Pge v. Lmic

CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 10, 2017
Docket16-35628
StatusPublished

This text of Pge v. Lmic (Pge v. Lmic) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pge v. Lmic, (9th Cir. 2017).

Opinion

FOR PUBLICATION

UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT

PORTLAND GENERAL ELECTRIC No. 16-35628 COMPANY, Plaintiff-Appellee, D.C. No. 3:16-cv-00495-HZ v. OPINION LIBERTY MUTUAL INSURANCE COMPANY; ZURICH AMERICAN INSURANCE COMPANY, Defendants-Appellants.

Appeal from the United States District Court for the District of Oregon Marco A. Hernandez, District Judge, Presiding

Argued and Submitted May 8, 2017 Portland, Oregon

Filed July 10, 2017

Before: Jay S. Bybee and Andrew D. Hurwitz, Circuit Judges, and Jed S. Rakoff,* Senior District Judge.

Opinion by Judge Rakoff

* The Honorable Jed S. Rakoff, Senior United States District Judge for the Southern District of New York, sitting by designation. 2 PGE V. LMIC

SUMMARY**

Arbitration

The panel vacated the district court’s judgment entering a preliminary injunction prohibiting sureties from pursuing claims against Portland General Electric Company (“PGE”) in arbitration and denying a mandatory stay of the judicial proceedings under § 3 of the Federal Arbitration Act, and remanded for further proceedings; and dismissed for lack of appellate jurisdiction the sureties’ appeal from the order denying their motion for a discretionary stay.

The appeal involves the interplay of three related contracts: a Construction Contract entered by PGE and several contracting companies to build an Oregon power plant; a performance Bond in which appellants/sureties Liberty Mutual Insurance Company and Zurich American Insurance Company issued a bond to PGE as required by the Construction Contract; and a Guaranty of performance issued to PGE by its parent company, Abengoa S.A. The Guaranty provided that the parties submit any disputes to binding arbitration to be conducted by the International Chamber of Commerce (“ICC”) under its procedural rules and Oregon substantive law.

PGE filed this diversity action against the sureties, alleging breach of the Bond and bad faith; and PGE sought a preliminary injunction prohibiting the sureties from arbitrating their claims against PGE.

** This summary constitutes no part of the opinion of the court. It has been prepared by court staff for the convenience of the reader. PGE V. LMIC 3

The panel held that the incorporation of the ICC Rules into an arbitration agreement constituted clear and unmistakable evidence of a delegation of gateway issues of arbitrability to the arbitrator.

The panel rejected PGE’s contention that the ICC Rules did not govern the present dispute because the Bond lacked an arbitration clause. The panel held that the following were questions of the scope of the arbitration agreement in the Guaranty, and delegated to the arbitrators: whether Abengoa properly joined the sureties to the arbitration pursuant to the Guaranty and the ICC Rules; whether the sureties’ claim against PGE met the Guaranty’s test of “aris[ing] out of or in connection with an agreement with a subcontractor or [the] Guaranty,” and whether PGE had therefore agreed to arbitrate its disputes against the sureties. The panel concluded that the district court erred in enjoining the sureties from participating in the ICC arbitration, and preventing the arbitral tribunal from addressing the scope of the arbitration.

COUNSEL

Eric D. Miller (argued), Perkins Coie LLP, Seattle, Washington; David Bledsoe, Perkins Coie LLP, Portland, Oregon; for Plaintiff-Appellee.

John Spencer Stewart (argued), Mario R. Nicholas, Thomas Ardell Larkin, and Jan D. Sokol, Stewart Sokol & Larkin LLC, Portland, Oregon, for Defendant-Appellants.

Nathan D. O’Malley (argued) and Sara H. Kornblatt, Gibbs Giden Locher Turner Senet & Wittbrodt LLP, Los Angeles, California, for Amicus Curiae Abengoa. 4 PGE V. LMIC

OPINION

RAKOFF, Senior District Judge:

If two parties enter a contract that both requires arbitration of their disputes and allows impleader of a third party, must a party that did not initiate the impleader arbitrate a dispute that arises out of the same transaction at issue in the arbitration with the impleaded third party? We hold, on the facts of this case, that this question is really a question about the scope of the arbitration clause for the arbitrator to decide. Since, instead, the district court undertook to decide that question, we vacate and remand.

BACKGROUND

This appeal concerns the interplay of three related contracts. In the first (the “Construction Contract”), entered into in June 2013, appellee Portland General Electric Company (“PGE”) hired several related contracting companies (collectively, the “Contractor”) to build an Oregon power plant. The Construction Contract allows PGE to terminate the agreement upon the Contractor’s default. A “Disputes” provision requires the parties to attempt to mediate any disputes, but if mediation fails, “each Party shall have the right to take whatever legal actions that they may choose.” A “Choice of Law; Jurisdiction” provision states that the agreement is governed by Oregon substantive law and that the parties “consent to the exclusive jurisdiction of any U.S. federal court with jurisdiction over Oregon.” The PGE V. LMIC 5

contract passingly mentions arbitration twice, but does not require it.1

The Construction Contract requires the Contractor to obtain a performance bond. Appellants Liberty Mutual Insurance Company and Zurich American Insurance Company (collectively, the “Sureties”) issued the required bond (the “Bond”) to PGE. The Bond incorporates the Construction Contract by reference and states that “[a]ny proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located, and in any court(s) to which the Parties to the Construction Contract have agreed will have jurisdiction over disputes thereunder.” The Bond is silent as to arbitration.

The Construction Contract also requires the Contractor to obtain a guaranty of performance from a parent company, Abengoa S.A. (“Abengoa”). Abengoa issued a guaranty to PGE (the “Guaranty”), in which both parties consented to submit any disputes “in connection with this Guaranty” to binding arbitration. Of particular relevance here, the Guaranty specifies that the arbitration is to be conducted by the International Chamber of Commerce (“ICC”) under its procedural rules and Oregon substantive law, and that “[o]nce the arbitration proceeding is commenced hereunder, either

1 A “Responsibilities of Contractor” provision gives PGE the right to audit the Contractor; PGE must “treat such audit data as confidential, but shall not be precluded from using such audit data in any legal proceedings (including without limitation mediation or arbitration) arising under this Agreement.” A “Costs and Attorney Fees” provision states: “In any litigation arising out of this Agreement, including arbitration and any case or proceeding under the Bankruptcy Code or any successor statute, the prevailing Party shall be entitled to recover [reasonable expenses].” 6 PGE V. LMIC

Party may implead any other person or entity (with such person or entity’s consent) in, and/or raise any claim against, any other person or entity provided such claim arises out of or in connection with an agreement with a Subcontractor or this Guaranty.”

On December 18, 2015, PGE declared the Contractor in default and terminated the Construction Contract. Abengoa filed a Request for Arbitration with the ICC on December 31, 2015, naming PGE as “respondent” and the Contractor as an “impleaded” party. Abengoa contended that the Contractor had not defaulted, that PGE’s termination of the Construction Contract was wrongful, and that Abengoa owed PGE nothing under the Guaranty. The Contractor sought similar relief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Agere Systems, Inc. v. Samsung Electronics Co. Ltd.
560 F.3d 337 (Fifth Circuit, 2009)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Invista S.À.R.L. v. Rhodia, S.A.
625 F.3d 75 (Third Circuit, 2010)
Turi v. Main Street Adoption Services, LLP
633 F.3d 496 (Sixth Circuit, 2011)
Qualcomm Incorporated v. Nokia Corporation
466 F.3d 1366 (Federal Circuit, 2006)
Momot v. Mastro
652 F.3d 982 (Ninth Circuit, 2011)
Apollo Computer, Inc. v. Helge Berg
886 F.2d 469 (First Circuit, 1989)
Sr. Kate Reid v. Doe Run Resources Corp.
701 F.3d 840 (Eighth Circuit, 2012)
Oracle America, Inc. v. Myriad Group A.G.
724 F.3d 1069 (Ninth Circuit, 2013)
Mundi v. Union Security Life Insurance
555 F.3d 1042 (Ninth Circuit, 2009)
Sokol Holdings, Inc. v. BMB Munai, Inc.
542 F.3d 354 (Second Circuit, 2008)
Shirley Douglas v. Trustmark National Bank
757 F.3d 460 (Fifth Circuit, 2014)
Carey Brennan v. Opus Bank
796 F.3d 1125 (Ninth Circuit, 2015)
Belnap v. Iasis Healthcare
844 F.3d 1272 (Tenth Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Pge v. Lmic, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pge-v-lmic-ca9-2017.