PGE v. Public Utility Comm.

Court of Appeals of Oregon·Decided September 16, 2026·No. A186771·Published

Opinion

54 September 16, 2026 No. 869

IN THE COURT OF APPEALS OF THE STATE OF OREGON

In the Matter of Portland General Electric Company, request for a general rate revision.

PORTLAND GENERAL ELECTRIC COMPANY, Petitioner,

v.

PUBLIC UTILITY COMMISSION OF OREGON and Oregon Citizens’ Utility Board, Respondents.

Public Utility Commission of Oregon UE435; A186771

Argued and submitted June 30, 2026. Iván Resendiz Gutierrez argued the cause for petitioner. Also on the briefs were Jessica Ann Bernardini and Miller Nash LLP.

Jordan R. Silk, Assistant Attorney General, argued the cause for respondents. Also on the brief were Dan Rayfield, Attorney General, and Paul L. Smith, Solicitor General.

Before Egan, Presiding Judge, Jacquot, Judge, and Armstrong, Senior Judge.

JACQUOT, J. Affirmed.

Cite as 353 Or App 54 (2026) 55

JACQUOT, J. Portland General Electric Company (PGE) seeks judicial review of a final order from the Public Utility Commission of Oregon (PUC), raising one assignment of error. The dispute regards the meaning of “associated energy storage,” within ORS 469A.120(2)(a), which enables qualified electric utility companies to recover certain expenses— those related to renewable energy—through an automatic process, rather than through a general rate case.1 PGE argued to the PUC that expenses for standalone energy storage projects are recoverable through the automatic process as “associated energy storage.” The PUC rejected that argument. On appeal, PGE argues that the PUC erroneously interpreted the statute and improperly denied automatic cost recovery for standalone energy storage projects. The PUC responds that it “correctly concluded that ORS 469A.120(2)(a) does not allow [automatic] cost recovery for standalone energy storage” and that a general rate case is the correct mechanism to seek recovery of such expenses. For the reasons provided below, we affirm.

We begin our analysis by examining the background of the Oregon Renewable Energy Act (OREA) and the parties’ arguments. We then turn to the text and context of the disputed provision of ORS 469A.120. Subsequently, we discuss relevant legislative history, concluding that when the legislature enacted and amended OREA, it intended a meaning for the term “associated” that is incompatible with PGE’s proffered interpretation. Under a correct reading of the statute , the term “associated” does not refer to all energy storage investments; rather, cost recovery under ORS 469A.120(2)(a) is available for capital investments in the construction or acquisition of “facilities that generate electricity from renewable energy sources” and the transmission and storage costs 1 A general rate case is a quasi-judicial process whereby a utility company files a request to increase or decrease utility rates, interested parties can intervene , there are opportunities for public comment, an administrative law judge reviews evidence and testimony, and ultimately, the PUC votes whether to approve, deny, or modify the utility’s request. See generally OAR ch 860. The Citizens’ Utility Board, also known as CUB, has the right to intervene as an advocate on behalf of Oregon utility consumers. ORS 774.180.

The automatic recovery process also allows for oversight, particularly if the utility seeks to increase consumer costs. ORS 469A.120(3)(b).

56 PGE v. Public Utility Comm.

associated with those particular facilities. Accordingly, we affirm PUC’s final order.

I. BACKGROUND

A. Enactment and Amendments of OREA OREA was enacted in 2007. Or Laws 2007, ch 301, § 13. It established a Renewable Portfolio Standard (RPS), which requires large utilities—such as PGE—to increase utilization of electricity generated from renewable sources, with at least 50 percent of energy sold to customers being derived from renewable sources by 2040. ORS 469A.052(1) (h). “The desired objectives of [the] RPS include: reducing greenhouse gas emissions, diversifying fuel sources, developing new technologies, and improving rural economies.” Staff Measure Summary, House Committee on Energy and the Environment, SB 838 C, May 18, 2007.2 Section 13 of OREA, which was codified as ORS 469A.120, was titled “Cost Recovery.” Or Laws 2007, ch 301, § 13. The first subsection provided that, except for a limitation specified in another provision of OREA, “[A]ll prudently incurred costs associated with compliance with [the RPS] are recoverable in the rates of an electric company, including interconnection costs, costs associated with using physical or financial assets to integrate, firm or shape renewable energy sources on a firm annual basis to meet retail electricity needs and other costs associated with transmission and delivery of qualifying electricity to retail electricity consumers.”

Or Laws 2007, ch 301, § 13. Another subsection directed the PUC to “establish an automatic adjustment clause” for certain electric company expenses. Id. That same subsection explained that the automatic process “allows timely recovery of costs prudently incurred by an electric company to construct or otherwise acquire facilities that generate electricity from renewable energy sources and for associated electricity transmission.” Id. Subsequently, the PUC established the Renewable Automatic Adjustment Clause (RAAC), a 2 Although staff measure summaries are not adopted or officially endorsed by the legislature, such summaries can “be important sources for understanding legislative intent[.]” State v. Gardner-Rolph, 345 Or App 681, 698, 584 P3d 270 (2025), rev den, 375 Or 261 (2026).

Cite as 353 Or App 54 (2026) 57

mechanism that allows utilities to recover certain expenditures through rate increases without having to go through a complete general rate case. PUC Order No 24-091 (2024). According to the PUC, by submitting a RAAC schedule, a utility company may “recover the actual and forecasted revenue requirement for [an] eligible plant that is in service as of the date of the proposed rate change.” Id.

In 2016, the legislature amended the automatic adjustment provision contained in ORS 469A.120(2).3 Or Laws 2016, ch 28, § 11. The operative language is:

“[The RAAC process] allows timely recovery of costs prudently incurred by an electric company to construct or otherwise acquire facilities that generate electricity from renewable energy sources [and for], costs related to associated electricity transmission and costs related to associated energy storage.”

Id. (with deleted material italicized and in brackets, and new material in boldface). Neither the word “associated” nor the phrase “associated energy storage” is defined by statute. B. Energy Costs at Issue There are two categories of energy storage relevant to this matter: co-located and standalone. Co-located energy storage facilities are connected directly to an energy- generating facility; typically, co-located energy storage is a collection of batteries located in close physical proximity to an energy-generating facility such as a solar panel array. See Oregon Department of Energy, Energy Facility Siting Council Agenda Item C: Overview of Battery Energy Storage Systems for the May 16, 2025, Energy Facility Siting Council Meeting, 1-3, https://www.oregon.gov/energy/ facilities/Council%20 Meetings/2025-05-16-EFSC-Item-C-Staff-Report-Battery- Storage-Technology-Overview.pdf (accessed July 31, 2026) (listing a summary of examples). In contrast, standalone energy storage is not directly connected to any one energy- generating facility; rather, standalone energy storage is tied 3 ORS 469A.120 was also amended in 2010. Or Laws 2010, ch 79, § 1. The 2010 amendments changed language related to “above-market costs” and renumbered subsections. Id.

58 PGE v. Public Utility Comm.

Free access — add to your briefcase to read the full text and ask questions with AI

PGE v. Public Utility Comm., (Or. Ct. App. 2026).

PGE v. Public Utility Comm. (PGE v. Public Utility Comm.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Gaines
206 P.3d 1042 (Oregon Supreme Court, 2009)
Bergerson v. Salem-Keizer School District
144 P.3d 918 (Oregon Supreme Court, 2006)
COST SECURITY v. Real Estate Agency
15 P.3d 29 (Oregon Supreme Court, 2000)
State v. KIMBLE/BERKNER
237 P.3d 871 (Court of Appeals of Oregon, 2010)
Village at Main Street Phase II, LLC v. Department of Revenue
339 P.3d 428 (Oregon Supreme Court, 2014)
Jenkins v. Board of Parole & Post-Prison Supervision
335 P.3d 828 (Oregon Supreme Court, 2014)
Waterkeeper v. Port of Coos Bay Or.
423 P.3d 60 (Oregon Supreme Court, 2018)
Coast Security Mortgage Corp. v. Real Estate Agency
15 P.3d 29 (Oregon Supreme Court, 2000)
Strasser v. State of Oregon
489 P.3d 1025 (Oregon Supreme Court, 2021)
State v. Gardner-Rolph
345 Or. App. 681 (Court of Appeals of Oregon, 2025)