Phillips v. American Liability & Surety Co.

162 A. 435, 309 Pa. 1, 1932 Pa. LEXIS 660
CourtSupreme Court of Pennsylvania
DecidedApril 13, 1932
DocketAppeal, 46
StatusPublished
Cited by11 cases

This text of 162 A. 435 (Phillips v. American Liability & Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips v. American Liability & Surety Co., 162 A. 435, 309 Pa. 1, 1932 Pa. LEXIS 660 (Pa. 1932).

Opinion

Opinion by

Mr. Justice Drew,

Henry DePamphilis, one of the defendants in this case, entered into a contract with the plaintiff, Carnig Phillips, for the erection of an addition to plaintiff’s dry-cleaning plant, and gave a bond to protect plaintiff from any default in the completion of the work, with the other defendant, American Liability & Surety Company, as surety. DePamphilis failed to finish the building, and the surety declined to do so, whereupon Phillips proceeded to complete the work himself. He then sued the principal and surety on the bond, claiming as damages $5,201.27 as the cost of completing the building over and above the contract price, and $1,155.00 for the delay caused by DePamphilis’s failure to finish the work within the time specified by the contract. From judgment on the verdict for plaintiff in the full amount of his claim, the defendant surety appealed.

By the contract between DePamphilis and plaintiff, payments on the contract price of $11,550.00 were to be made as follows: “Eighty-five (85%) per cent of the value, proportionate to the amount of the contract, of materials delivered on the job shall be paid every thirty *4 days upon, the proper vouchers for materials furnished by the inspector, or the architect, if any be employed, and shall be due not later than ten days from the receipt by the architect, if any be employed, or the inspector, of the proper vouchers.” Payments on account of labor were to be made in the same way every two weeks. However, in no event were these payments during the progress of the work to exceed 85% of the contract price, the balance being withheld until the building was completed. It was further provided in the contract that “Cessation of work on the job by the contractor [DePamphilis] or upon failure of the contractor to have a sufficient number of skilled workmen on the job according to its size for a period of four continuous days, then the owner [Phillips] at his option may declare the contract broken and proceed with the finishing of the work at the expense of the contractor.”

The bond provided, inter alia, that Phillips, the obli-gee, should faithfully perform all the terms of his contract with DePamphilis, and should retain the portion of the contract price therein stipulated, that the obligation of the surety should be construed “strictly as one of suretyship only,” that the surety should not be liable for any damage caused by delay in excess of 10% of the penalty of the bond, or $1,155.00, and that, if DePam-philis failed to finish the building, the surety might, at its option, do so. In the event of a default by DePam-philis it was required in the bond that “A written statement of the particular facts showing such default and the date thereof shall be delivered to the surety by registered mail......promptly and in no event later than ten days after the obligee......shall become aware of such default.”

DePamphilis began work under the contract June 3, 1929. One Kraus, a man of experience in the building trade, acted as inspector, on behalf of Phillips and the Easton Trust Company, which was financing the erection of the building. Prom time to time DePamphilis *5 would submit statements of the amounts expended by him on payrolls to Kraus, who would then estimate the proportion of the work completed and the value of the materials delivered on the job. From this data he calculated the sum which, in his opinion, DePamphilis ought to receive as a payment on the contract price, setting that amount as 85% of the estimated value of materials furnished on the job plus a like proportion of the payroll, and gave a voucher so certifying to Phillips, who then paid DePamphilis. Phillips testified that he had made no payments, not even those of October 5th and October 19th, unless Kraus had given a voucher so authorizing, but Kraus said he did not recall signing any vouchers after October 1, 1929. DePamphilis was then in financial difficulties, and had trouble meeting his payrolls; consequently he was unable to keep workmen on the job, and the building progressed haltingly after October 1st. In order to prevent cessation of the work, Phillips made two other payments, without vouchers, on October 4th and October 13th, one to a ma-terialman who refused to extend credit to DePamphilis for bricks to be used in the construction, the other to bricklayers who threatened to tie up the job unless they were paid. Kraus refused to sign any more vouchers, because almost 85% of the contract price had been paid. DePamphilis was unable to secure funds, and finally abandoned the job. Kraus testified that the last work was done about October 12th; Phillips, DePamphilis, and two of the latter’s workmen testified that the last work was done on October 26th. In all, Phillips paid $9,536.40 toward the contract price before DePamphilis defaulted. There was considerable variance in the testimony as to the proportion of the work completed when DePamphilis quit, the estimates given by different witnesses ranging from 60% to 90%.

On October 18th, plaintiff, by his attorney, informed the surety by registered mail, “that the contractor is not faithfully complying with the terms of his contract, and *6 ......it appears that if conditions are permitted to continue the contractor will be unable to complete this work.” Other letters were sent on the 21st and 28th of the month. Following tbe letter of October 18th, W. A. Doody, general counsel for the appellant and manager of its surety department, on October 25, 1929, had an interview with Phillips and his attorney. Doody suggested that Phillips pay the balance of the contract price to DePamphilis to enable him to go on with the work, the surety waiving its right to demand retention of this sum, but this Phillips declined to do. Doody then proposed that the company would itself undertake the completion of the work, if plaintiff would waive his right to damages for delay, but this suggestion was also refused. However, Doody agreed to have a contractor look over the job before the company would exercise its option to finish the work. Accordingly, one Drake, a construction engineer, examined the unfinished building and made an estimate, to which he testified, that the job could be completed for $4,264.77. On November 2d, no workmen having appeared for five consecutive days, Phillips exercised the option reserved to him to declare the contract broken, and his attorney sent notice to this effect to the surety. This was the first and only instance when the facts permitted Phillips to declare a default under the terms of the contract. He acted promptly and within the time limit provided in the bond. Appellant, however, declined to go on with the building, and on November 11, 1929, Phillips undertook its completion, notifying the surety of this step. Because of uncertainty as to just how much work remained to be done, he was unable to secure bids for the job. The contractor employed was therefore paid on the basis of cost of materials and labor plus 10%, receiving in all $7,214.87. This sum, together with that paid DePamphilis, was $5,201.27 above the contract price, and it was for this added expense that plaintiff sued.

*7 The learned trial judge charged that, as a matter of law, Phillips gave appellant the notice of DePamphilis’s default called for by the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Balboa Insurance v. Fulton County
251 S.E.2d 123 (Court of Appeals of Georgia, 1978)
Travelers Indemnity Co. v. Rexnord, Inc.
389 A.2d 246 (Commonwealth Court of Pennsylvania, 1978)
First National Bank v. Daulerio
54 Pa. D. & C.2d 348 (Montgomery County Court of Common Pleas, 1972)
Veneto v. McCloskey & Co.
128 N.E.2d 337 (Massachusetts Supreme Judicial Court, 1955)
Plummer v. Wilson
185 A. 311 (Supreme Court of Pennsylvania, 1936)
McClelland v. New Amsterdam Casualty Co.
185 A. 198 (Supreme Court of Pennsylvania, 1936)
McClelland v. New Amsterdam Casualty Co.
23 Pa. D. & C. 597 (Philadelphia County Court of Common Pleas, 1935)
Ohlinger v. Maidencreek Township
167 A. 882 (Supreme Court of Pennsylvania, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
162 A. 435, 309 Pa. 1, 1932 Pa. LEXIS 660, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-v-american-liability-surety-co-pa-1932.