Philips v. Sun-Best Fruit Distributors

324 P.2d 948, 160 Cal. App. 2d 70, 1958 Cal. App. LEXIS 2095
CourtCalifornia Court of Appeal
DecidedMay 2, 1958
DocketCiv. 5651
StatusPublished
Cited by6 cases

This text of 324 P.2d 948 (Philips v. Sun-Best Fruit Distributors) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philips v. Sun-Best Fruit Distributors, 324 P.2d 948, 160 Cal. App. 2d 70, 1958 Cal. App. LEXIS 2095 (Cal. Ct. App. 1958).

Opinion

GRIFFIN, J.

Plaintiff-respondent brought this action for personal injuries resulting from a fall into a conveyor gutter or trench in a building under construction. At the time and place defendant-appellant Rookie Gamber (referred to in the pleadings and testimony as Rocky or Rock and hereinafter referred to as Gamber) individually and doing business as Gamber Construction Company, was supervising the construction of a fruit-processing shed for the defendant-appellant Sun-Best Fruit Distributors, a copartnership (hereinafter referred to as Sun-Best). It is alleged plaintiff’s injuries were the proximate result of the negligence of all defendants. By answer defendants denied this allegation and alleged contributory negligence on the part of plaintiff and that he assumed the risk.

*73 The facts show generally that prior to July 20, 1954, Gamber was employed by Sun-Best, which was the owner of the real property. Sun-Best agreed with Gamber that he would be paid a fixed fee for supervising and running the job of constructing a fruit-processing shed. Gamber testified this arrangement was not a contract on a bid basis or for cost plus a fixed percentage. He was to supervise the construction and obtain bids from subcontractors. Bids were submitted to Sun-Best. It determined which subcontractor was to obtain the job. Plaintiff Philips, aged 46, prior to this job, had been a salesman for Drake Steel Company. Shortly prior to July 20th, Gamber and plaintiff discussed the possibility of Gamber getting this contract. Plaintiff suggested he contact Abeo Company, a steel fabricator, and introduced Gamber to its president. That company’s bid obtained the contract to fabricate and erect the steel in the building. Plaintiff received an order from Abeo Company for the steel required. He advised the fabricator and the contractor as to the kind of steel that was available, but had nothing to do with the plans and specifications or supervising of the work. During the course of construction plaintiff met Gamber on several occasions in a restaurant across the street from this building to advise him on the availability of certain items of steel or to tell him of the progress of the fabrication at the Abeo Company plant. He said he was sort of a liaison between the contractor and fabricator.

The building was of concrete blocks. The floor was poured concrete over a compacted fill 140 by 60 feet, creating a floor level about 48 inches above the original ground level. A gutter or trench for a conveyor, 32 inches wide and from 18 to 30 inches in depth was left open in the floor surface. The east-west gutter commenced near the east wall and ran west for about 30 feet. It then made a right-angle turn and ran to the north wall and out of the building. . Near the turn was a pit or sump deeper than the gutter. The roofing to the building had not been placed. On July 20th plaintiff received a message to meet Gamber and a Mr. Smith of the Abeo Company at the building. Plaintiff said he had never been in the building before. When he arrived, Gamber was seated in a car parked across the street from the, building. According to plaintiff’s story, Gamber asked plaintiff if he would check the steel in the building and see what he thought of its erection. Without going inside, he noticed some frame *74 work out of line and told Gamber about it. Gamber suggested that plaintiff check with one Naden, job superintendent for Abeo Company inside the partially completed building. Plaintiff, according to his testimony, entered by a doorway on the south end, walked northwesterly to a point where he said he found a lot of things in his way, such as a truck, wheelbarrow, pile of brick, sand and mortar, empty sacks and debris; that he noticed a board across the east-west gutter in the floor; that it was his understanding that a conveyor was to be placed there; that it was 3 feet wide by 3 feet deep,—deep enough for him to fall into on his return trip; that from there the trench extended both to his right and to his left, how far he could not guess; that before going to the crossing, somewhere near the middle of the floor he observed a trench and thought the debris was covering it; that he could not step across the gutter at that point so he continued west over to the board crossing; that he walked across the board and then saw Naden on top of the north wall near the northeast corner; that he walked over and told him he thought the girders forming the canopy were crooked and Naden informed him they would straighten out when properly tightened down; that at Naden’s request he examined other girders on his way out of the building; that while he was walking south from that point toward the south end of the building he was looking up at the girders and fell into the east-west gutter between the center and the east side of the building and was severely injured; that there was considerable debris along this route and near this point; and that the pit or trench there was hidden by debris so he could not see it. He later testified he did not fall over any of the debris because he had a clear path and did not see the hole because he was looking at the trusses overhead; that from the time he entered the building until he fell he had only crossed one trench; that he did not know the other trench existed until he fell into it; that the reason he did not see the trench was because he was looking at the trusses and not because of the debris; that had Naden not asked him to inspect the girders he would have been looking where he was going on his way out; and that he later heard Gamber say: “We should have covered it, that excavation, last week when a brick mason fell into a hole on the other side of the building.”

Naden testified he told plaintiff, on his way out, to look and see how straight the steel purlins on the trusses were on the southern end which was completed; that he did not there *75 after observe plaintiff until he fell; that there was a pile or two of bricks around but he did not recall seeing the debris material described by plaintiff.

Gamber testified plaintiff had been in the building two or three times prior to July 20th; that he did not remember telling plaintiff to go into the building on that date and probably did not ask him to look at the steel work; that the pit at the west end of the gutter was completely covered with boards, and planks had been spread across the gutter at intervals to walk across but no barricades had been placed around the gutter; and that when he entered through the south door that morning both the east-west and north-south trenches were perfectly visible. Other witnesses so testified and stated that the plaintiff’s pictures of a trailer and papers covering, to some extent, the gutter near the place where plaintiff fell, which pictures were subsequently taken, were not true pictures of conditions as they existed on July 20th; and that there was nothing blocking or obstructing plaintiff’s view as he approached the trench from the north just before he fell. The evidence further shows that one of defendant partners of Sun-Best would go to the job, possibly daily, to see how it was progressing, ask questions of Gamber, inspect the completed work and see if it was satisfactory. The plans for the building were prepared for Sun-Best by a registered civil engineer obtained by Gamber. Upon this evidence a jury found in favor of plaintiff and against both defendants for $10,000. They filed separate notices of appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Halliday v. Greene
244 Cal. App. 2d 482 (California Court of Appeal, 1966)
Lattanzi v. San Moritz Club
202 Cal. App. 2d 546 (California Court of Appeal, 1962)
Perrotti v. Sampson
188 Cal. App. 2d 238 (California Court of Appeal, 1961)
Schumann v. C. R. Reichel Engineering Co.
187 Cal. App. 2d 309 (California Court of Appeal, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
324 P.2d 948, 160 Cal. App. 2d 70, 1958 Cal. App. LEXIS 2095, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philips-v-sun-best-fruit-distributors-calctapp-1958.