Pietz v. Orthopedic Equipment Co., Inc.

562 So. 2d 152, 1989 WL 162219
CourtSupreme Court of Alabama
DecidedDecember 22, 1989
Docket88-908
StatusPublished
Cited by17 cases

This text of 562 So. 2d 152 (Pietz v. Orthopedic Equipment Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pietz v. Orthopedic Equipment Co., Inc., 562 So. 2d 152, 1989 WL 162219 (Ala. 1989).

Opinions

Harold Walter Pietz, a student at Jacksonville State University, was injured when he fell during an ROTC field exercise on November 16, 1985. The Jacksonville State ROTC unit was required to rappel down a cliff, using equipment issued by the ROTC unit. Part of this equipment was the snap link mountain piton (a/k/a a carabiner) manufactured by Orthopedic Equipment Company, Inc. ("OEC"), a wholly-owned subsidiary of Biomet, Inc. As Pietz descended a steep cliff, the non-locking gatekeeper portion of the snap link opened, causing the rope to slacken and Pietz to free fall approximately 80 feet along the rock ledge. Pietz was severely injured in this fall.

Pietz filed suit against OEC under the Alabama Extended Manufacturer's Liability Doctrine, alleging defects in the design of the snap link. The complaint was amended to add F.I. Saemann Enterprises, Inc., and Biomet, Inc., as defendants. All three defendants filed motions for summary judgment, contending that the snap link was designed by the Federal Government and claiming immunity from liability for any design defects, under the government *Page 154 contractor defense doctrine. The motions were originally heard by the trial judge on October 6, 1988. Summary judgment was entered in favor of F.I. Saemann Enterprises, Inc., at that time. The trial judge suggested that he certify the government contractor defense issue for Ala.R.App.P. Rule 5 review. However, after an attempt by the defendants to move the cases to the United States District Court and a remand of the case to state court, the trial judge heard the motions and entered summary judgment on behalf of OEC and Biomet on March 30, 1989. Pietz appeals from this judgment.

The issues before us are: (1) whether the trial judge erred in entering summary judgment based on the government contractor defense as set forth in Boyle v. United Technologies Corp.,487 U.S. 500, 108 S.Ct. 2510, 101 L.Ed.2d 442 (1988), and (2) whether Biomet is a "successor in interest" to OEC.

The government contractor defense originated in the case ofYearsley v. W.A. Ross Construction Co., 309 U.S. 18,60 S.Ct. 413, 84 L.Ed. 554 (1940). The Yearsley case involved a government contractor who built some river dikes for the government; the work caused erosion on land adjacent to the dikes. The United States Supreme Court stated, "[I]f [the] authority to carry out the project was validly conferred, that is, if what was done was within the constitutional power of Congress, there is no liability on the part of the contractor for executing its will." Id. at 20-21, 60 S.Ct. at 414-415. Two later cases created the Feres-Stencel doctrine, which were followed until Boyle. See, Feres v. United States,340 U.S. 135, 71 S.Ct. 153, 95 L.Ed. 152 (1950), and Stencel AeroEngineering Corp. v. United States, 431 U.S. 666,97 S.Ct. 2054, 52 L.Ed.2d 665 (1977).

In Boyle, the United States Supreme Court reviewed the various government contractor defenses utilized by the circuit courts of appeals. The issue before the Boyle Court was whether a contractor providing military equipment to the Federal Government could be held liable under state tort law for injury resulting from a design defect. Boyle created a new government contractor defense and enunciated a three-part test:

"Liability for design defects in military equipment cannot be imposed, pursuant to state law, when (1) the United States approved reasonably precise specifications; (2) the equipment conformed to those specifications; and (3) the supplier warned the United States about the dangers in the use of the equipment that were known to the supplier but not to the United States."

487 U.S. 500 at 512, 108 S.Ct. 2510 at 2518.

The Supreme Court makes it clear in Boyle that whether the facts of the case establish the condition for the defense is a question for the jury. The Court, in remanding the case, wrote:

"It is somewhat unclear from the Court of Appeals' opinion, however, whether it was in fact deciding that no reasonable jury could, under the properly formulated defense, have found for the petitioner on the facts presented, or rather was assessing on its own whether the defense had been established. The latter, which is what the petitioner asserts occurred, would be error since whether the facts establish the conditions for the defense is a question for the jury."

487 U.S. 500 at 514, 108 S.Ct. 2510 at 2519 (emphasis added).

Further, the Supreme Court in Boyle cautioned that it was not suggesting that state law would generally be pre-empted by the government contractor defense. To illustrate, the Court used two examples:

"If, for example, the United States contracts for the purchase and installation of an air conditioning unit, specifying the cooling capacity but not the precise manner of construction, a state law imposing upon the manufacturer of such units a duty of care to include a certain safety feature would not be a duty identical to anything promised the government but neither would it be contrary. The contractor could comply with both its contractual obligations and the state-prescribed duty of care. No one suggests *Page 155 that state law would generally be pre-empted in this context."

Id., 487 U.S. at 509, 108 S.Ct. at 2516 (emphasis added). The second example given by the Supreme Court was as follows:

"If, for example, a federal procurement officer orders, by model number, a quantity of stock helicopters that happen to be equipped with escape hatches opening outward, it is impossible to say that the government has a significant interest in that particular feature. That would be scarcely more reasonable than saying that a private individual who orders such a craft by model number cannot sue for the manufacturer's negligence because he got precisely what he ordered."

Id., 487 U.S. at 509, 108 S.Ct. at 2516.

Thus, it is clear that the question of whether a government contractor is to be shielded from liability becomes a question for the jury to weigh. It is also clear that the threshold question is whether the equipment is indeed "military equipment."

In the present case, the trial judge entered summary judgment for OEC and Biomet.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parrett Trucking, Inc. v. Telecom Solutions, Inc.
989 So. 2d 513 (Supreme Court of Alabama, 2008)
Isaacson v. Dow Chemical Co.
304 F. Supp. 2d 404 (E.D. New York, 2004)
In Re" Agent Orange" Product Liability Lit.
304 F. Supp. 2d 404 (E.D. New York, 2004)
Budrow v. Ames, No. Cv97-0572408 (Jun. 10, 1998)
1998 Conn. Super. Ct. 9848 (Connecticut Superior Court, 1998)
Budrow v. Ames, No. Cv 97 0572408 (June 10, 1998)
1998 Conn. Super. Ct. 7193 (Connecticut Superior Court, 1998)
Andrew v. Unisys Corp.
936 F. Supp. 821 (W.D. Oklahoma, 1996)
In Re Catfish Antitrust Litigation
908 F. Supp. 400 (N.D. Mississippi, 1995)
Asher v. KCS Intern., Inc.
659 So. 2d 598 (Supreme Court of Alabama, 1995)
Mary Carley v. Wheeled Coach
991 F.2d 1117 (Third Circuit, 1993)
In Re Chateaugay Corp.
146 B.R. 339 (S.D. New York, 1992)
Brown v. Economy Baler Co.
599 So. 2d 1 (Supreme Court of Alabama, 1992)
Hanks v. Courtesy Ford Sales, Inc.
574 So. 2d 731 (Supreme Court of Alabama, 1990)
Pietz v. Orthopedic Equipment Co., Inc.
562 So. 2d 152 (Supreme Court of Alabama, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
562 So. 2d 152, 1989 WL 162219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pietz-v-orthopedic-equipment-co-inc-ala-1989.