Phillips Building Co., Inc. v. An

915 P.2d 1146, 81 Wash. App. 696, 1996 Wash. App. LEXIS 173
CourtCourt of Appeals of Washington
DecidedMay 10, 1996
Docket18426-5-II
StatusPublished
Cited by86 cases

This text of 915 P.2d 1146 (Phillips Building Co., Inc. v. An) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips Building Co., Inc. v. An, 915 P.2d 1146, 81 Wash. App. 696, 1996 Wash. App. LEXIS 173 (Wash. Ct. App. 1996).

Opinion

Armstrong, J.

Phillips Building Company and Bill *698 and Soo An agreed to arbitrate several claims of disputed amounts against each other arising from the construction of a motel. The arbitrators awarded the Ans approximately $15,000 in satisfaction of all of the claims and required them to discharge all subcontractor and supplier liens on the motel. The arbitrators also ruled that each party should bear its own attorney fees and costs. The Ans moved to modify the decision to include an award of attorney fees to them as the prevailing party. Because the prevailing party cannot be determined from the face of the arbitration award, we affirm the trial court’s denial of the motion to modify.

FACTS

Bill and Soo An (the Ans) entered into a contract with Phillips Building Co. (PBC) for the construction of a motel in Tumwater, Washington. The contract provided that all disputes between the parties would be settled by arbitration. During construction, a dispute arose and PBC sued the Ans, filing a lien against the motel for the unpaid contract balance. PBC claimed over $1.2 million in damages as a result of the unpaid balance, work interference, economic compulsion, and quantum meruit. The Ans counterclaimed against PBC for misrepresentation, breach of contract, defective construction, and breach of warranty. The Ans sought approximately $980,000 in damages, and joined John and Ann Phillips (Phillips) as third party defendants. The Phillips were required to personally guarantee PBC’s obligations under the contract. At a mediation session, the parties signed an "Agreement to Arbitrate.” The agreement provided that "[a]ll attorneys fees and costs will be awarded to the prevailing party.”

At oral argument before this court, the parties could not agree on the claims and amounts that each side had *699 sought during arbitration. 1 It appears that PBC had sought approximately $1.3 million and that the Ans counterclaimed for between $500,000 and $600,000. The parties also disagree over whether issues concerning the warranties and the liens owed to various subcontractors and suppliers were before the arbitration panel. 2

During the arbitration proceedings, approximately $138,000 in subcontractor and supplier liens was still on the motel. The Ans had paid, but not released, all of these liens, except for one unpaid lien of $4,424.40. Seafirst Bank had refused to release PBC’s $100,000 bond, guaranteeing lien-free completion, until all of the liens were released by the Ans.

After three weeks of testimony, the arbitrators issued the following decision:

[PBC] shall assign all rights to warranties, express or implied, received from subcontractors and/or suppliers to [the Ans].
In satisfaction of all monetary and performance claims entered in relation to this case and to the above-referenced contract, the following monetary award is made:
[PBC] shall pay to [the Ans] the sum of Fifteen Thousand, Two Hundred, Eighty-Eight and no/100 dollars ($15,288.00).
[The Ans] shall discharge all subcontractors’ and suppliers’ liens filed in relation to the above-referenced, contract and outstanding as of February 16, 1994.
*700 Each party shall bear its own attorneys fees and costs incurred in relation to this arbitration.

Following receipt of the award, the Ans moved for attorney fees and costs as the prevailing party. The arbitrators denied the Ans’ motion, stating again that each party shall bear its own attorney fees and costs. The arbitrators also instructed the Ans to pay and release the motel liens in accordance with the original award, which they had not done. The Ans subsequently requested that the Superior Court modify the arbitration award and grant them attorney fees as the prevailing party. The trial judge noted that it was impossible to determine if the arbitrators had offset successful awards for each party or whether both sides had successfully defended against the others’ claims. He also found that neither side had prevailed for purposes of fees and costs. Believing that the $15,000 award to the Ans was de minimis in light of the magnitude of the claims, the trial court refused to modify the award. The Ans appeal.

ANALYSIS

The Ans argue that the arbitrators exceeded their authority by failing to award them attorney fees as the prevailing party. PBC first responds that the court may not review the merits of the award. PBC then responds that the arbitrators properly denied an award of attorney fees because neither side was the prevailing party. 3

*701 A. Judicial Review of Arbitration Awards

An arbitration award can be vacated only upon one of the grounds specified in RCW 7.04.160. Westmark Properties, Inc. v. McGuire, 53 Wn. App. 400, 402, 766 P.2d 1146 (1989). Under the statute, an award may be vacated:

(4) Where the arbitrators exceeded their powers, or so imperfectly executed them that a final and definite award upon the subject matter submitted was not made.

RCW 7.04.160(4). Arbitrators may exceed their authority by failing to award attorney fees to the prevailing party under an arbitration agreement. See Agnew v. Lacey Co-Ply, 33 Wn. App. 283, 654 P.2d 712 (1982), review denied, 99 Wn.2d 1006 (1983)

Judicial review of an arbitration award, however, is limited to the face of the award. Boyd v. Davis, 127 Wn.2d 256, 263, 897 P.2d 1239 (1995); Lindon Commodities, Inc. v. Bambino Bean Co., 57 Wn. App. 813, 816, 790 P.2d 228 (1990). Such review does not include a review of the merits of the case. Barnett v. Hicks, 119 Wn.2d 151, 157, 829 P.2d 1087 (1992). Unless the award on its face shows adoption of an erroneous rule or a mistake in applying the law, the award will not be vacated. Harris v. Grange Ins. Ass’n, 73 Wn. App. 195, 198, 868 P.2d 201 (1994).

B. Prevailing Party Attorney Fees

RCW 4.84.330

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marriage Of: Chad R. Bacon, V. Destiny K. Bacon
Court of Appeals of Washington, 2025
2400 Elliott Llc, V. Vp Elite Construction Llc
Court of Appeals of Washington, 2024
Chris Walters, V. Robert S. Reynolds
Court of Appeals of Washington, 2023
Marvin Olsen, Et Ux, V. H. Gary Wallis, Et Ux
Court of Appeals of Washington, 2022
James Krell, V. Port Ludlow Townhome Assn
Court of Appeals of Washington, 2022
Richard Randall v. Thomas Koch
Court of Appeals of Washington, 2020
On-site Manager, Inc. v. Brian & Karen Handlin
Court of Appeals of Washington, 2018
Ted Spice, V Donna Dubois
Court of Appeals of Washington, 2016
Gregory Rose, et ux v. FMS, Inc.
Court of Appeals of Washington, 2015
In re the Marriage of Catherine Allen & Jeffrey Allen
Court of Appeals of Washington, 2015
Naumes, Inc. v. City Of Chelan
Court of Appeals of Washington, 2014
In Re The Parentage Of H.a.a., A.k.a. And B.m.a.
Court of Appeals of Washington, 2014
Kassa Ins. Services v. Ryan Pugh, et ux
Court of Appeals of Washington, 2014
Sona & Jim Chu, Resps v. Hyun Seo-jeong, Apps.
Court of Appeals of Washington, 2014
Andy & Sue Whitworth, V Dave's View, Llc
Court of Appeals of Washington, 2013

Cite This Page — Counsel Stack

Bluebook (online)
915 P.2d 1146, 81 Wash. App. 696, 1996 Wash. App. LEXIS 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-building-co-inc-v-an-washctapp-1996.