Hastings Land Improvement Co. v. Empire State Surety Co.

156 A.D. 258, 141 N.Y.S. 417, 1913 N.Y. App. Div. LEXIS 9126
Appellate Division of the Supreme Court of the State of New York·Decided April 18, 1913·Published·Cited by 2 cases

Opinion

Scott, J.:

The plaintiff made a contract with the O’Connor-McIntire Company for certain work to be done by the latter in paving streets and constructing sidewalks and gutters. The work was to be fully performed for a lump sum of $11,000, and was to be completely finished by the 1st day of November, 1909. The contract contained the following clause: (4) Payments will be made monthly upon proper certificate of the Superintendent of the amount of work done to the extent of eighty per cent of the amount of said certificate, and the said party of the second part hereby agrees that the certificate of the said superintendent that the work has been faithfully performed in accordance with the requirements of the contract and these specifications herein contained,. shall be a condition precedent to the right of the said party of the second part to payment for the entire work or any part thereof due it under this agreement, and the said party of the second part further agrees that twenty per cent of the amount due under any certificate under this agreement shall be retained by the party of the first part from the amount due to the said party of the second part at the time of making such payment.”

It was provided that if the contractor should abandon the work or in any way violate any of the conditions of the contract, the plaintiff might notify said contractor to discontinue all work or any part thereof, and that thereupon the plaintiff might; complete the work itself at the expense of the contractor who bound itself and its bondsmen to pay to plaintiff the surplus cost, if any, incurred by said plaintiff over and above the amount agreed to be paid to said contractor for doing the work. The defendant entered upon an undertaking to plaintiff conditioned that the said contractor would faithfully per[260] form the said contract on its part. There were certain conditions attached to the obligation of the surety, one of which was that plaintiff should “retain not less than fifteen per centum (15%) of all payments for work performed and materials furnished in the performance of said contract until the complete performance ” thereof by the contractor.

The contractor found some difficulty in obtaining sufficient money or credit to carry on the work according to the terms of the contract and on October 27, 1909, a supplementary or amendatory contract was entered into whereby plaintiff agreed to pay for labor and materials to be employed and furnished by the contractor, the amounts so paid to be pro tanto in lieu -of the monthly payments provided to be paid to the contractor under the original contract. It was further provided that these payments for labor and materials should be so limited that the total amount thereof per month, together with the payments to be made monthly upon the proper certificate of the superintendent, as provided for by the original contract should not exceed eighty per cent of the said certificate as therein provided. “The intention being (so reads; the contract) that the amount of the monthly payments may be reduced by the amount paid by the party of the . first part for necessary labor and materials as herein provided. ” This supplementary and amendatory contract was formally consented to by the defendant on October 29, 1909?. . The plaintiff continued to pay for labor and materials under this last agreement until December 7, 1909, when it found it could pay no more without paying in excess of eighty ;per cent of the value of the work done, whereupon it notified the contractor to this effect, and further notified him that he must place more men upon the job and push the work rapidly, and that failure to do so would be considered an abandonment of the contract. Ho response was made by the contractor and no further effort made by him to proceed with the work.." The answer admits that defendant was duly notified of the -contractor’s default, but defendant made no attempt to avail itself of the provision of the undertaking authorizing it to proceed with the completion of- the work.

The plaintiff did proceed with ■ and complete the work, expending, including the amounts paid under the original and [261] supplementary contracts, a sum exceeding by over $4,000 the agreed contract price. It has recovered a judgment against defendant for the sum of $3,000 with interest, the amount of the undertaking.

The answer as amended at the trial consists of formal denials on information and belief of parts of the complaint, and of a separate defense that the plaintiff and the O’Connor-McIntire Company made substantial changes in the original contract, and the work done and to be done thereafter without the knowledge or consent of the defendant. No evidence was offered to support this separate defense.

Free access — add to your briefcase to read the full text and ask questions with AI

Hastings Land Improvement Co. v. Empire State Surety Co., 156 A.D. 258, 141 N.Y.S. 417, 1913 N.Y. App. Div. LEXIS 9126 (N.Y. Ct. App. 1913).

156 A.D. 258 (Hastings Land Improvement Co. v. Empire State Surety Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Phillips v. American Liability & Surety Co.
162 A. 435 (Supreme Court of Pennsylvania, 1932)
British American Tobacco Co. v. United States Fidelity & Guaranty Co.
177 A.D. 582 (Appellate Division of the Supreme Court of New York, 1917)