc. ("Plaintiff") and defendant Universal Concrete Products, Inc. ("Defendant"). Plaintiff, the general contractor for the construction project, claims that Defendant, its subcontractor, materially breached the terms of the parties' subcontract and improperly encumbered the project property with a mechanic's lien that has been discharged by bond. (See Dkt. 7 at 6-9). Plaintiff seeks damages for breach of contract, unjust enrichment, and violations of the New York Lien Law, and an order invalidating and vacating the lien and bond. (Id. ).
Presently before the Court is Defendant's motion to dismiss, stay, or transfer this action (Dkt. 8), and Marist's motion to intervene as a plaintiff-intervenor (Dkt. 18). For the following reasons, Defendant's motion is denied, and Marist's motion is granted.
BACKGROUND 1
Marist, a private liberal arts college located in Poughkeepsie, New York, engaged the services of Kirchoff-Consigli Construction Management, LLC ("KCCM") to act as the general contractor for a construction project involving several buildings on Marist's campus (the "Project"). (Dkt. 18-1 at ¶ 4 (Affidavit of Justin Butwell)). Defendant acted as KCCM's subcontractor for the Project until May 4, 2015, when Marist hired Plaintiff to replace KCCM as the general contractor. (Id. at ¶¶ 5-7). On May 29, 2015, Plaintiff and Defendant entered into a subcontract to perform work on the Project (the "Subcontract"). (Id. at ¶ 8; see Dkt. 7 at ¶ 8).
Plaintiff alleges that the Subcontract contains an alternative dispute resolution clause, requiring the parties to proceed with mediation before seeking judicial recourse should a dispute arise under the Subcontract's terms. (See Dkt. 7 at ¶ 10). Defendant allegedly fell behind on its scheduled timetable, causing Plaintiff to send a number of letters to Defendant requesting that it cure these defaults. (Id. at ¶ 12; see Dkt. 7-1 (Letter Exhibits)). On September 27, 2016, Plaintiff requested damages from Defendant for its failure to remedy its allegedly untimely performance. (Dkt. 7 at ¶ 14). In response, on October 31, 2016, Defendant filed a mechanic's lien on the subject property, which was discharged by bond. (Id. at ¶ 15).
On December 22, 2016, Defendant filed a writ of summons, without a complaint, in the Court of Common Pleas of Montgomery County, Pennsylvania, naming Plaintiff and Marist as party defendants. (Dkt. 8-2 (Writ of Summons)). Plaintiff alleges that Defendant filed this action without complying with the mediation requirements set forth in the Subcontract. (Dkt. 7 at ¶ 16). Indeed, after Plaintiff filed for mediation with the American Arbitration Association ("AAA") in March of 2017, and the AAA scheduled a preliminary mediation session, Defendant refused to proceed with mediation. (Id. at ¶¶ 23-26).
PROCEDURAL HISTORY
On May 4, 2017, Plaintiff commenced this action against Defendant in New York State Supreme Court, Monroe County, alleging causes of action for breach of contract and unjust enrichment ("NYS Action"). (Dkt. 1-1 at ¶¶ 8-13). On June 8, *3842017, Defendant filed an action in the United States District Court for the Eastern District of Pennsylvania, requesting the federal court to declare the mediation clause of the Subcontract void and unenforceable, and to enjoin Plaintiff from enforcing that clause against Defendant ("EDPA Action"). (Dkt. 8-6 at 12-13). The next day, Defendant removed the NYS Action to this Court, alleging that the Court could entertain this action on the basis of diversity jurisdiction. (Dkt. 1 at ¶ 7).2 On the same day, Defendant filed its complaint in the Court of Common Pleas of Montgomery County, Pennsylvania, alleging various causes of action, including breach of contract, unjust enrichment, misappropriation of trade secrets, and tortious interference with business relations. (Dkt. 8-4 at 10-21). Throughout the remainder of this Decision and Order, the Court will refer to the action commenced in the Court of Common Pleas of Montgomery County, Pennsylvania, as the "State Action."
On June 30, 2017, Plaintiff filed an amended complaint that expounded upon the original complaint, and alleged causes of action against Defendant that included breach of contract, unjust enrichment, and violations of the New York Lien Law. (Dkt. 7 at 6-9). On July 14, 2017, Defendant moved to dismiss or stay this action on the ground that the abstention doctrine set forth in Colo. River Water Conservation Dist. v. United States,
On October 2, 2017, Marist filed a motion to intervene in this action pursuant to Rule 24 of the Federal Rules of Civil Procedure. (Dkt. 18). Marist is represented on this motion by the same law firm that represents Plaintiff in the instant action. Not surprisingly, Plaintiff does not object to Marist's motion to intervene. However, Defendant opposes the motion. (Dkt. 22).
Oral argument was held before the undersigned on December 13, 2017, at which time the Court reserved decision on both motions.
DISCUSSION
I. Defendant's Motion to Dismiss or to Stay This Action Based on Colorado River Abstention is Denied
A. Legal Standard
"A motion to dismiss based on Colorado River is considered as a motion to dismiss for lack of subject matter jurisdiction pursuant to Rule 12(b)(1) of the Federal Rules of Civil Procedure." Stahl York Ave. Co., LLC v. City of New York, No. 14 CIV. 7665 (ER),
Free access — add to your briefcase to read the full text and ask questions with AI
ELIZABETH A. WOLFORD, United States District Judge
INTRODUCTION
This action is but one of many legal disputes currently pending between the *383parties, arising out of construction activities on property owned by Marist College ("Marist") in Poughkeepsie, New York. This dispute involves the contractual rights and obligations between plaintiff The Pike Company, Inc. ("Plaintiff") and defendant Universal Concrete Products, Inc. ("Defendant"). Plaintiff, the general contractor for the construction project, claims that Defendant, its subcontractor, materially breached the terms of the parties' subcontract and improperly encumbered the project property with a mechanic's lien that has been discharged by bond. (See Dkt. 7 at 6-9). Plaintiff seeks damages for breach of contract, unjust enrichment, and violations of the New York Lien Law, and an order invalidating and vacating the lien and bond. (Id. ).
Presently before the Court is Defendant's motion to dismiss, stay, or transfer this action (Dkt. 8), and Marist's motion to intervene as a plaintiff-intervenor (Dkt. 18). For the following reasons, Defendant's motion is denied, and Marist's motion is granted.
BACKGROUND 1
Marist, a private liberal arts college located in Poughkeepsie, New York, engaged the services of Kirchoff-Consigli Construction Management, LLC ("KCCM") to act as the general contractor for a construction project involving several buildings on Marist's campus (the "Project"). (Dkt. 18-1 at ¶ 4 (Affidavit of Justin Butwell)). Defendant acted as KCCM's subcontractor for the Project until May 4, 2015, when Marist hired Plaintiff to replace KCCM as the general contractor. (Id. at ¶¶ 5-7). On May 29, 2015, Plaintiff and Defendant entered into a subcontract to perform work on the Project (the "Subcontract"). (Id. at ¶ 8; see Dkt. 7 at ¶ 8).
Plaintiff alleges that the Subcontract contains an alternative dispute resolution clause, requiring the parties to proceed with mediation before seeking judicial recourse should a dispute arise under the Subcontract's terms. (See Dkt. 7 at ¶ 10). Defendant allegedly fell behind on its scheduled timetable, causing Plaintiff to send a number of letters to Defendant requesting that it cure these defaults. (Id. at ¶ 12; see Dkt. 7-1 (Letter Exhibits)). On September 27, 2016, Plaintiff requested damages from Defendant for its failure to remedy its allegedly untimely performance. (Dkt. 7 at ¶ 14). In response, on October 31, 2016, Defendant filed a mechanic's lien on the subject property, which was discharged by bond. (Id. at ¶ 15).
On December 22, 2016, Defendant filed a writ of summons, without a complaint, in the Court of Common Pleas of Montgomery County, Pennsylvania, naming Plaintiff and Marist as party defendants. (Dkt. 8-2 (Writ of Summons)). Plaintiff alleges that Defendant filed this action without complying with the mediation requirements set forth in the Subcontract. (Dkt. 7 at ¶ 16). Indeed, after Plaintiff filed for mediation with the American Arbitration Association ("AAA") in March of 2017, and the AAA scheduled a preliminary mediation session, Defendant refused to proceed with mediation. (Id. at ¶¶ 23-26).
PROCEDURAL HISTORY
On May 4, 2017, Plaintiff commenced this action against Defendant in New York State Supreme Court, Monroe County, alleging causes of action for breach of contract and unjust enrichment ("NYS Action"). (Dkt. 1-1 at ¶¶ 8-13). On June 8, *3842017, Defendant filed an action in the United States District Court for the Eastern District of Pennsylvania, requesting the federal court to declare the mediation clause of the Subcontract void and unenforceable, and to enjoin Plaintiff from enforcing that clause against Defendant ("EDPA Action"). (Dkt. 8-6 at 12-13). The next day, Defendant removed the NYS Action to this Court, alleging that the Court could entertain this action on the basis of diversity jurisdiction. (Dkt. 1 at ¶ 7).2 On the same day, Defendant filed its complaint in the Court of Common Pleas of Montgomery County, Pennsylvania, alleging various causes of action, including breach of contract, unjust enrichment, misappropriation of trade secrets, and tortious interference with business relations. (Dkt. 8-4 at 10-21). Throughout the remainder of this Decision and Order, the Court will refer to the action commenced in the Court of Common Pleas of Montgomery County, Pennsylvania, as the "State Action."
On June 30, 2017, Plaintiff filed an amended complaint that expounded upon the original complaint, and alleged causes of action against Defendant that included breach of contract, unjust enrichment, and violations of the New York Lien Law. (Dkt. 7 at 6-9). On July 14, 2017, Defendant moved to dismiss or stay this action on the ground that the abstention doctrine set forth in Colo. River Water Conservation Dist. v. United States,
On October 2, 2017, Marist filed a motion to intervene in this action pursuant to Rule 24 of the Federal Rules of Civil Procedure. (Dkt. 18). Marist is represented on this motion by the same law firm that represents Plaintiff in the instant action. Not surprisingly, Plaintiff does not object to Marist's motion to intervene. However, Defendant opposes the motion. (Dkt. 22).
Oral argument was held before the undersigned on December 13, 2017, at which time the Court reserved decision on both motions.
DISCUSSION
I. Defendant's Motion to Dismiss or to Stay This Action Based on Colorado River Abstention is Denied
A. Legal Standard
"A motion to dismiss based on Colorado River is considered as a motion to dismiss for lack of subject matter jurisdiction pursuant to Rule 12(b)(1) of the Federal Rules of Civil Procedure." Stahl York Ave. Co., LLC v. City of New York, No. 14 CIV. 7665 (ER),
"A plaintiff asserting subject matter jurisdiction has the burden of proving by a preponderance of the evidence that the court retains jurisdiction." Makarova v. United States ,
B. Colorado River Abstention
1. General Principles
"Abstention from the exercise of federal jurisdiction is the exception, not the rule." Colo. River Water Conservation Dist. ,
2. The State Action and this Matter are "Parallel" Proceedings
"[A] finding that the concurrent proceedings are 'parallel' is a necessary prerequisite to abstention under Colorado River ." Dittmer v. County of Suffolk ,
*386DDR Constr. Servs., Inc. v. Siemens Indus., Inc. ,
Here, Defendant argues that the instant matter and the State Action are "parallel" proceedings because "[b]oth actions involve a dispute between [Plaintiff] and [Defendant] in regard to alleged breaches of the [Subcontract] for the Marist Project." (Dkt. 8-7 at 14). Therefore, Defendant concludes, the same parties are litigating substantially the same issues in both forums. (Id. at 14-15). Plaintiff responds that the parties are not identical because "Marist College is not currently a party to this action," and that the causes of action asserted in this case are "completely different." (Dkt. 11 at 12). However, Plaintiff's argument is not persuasive.
"[T]he threshold requirement is that there be a substantial identity of parties between the state and federal actions." Aurelius Capital Master, Inc. v. MBIA Ins. Corp. ,
*387Furthermore, the issues are substantially the same between the two proceedings. Again, "absolute congruency [of assertions] is not necessary to support a finding of Colorado River parallelism." Pabco Constr. Corp. ,
Therefore, the Court concludes that the State Action and the instant matter are "parallel" proceedings for purposes of Colorado River abstention. The Court now turns to whether the Colorado River factors weigh in favor of or against the exercise of federal jurisdiction.
3. The Colorado River Factors Weigh in Favor of Federal Jurisdiction
"After determining that the state and federal proceedings are parallel, the question becomes whether the court should exercise its discretion to abstain." Phillips v. Citibank, N.A.,
the court should consider (1) whether the controversy involves a res over which one of the courts has assumed jurisdiction; (2) whether the federal forum is less inconvenient than the other for the parties; (3) whether staying or dismissing the federal action will avoid piecemeal litigation; (4) the order in which the actions were filed, and whether proceedings have advanced more in one forum than in the other; (5) whether federal law provides the rule of decision; and (6) whether the state procedures are adequate to protect the plaintiff's federal rights.
Woodford v. Cmty. Action Agency of Greene Cty., Inc. ,
a. Jurisdiction Over Res
Both parties contend that this action does not entail the exercise of judicial jurisdiction over property. (Dkt. 8-7 at 18; Dkt. 11 at 14). "[T]he absence of a res 'point[s] toward exercise of federal jurisdiction.' " Vill. of Westfield v. Welch's ,
b. Forum Convenience
Defendant also concedes that neither "forum [is] dramatically more convenient," and characterizes this factor as "neutral." (Dkt. 8-7 at 18). The Second Circuit has "held that where the federal court is 'just as convenient' as the state court, that factor favors retention of the case in federal court." Vill. of Westfield,
Therefore, the Court concludes that the second factor weighs in favor of federal jurisdiction.
c. Avoidance of Piecemeal Litigation
"[T]he primary context in which [the Second Circuit] ha[s] affirmed Colorado River abstention in order to avoid piecemeal adjudication has involved lawsuits that posed a risk of inconsistent outcomes not preventable by principles of res judicata and collateral estoppel." Woodford ,
Here, the State Action names Marist as a defendant, but Marist is not a named party in the instant federal action. Accordingly, "the state action is more comprehensive, because it involves defendants not present in the federal action[, and thus, there is] ... some risk of inconsistent result[s]." In re Asbestos Litig. ,
The Court notes that the importance of this factor is also lessened by the fact that Marist has moved to intervene in the present action. (Dkt. 18). As will be discussed below, Marist maintains "a claim or defense that shares with the main action a common question of law or fact," Fed. R. Civ. P. 24(b)(1)(B), and will be permitted to intervene in this action. See Gonzalez v. Cruz ,
Therefore, the Court finds that this factor weighs in favor of abstention, but, on balance, that it carries only modest weight. See Mazuma Holding Corp. v. Bethke ,
d. Order of Filing and Progress of Proceedings
The jurisdictional priority factor "is to be applied in a pragmatic, flexible manner with a view to the realities of the case at hand. Thus, priority should not be measured exclusively by which complaint was filed first, but rather in terms of how much progress has been made in the two actions." Moses H. Cone Mem'l Hosp. ,
As of August 11, 2017, at the time Defendant filed its reply papers on this motion, the State Action had not proceeded any further than the instant matter. (Dkt. 14 at 6). During the motion hearing held on December 13, 2017, counsel for Plaintiff and Defendant informed the Court that the status of the State Action had not advanced. Although Defendant argues that this factor weighs in favor of abstention, Defendant's rationale is contrary to the basic tenet that "[a]bstention from the exercise of federal jurisdiction is the exception, not the rule." Colo. River Water Conservation Dist. ,
Since the parallel actions have proceeded at relatively the same pace, the fact that the State Action was filed before this action has little impact on the Court's analysis of this factor. Moreover, while the State Action was technically filed on December 22, 2016, by a writ of summons (Dkt. 8-2), the complaint was not subsequently filed until June 9, 2017 (Dkt. 8-4)-some five-and-a-half months later-which was one day after Plaintiff filed the present action in New York State Supreme Court. (Dkt. 1-1 at 1-6). Therefore, the Court concludes that the fourth factor counsels against abstention.
e. The Source of Substantive Law
"When the applicable substantive law is federal, abstention is disfavored, though the inverse proposition will not alone support a surrender of federal jurisdiction." De Cisneros ,
Defendant argues that the fifth factor weighs in favor of abstention because the source of substantive law in this action will likely be New York State law, and that Pennsylvania law will govern claims six and seven of the State Action.
*391(Dkt. 8-7 at 17). Defendant also contends that its misappropriation of trade secrets claim in the State Action "presents a complex and novel question of Pennsylvania law." (Id. ). "State law provides the rule of decision in all diversity cases, and the source-of-law factor has more influence when a federal rule of decision is involved; only in some rare circumstances [may] the presence of state law issues ... weigh in favor of ... surrender of federal jurisdiction." Bethlehem Contracting Co. ,
"In cases involving only routine issues of state law, which federal district courts are fully capable of deciding, there are no such rare circumstances." Smehlik v. Athletes & Artists, Inc. ,
Therefore, the Court finds that the fifth factor weighs in favor of federal jurisdiction.
f. Whether the State Court Will Adequately Protect the Parties' Interests
"In analyzing the sixth factor in the special circumstances test, federal courts are to determine whether the 'parallel state-court litigation will be an adequate vehicle for the complete and prompt resolution of the issues between the parties.' " Vill. of Westfield ,
The Court does not agree with Plaintiff that the State Action is proceeding at a prejudicially slow pace. Cf. Vill. of Westfield ,
Thus, it is the Court's view that the "[a]voidance of piecemeal litigation is perhaps the only Colorado River factor that weighs in favor of abstention. That is not enough, however, to warrant abstention in light of the fact that all other factors weigh heavily in favor of the retention of jurisdiction." In re Comverse Tech., Inc. Derivative Litig. , No. 06-CV-1849 (NGG) (RER),
II. Defendant's Alternative Request to Transfer this Action to the Eastern District of Pennsylvania is Denied
Defendant further argues that should this Court decline to dismiss or to stay this action under the Colorado River doctrine, the Court should transfer the action to the United States District Court for the Eastern District of Pennsylvania under the first-to-file rule. (Dkt. 8-7 at 18-20). Specifically, Defendant contends that because it commenced the EDPA Action on June 8, 2017-one day before the instant action was removed to federal court-Plaintiff's complaint should be transferred. Plaintiff responds that Defendant cannot invoke the first-to-file rule because the EDPA Action was improperly filed in anticipation of this removal action as a manipulative tactic. (Dkt. 11 at 23-24). Plaintiff also urges this Court to consider the date it filed the instant action in New York State Supreme Court, rather than the date the action was removed to federal court, in applying the first-to-file rule. (Id. at 24).
It is well-established in this Circuit that "[w]here there are two competing lawsuits, the first suit should have priority, absent the showing of balance of convenience ... or ... special circumstances ... giving priority to the second." First City Nat. Bank & Tr. Co. v. Simmons ,
Defendant's argument for the application of the first-to-file rule lacks merit. Defendant filed the EDPA action-which asks the court to declare the Subcontract as void and unenforceable, and to enjoin Plaintiff from enforcing it-just one day before the NYS Action was removed to this Court. (Dkt. 8-6; see Dkt. 1). Moreover, it was Defendant, not Plaintiff, who invoked federal jurisdiction by filing a notice *393of removal. (Dkt. 1). These facts suggest that Defendant engaged in gamesmanship in an attempt to manipulate the choice of forum. Given the equitable nature of the first-to-file doctrine, the Court finds Defendant's assertions unpersuasive. See generally AEI Life, LLC v. Lincoln Ben. Life Co. ,
In any event, the Court need not determine whether Defendant's conduct constitutes the type of "special circumstances" that warrant granting priority to the second-filed action. Instead, the Court agrees with Plaintiff that the appropriate benchmark for determining which case was filed first is the date the action was commenced in state court, not the date of removal. See MacDermid Printing Sols., LLC v. E.I. Du Pont De Nemours & Co. , No. 3:15-CV-00320 (MPS),
Here, Defendant's EDPA Action was filed on June 8, 2017. (Dkt. 8-6). However, Plaintiff's NYS Action was filed on May 4, 2017. (See Dkt. 1-1 at 1-6; Dkt. 8-7 at 15 (stating the same)); see generally CPLR 304(a) ("An action is commenced by filing a summons and complaint or summons with notice in accordance with rule twenty-one hundred two of this chapter."). Accordingly, as between the instant lawsuit and the EDPA Action, this action is the first-filed matter for purposes of the first-to-file rule, and Defendant's request to transfer this action to the Eastern District of Pennsylvania is denied.
Therefore, for the foregoing reasons, Defendant's motion (Dkt. 8) is denied in its entirety.
III. Marist's Application for Permissive Intervention is Granted
"A district court may grant a motion for permissive intervention if the application is timely and if the 'applicant's claim or defense and the main action have a question of law or fact in common.' " In re Holocaust Victim Assets Litig.,
Additional relevant factors "include the nature and extent of the intervenors' interests," the degree to which those interests are "adequately represented by other parties," and "whether parties seeking intervention will significantly contribute to [the] full development of the underlying factual issues in the suit and to the just and equitable adjudication of the legal questions presented."
Diversified Grp., Inc. v. Daugerdas,
B. Timeliness of the Motion
Here, Defendant's sole argument in opposition to Marist's request for permissive intervention is that the motion is untimely. (Dkt. 22 at 18-19). "The timeliness requirement is flexible and the decision is one entrusted to the district judge's sound discretion." United States v. Yonkers Bd. of Educ. ,
At oral argument, Marist's counsel could not pinpoint exactly when Marist became aware of the possibility that Plaintiff would file the present action. However, counsel did not believe that Marist became aware of this action prior to the date that Plaintiff filed its complaint in New York State Supreme Court on May 4, 2017. Defendant speculates that Marist could have developed an awareness of this action before May 2017, based upon the fact that the same law firm represents Marist and Plaintiff. (Dkt. 22 at 13). Defendant offers no concrete support for this assertion. As such, the Court finds that Marist was on notice of Plaintiff's action for about five months before it decided to file a motion to intervene on October 2, 2017. (Dkt. 18). Although Marist does not provide any substantive explanation for this delay, the Court, nevertheless, finds Marist's motion to intervene as timely filed.
Although some courts have found comparable or even shorter filing delays as untimely, see, e.g., NAACP v. New York,
*395S.E.C. v. Credit Bancorp, Ltd., No. 99 CIV. 11395 (RWS),
Although the passage of time must be considered by a court in determining the timeliness of the motion, "the mere lapse of time does not render a motion to intervene untimely." United States v. Int'l Bus. Machs. Corp.,
Here, Plaintiff does not oppose this motion, and thus, does not assert that it will suffer any prejudice as a result of the five-month delay. Notably, although Defendant opposes Marist's motion, Defendant also does not argue that it will be prejudiced by this delay. Instead, Defendant characterizes the five-month passage of time as dilatory in and of itself. (See Dkt. 22 at 11-13, 18-19). "This argument, however, speaks to [Defendant]'s preference to avoid intervention in general and does not claim specifically that the timing of this motion has caused it prejudice. " Allco Fin. Ltd. v. Etsy,
Defendant also relies upon the Second Circuit's decision in MasterCard Int'l Inc. v. Visa Int'l Serv. Ass'n, Inc.,
Accordingly, in viewing the five-month delay against the surrounding circumstances, the Court finds that this motion was timely filed. Marist filed this motion just five months after the commencement of this action in New York State Supreme Court, four months after the removal of the NYS Action to federal court, and about three months after the filing of the amended complaint. "Given the leniency with which [courts in this Circuit have] treated the requirement of timeliness," Cook v. Pan Am. World Airways, Inc.,
C. Common Questions of Law or Fact
Marist must also demonstrate that it "has a claim or defense that shares with the main action a common question of law or fact." Fed. R. Civ. P. 24(b)(1)(B). "However, '[t]he words claim or defense [in permissive intervention] are not to be read in a technical sense, but only require some interest on the part of the applicant.' " Louis Berger Grp., Inc. v. State Bank of India,
Therefore, the Court finds that Marist maintains a claim "that shares with the main action a common question of law or fact." Fed. R. Civ. P. 24(b)(1)(B).
*397D. The Absence of Undue Delay or Prejudice and the Inadequacy of Representation
Notably absent from Defendant's submissions is any argument that the intervention requested would "unduly delay or prejudice the adjudication of the rights of the original parties." See Fed. R. Civ. P. 24(b)(3) ; Brennan,
In addition, the Court questions whether Plaintiff would adequately represent Marist's interests in this matter. " 'Rule 24(b) does not list inadequacy of representation as one of the considerations for the court' in exercising its discretion under Rule 24(b) and although a court may consider it, 'it is clearly a minor factor at most.' " Allco Fin. Ltd. ,
Therefore, the Court exercises its discretion in granting Marist's request for permissive intervention under Rule 24(b)(1)(B). Accordingly, the Court "need not determine whether intervention as of right under Rule 24(a) is warranted." Int'lDesign Concepts, LLC,
CONCLUSION
For the foregoing reasons, Defendant's motion to dismiss, stay, or transfer this action (Dkt. 8) is denied, and Marist's motion to intervene (Dkt. 18) is granted.
SO ORDERED.
Related
Cite This Page — Counsel Stack
284 F. Supp. 3d 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pike-co-v-universal-concrete-prods-inc-nywd-2018.