Phœnix Tempe Stone Co. v. De Waard

20 F.2d 757, 1927 U.S. App. LEXIS 2635
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 27, 1927
DocketNo. 4971
StatusPublished
Cited by5 cases

This text of 20 F.2d 757 (Phœnix Tempe Stone Co. v. De Waard) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phœnix Tempe Stone Co. v. De Waard, 20 F.2d 757, 1927 U.S. App. LEXIS 2635 (9th Cir. 1927).

Opinion

GILBERT, Circuit Judge

(after stating the facts as above). The defendant contends that the plaintiffs’ complaint fails to state a eanáe of action, that the demurrer thereto should have been sustained, and it argues that, although the complaint alleges certain breaches of the subcontract in connection with the extra work claimed to have been performed by the plaintiffs, the facts thereafter pleaded show that the plaintiffs waived any prior breach on the part of the defendant. It is true that the complaint indicates that after the alleged breaches negotiations were continued between the parties with a view to complete performance, but it also shows that the defendant, after refusing to pay for the extra work, notified the plain[759]*759tiffs that it was going to take over and perform the'contract itself. The case stated is not, therefore, one of a subcontractor abandoning the work on the failure of the contractor to pay an installment due under the contract. The facts pleaded bring the case within the rule that, where an' act of the defendant renders complete performance of the contract impossible, the plaintiff may treat the act as a discharge from further performance, and may claim compensation for what has been done, and the damages which have been sustained. 3 Elliott on Contracts, 218; United States v. Behan, 110 U. S. 338, 4 S. Ct. 81, 28 L. Ed. 168. The case of Greenlee County v. Cotey, 17 Ariz. 542, 155 P. 302, relied upon by the defendant, is not authority to the contrary.

Error is assigned to certain instructions to the jury concerning the question of the conflict between the line of bedrock as shown by the plans and specifications, and the line thereof as it was proven actually to have existed, and the extra work which the plaintiffs contended that they were required to perform in addition to that shown by the plans and specifications. The court charged that the plans and specifications were a part of the contract, and that they specified the depth at which bedrock would be found, and amounted to a positive statement, which must be taken as true and binding upon the defendant; that the provision in the contract that the cylinders should be sunk to bedrock did not take precedence over the plans which showed the depth at which bedrock would be encountered; that under the contract the defendant had no right to require the plaintiffs to do extra work without written authorization therefor by the state engineer; that under the provision of the contract “that the contractor has by careful examination satisfied himself as to the intent of the specifications and plans,” etc., the plaintiffs were not required to make an independent investigation to determine whether or not bedrock was to be found at the depth shown; and that the delineation of the line of bedrock constituted a representation upon which the plaintiffs had the right to rely without investigation.

We find no error in those instructions. Hollerbach v. United States, 233 U. S. 165, 34 S. Ct. 553, 58 L. Ed. 898; Christie v. United States, 237 U. S. 234, 35 S. Ct. 565, 59 L. Ed. 933; United States v. Spearin, 248 U. S. 132, 137, 39 S. Ct. 59, 63 L. Ed. 166. In the case last cited the court said: “But the insertion of the articles prescribing the character, dimensions, and location of the sewer imported a warranty that, if the specifications were complied with, the sewer would be adequate. This implied warranty is not overcome by the general clauses requiring the contractor to examine the site, to check up the plans, and to assume responsibility for the work until completion and acceptance.” In United Const. Co. v. Town of Haverhill, N. H. (C. C. A.) 9 F.(2d) 538, it was held that, if the plans and specifications for a bridge were a representation as to the character of the foundation at a depth specified therein, the contractor was excused by misrepresentation from performance of its promise to excavate to a solid ledge. The responsibility of the defendant was not overeóme by the failure of the plaintiffs to inform themselves of the actual conditions, where those conditions differed materially from the requirements of the plans and specifications. Spearin v. United States, 248 U. S. 132, 136, 39 S. Ct. 59, 63 L. Ed. 166. The case is not one of those in which the plans and specifications are not intended to show the facts, leaving the bidder to ascertain for himself the nature and quantity of the work contemplated. Here there was nothing to give .the plaintiffs warning that the plans might not bo accurate, and nothing to advise them that the representations made thereby were not intended to amount to a guaranty upon which they might malic their bids. It is doubtless true, as one of the plaintiffs testified, that “no contractor in the world” can be found who will make a bid on a bridge that does not show the depth of the foundation.

The writer hereof submits that the view of the majority of the court on the foregoing feature of the case ignores the theory on which the ease was tried in the court below. The defendant made no contention that the question was one for the jury. Its position throughout the trial was that the question was one of law. It took no exception to the court’s instructions on the ground that it should have been submitted to the jury, and it made no request that it be submitted to the jury. The sole ground of its exception was that it was not a fact that the plans showed the depth at which bedrock would be found, “and for the further reason that the true construction of the special provision is that the cylinders must be sunk to the actual bedrock and not to a bedrock assumed to exist by the plans.” Again it said: “The plans received in evidence in the cause do not show any definite line for bedrock for the bottom [760]*760of the cylinders, and for that reason the plaintiffs were obliged to put the cylinders down to actual bedrock at all events.” In brief, the only exception they took to the instruction was an unsustainable one.

The defendant contends that it was entitled to an instructed verdict on the ground that, if any breaches of the contract were made by the defendant through its failure to obtain authority for the extra work, the plaintiffs thereafter elected to proceed with the contract, and thereby they waived said breaches, and their subsequent failure to carry on the work with sufficient dispatch gave the defendant the right to take over the completion thereof. The contention assumes as a conclusion of law that there was a waiver. To this it is to be said that whether in any case there has been a waiver is generally a question of fact, and the sufficiency of the evidence to establish it is for the jury. 12 R. C. L. 912. There is lack of evidence here to show a waiver. When the plaintiffs on October 4, 1924, wrote to the defendant, directing its attention to the extra work which confronted them, it is obvious that they hoped for an amicable adjustment of the difficulty, and the record shows that the matter was the subject of negotiation for several weeks thereafter. On October 18, 1924, the plaintiffs again wrote, directing the defendant’s attention to the extra work rendered • necessary by the misrepresentation found in the plans, and expressing the hope that the defendant could make arrangement with the highway engineer for an allowance for extra work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dale v. Preg
204 F.2d 434 (Ninth Circuit, 1953)
United States v. Lundstrom
139 F.2d 792 (Ninth Circuit, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
20 F.2d 757, 1927 U.S. App. LEXIS 2635, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phnix-tempe-stone-co-v-de-waard-ca9-1927.