McClelland v. New Amsterdam Casualty Co.

23 Pa. D. & C. 597, 1935 Pa. Dist. & Cnty. Dec. LEXIS 170
CourtPennsylvania Court of Common Pleas, Philadelphia County
DecidedJune 28, 1935
Docketno. 11490
StatusPublished

This text of 23 Pa. D. & C. 597 (McClelland v. New Amsterdam Casualty Co.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Philadelphia County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McClelland v. New Amsterdam Casualty Co., 23 Pa. D. & C. 597, 1935 Pa. Dist. & Cnty. Dec. LEXIS 170 (Pa. Super. Ct. 1935).

Opinion

Alessandroni, J.,

The McClelland Company entered into a contract with Morris Wood for the erection of a large apartment building in the City of Philadelphia to be known as Green Hill Farms, the con[598]*598tract being dated June 29,1928, and the total price being $538,448. The contract provided that before the issuance of the final certificate of approval the McClelland Company as general contractor was obliged to submit evidence satisfactory to the architect that all payrolls, material bills and other indebtedness connected with the work had been paid; and that the percentage retained by the owner, totaling approximately $80,000, was not to be paid to the McClelland Company until such proof was submitted and a full release of all liens delivered. The McClelland Company in turn entered into a contract with M. F. Dussinger & Company as subcontractor for the plumbing work and materials required in the erection of the building.

M. F. Dussinger & Company as principal and the defendant as surety executed a bond in favor of the Mc-Clelland Company, contractor, and Morris Wood, owner, in the amount of $67,180 on October 8, 1928, which bond incorporated by reference the terms and conditions of the contract between the general contractor and the subcontractor, and was conditioned “that if the said principal shall well and truly perform the terms and provisions of said contract and the obligations on his part required to be performed, and shall pay all bills for labor, materials and supplies furnished in connection therewith, then this obligation shall be null and void, otherwise to be and remain in full force and effect.” This bond is the basis upon which the present action rests.

Dussinger & Company began work on the contract in September of 1928 and performed their work on schedule and satisfactorily until September 23, 1929. In November of 1928, Dussinger informed McClelland that he did not have enough credit to purchase at one time the large amount of materials required for the job and asked him to guarantee the payment of an order which he was placing with the Ha joca Corporation for the necessary materials. McClelland stated that he executed the guarantee relying on the provisions of the bond. Subsequently, sev[599]*599eral additional orders were guaranteed for Dussinger by McClelland, but these do not now form part of the claim in this suit. On September 23, 1929, Dussinger notified McClelland that he could not proceed further on the contract for lack of funds, and the McClelland Company immediately notified him and the defendant surety of the default in accordance with article 3 of the contract between the parties, which gave the contractor the right to terminate the employment of the said contractor on 3-days’ notice, upon default. Dussinger and Company subsequently became bankrupt and the McClelland Company was required to pay the balance due for materials supplied Dussinger for the Green Hill Farms project. The balance then due was $10,175.20.

McClelland testified that he did not consider the request for a guarantee by Dussinger as a default and that it was customary for general contractors to give such assistance to their subcontractors. There was also other testimony establishing a general custom among contractors to help subcontractors with credit for materials. Dussinger himself testified that if the guarantee had not been executed by McClelland he would have been able to continue with his work on the contract by purchasing smaller lots of material at higher prices. No money was diverted by Dussinger from the Green Hill Farms project to other work. It was also testified that the execution of the guarantee by McClelland reduced the loss that would have resulted when a default occurred, and that by reason thereof the materials were purchased at a lower price than would have been the case if smaller quantities had been ordered.

All questions were submitted to the jury in a careful charge. The jury returned a verdict for the plaintiffs in the sum of $12,480.50. This motion seeks to set the verdict aside upon the theory that the plaintiffs have not established a right of action against the defendants.

The plaintiff, McClelland, instituted this action, proceeding on two legal theories. The first is based upon the [600]*600premise that the Hajoca Corporation had a right to recover the sum due it for materials as a third party beneficiary on the bond executed in favor of the plaintiffs, to which right McClelland is now subrogated. The second is that the plaintiff McClelland is entitled to recover on the bond because of breach of the condition that the material-men be paid, McClelland being obliged to pay the material claim in order to fulfill his contract with the owner. We are of the opinion that both theories are sustained by the law of this State.

The defendant first argues that the Hajoca Corporation could not recover on the bond for materials furnished Dussinger and, therefore, McClelland could not be subrogated to any legal right in making such payment. The basis for this contention rest primarily upon the decisions of the Supreme Court in the case of Greene County, for use, v. Southern Surety Co., 292 Pa. 304, and the cases which followed it. The condition of the bond in question was that Dussinger & Company “shall pay all bills for labor, materials and supplies”. The Greene County case has long been recognized as inequitable and contrary to the best considered legal opinion in this country. This was acknowledged by Mr. Justice Kephart in his opinion in the Greene County case, but the rule of stare decisis was there invoked by the Supreme Court. Since that time exceptions to the established rule have gradually whittled away the effect of that decision: Concrete Products Co. v. United States Fidelity & Guaranty Co., 310 Pa. 158; until finally our appellate courts have wholly disregarded it: Commonwealth v. Great American Indemnity Co., 312 Pa. 183; Philipsborn v. 17th & Chestnut Holding Corp., 111 Pa. Superior Ct. 9. The latter cases definitely overrule the Greene County case and bring the law of Pennsylvania on third party beneficiaries into complete accord with the rule prevailing in 45 of the remaining 47 States of the Union, as well as with the opinion expressed by the learned authorities who prepared the Restatement of the Law of Contracts.

[601]*601A similar bond was interpreted by the Supreme Court in Commonwealth v. Great American Indemnity Co., supra, wherein the court stated on p. 190:

“In an opinion by Mr. Justice Maxey, we quoted with approval from an article by Professor Arthur L. Corbin of the Yale Law School, in which he said (Selected Readings on the Law of Contracts, page 668) : ‘We should now start with the general proposition that two contracting parties have power to create rights in a third party. This has long been a general rule; it is not an “exception”. “Privity” is not necessary; the third party need not be a “promisee,” nor need he give consideration.... The third party has an enforceable right if the surety promises in the bond, either in express words or by reasonable implication, to pay money to him . . . [page 669] In the case of a surety bond for the payment of money, if there is a promise to pay money to an ascertainable person, the fact that he is a third person who gave no consideration for the promise does not prevent him from enforcing it . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Byram Lumber & Supply Co. v. Page
146 A. 293 (Supreme Court of Connecticut, 1929)
Baurer v. Devenis
121 A. 566 (Supreme Court of Connecticut, 1923)
Greene County v. Southern Surety Co.
141 A. 27 (Supreme Court of Pennsylvania, 1927)
McCormick v. Fidelity & Casualty Co.
161 A. 532 (Supreme Court of Pennsylvania, 1932)
Commonwealth v. Great American Indemnity Co.
167 A. 793 (Supreme Court of Pennsylvania, 1933)
Clavan v. Herman
131 A. 705 (Supreme Court of Pennsylvania, 1925)
Phillips v. American Liability & Surety Co.
162 A. 435 (Supreme Court of Pennsylvania, 1932)
Concrete Products Co. v. United States Fidelity & Guaranty Co.
165 A. 492 (Supreme Court of Pennsylvania, 1932)
Sokoloff v. Fidelity Cas. Co. of N. Y.
135 A. 746 (Supreme Court of Pennsylvania, 1926)
Frank Pure Food Co. v. Dodson
126 A. 243 (Supreme Court of Pennsylvania, 1924)
Philipsborn v. 17th & Chestnut Holding Corp.
169 A. 473 (Superior Court of Pennsylvania, 1933)
Young v. American Bonding Co.
77 A. 623 (Supreme Court of Pennsylvania, 1910)
Loughney v. Huntsman Construction Co.
97 A. 179 (Supreme Court of Pennsylvania, 1916)
Philadelphia v. Ray
109 A. 689 (Supreme Court of Pennsylvania, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
23 Pa. D. & C. 597, 1935 Pa. Dist. & Cnty. Dec. LEXIS 170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcclelland-v-new-amsterdam-casualty-co-pactcomplphilad-1935.