Petition of Interstate Power Co.

416 N.W.2d 800, 1987 Minn. App. LEXIS 5101, 1987 WL 22232
CourtCourt of Appeals of Minnesota
DecidedDecember 15, 1987
DocketC9-87-1218
StatusPublished
Cited by3 cases

This text of 416 N.W.2d 800 (Petition of Interstate Power Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petition of Interstate Power Co., 416 N.W.2d 800, 1987 Minn. App. LEXIS 5101, 1987 WL 22232 (Mich. Ct. App. 1987).

Opinion

OPINION

FORSBERG, Judge.

On July 1, 1986, Relator Interstate Power Company (“Interstate”) filed an application with the Minnesota Public Utilities Commission (“Commission”) for an increase of $2,472,944 in its annual Minnesota electric rates. In August 1986, the Commission issued an interim rate order, allowing Interstate to collect $1,161,505, subject to refund upon the issuance of a final order.

In December 1986, an administrative law judge (“ALJ”) conducted hearings on Interstate’s proposed rates, and in March 1987, the ALJ issued his report recommending the allowance of increased annual revenues in the amount of $521,995.

Interstate, the Office of the Attorney General, and the Department of Public Service (“DPS”) filed exceptions to the AU’s report, and the matter was reviewed by the Commission. On May 1, 1987, the Commission issued its order, allowing Interstate a final annual rate increase of $373,817. The Commission denied petitions for reconsideration and rehearing, and Interstate appealed to this court, seeking an additional increase of $737,976. The Commission moved to strike portions of Interstate’s brief, and we have considered that motion as part of our review. To the extent Interstate’s allegations are unsupported by the record, they have been disregarded. We affirm in part, reverse in part and remand.

FACTS

Interstate is an electric and gas utility which serves southern Minnesota and portions of Iowa and Illinois. Interstate’s proposed rate increase included a request for rate base treatment and amortization of the costs incurred in one transmission project and two generation projects, which Interstate entered into with other companies, and which were later cancelled when circumstances changed. In its petition for rehearing and reconsideration before the Commission, Interstate withdrew its re *803 quest for rate base treatment of the unam-ortized cancelled plant expenses. Since these rate base issues were not raised in Interstate’s application for rehearing, we have not considered them on appeal. 1

Carroll County Project.

In the early 1970’s, due to a forecasted deficiency in service for 1982, Interstate requested its engineering firm to study and recommend alternative methods of obtaining additional power. In 1973, Interstate signed a letter of intent with Commonwealth Edison Company (“Commonwealth”) to build a joint nuclear generating facility in Carroll County, Illinois. The Iowa-Illinois Gas and Electric Company joined the project, and the three companies set up a trust arrangement for holding land titles. The parties signed a formal agreement in 1984, and Commonwealth was designated as the parties’ agent.

By 1975, Commonwealth had acquired additional land, and the companies applied to the Illinois Commerce Commission for approval of their joint participation in the proposed Carroll County project, pursuant to Section 27 of the Illinois Public Utilities Act. In 1976, the Illinois Commission issued an order denying approval of the Section 27 application, and advising the companies that they should request a Certificate of Public Convenience and Necessity under Section 55 of the Iowa Public Utilities Act before reapplying for approval under Section 27. At the time, a Section 55 certificate was valid for two years.

Commonwealth never applied for a Section 55 certificate, because the Carroll County project never came within two years of commencing physical construction. Based on discussions with Commonwealth, Interstate believed that there was no point in applying for a certificate if it would run out before construction commenced.

Interstate subsequently engaged another engineering firm to evaluate Interstate’s participation in the Carroll County project. The engineers recommended that Interstate stay in the project, but in 1979 they recommended that Interstate obtain a reduction in participation. Based upon this recommendation, the delays in the project, the denial of Section 27 approval, and a decision to participate in the Guthrie project discussed below, Interstate followed this recommendation and reduced its participation in the Carroll County project.

In September 1981, the companies filed a new Section 27 application with the Illinois Commission, arguing that an application for a Section 55 certificate would still be premature because they had no plans to commence construction within two years. The Section 27 application was again denied, and in December 1981, Commonwealth decided to postpone the Carroll County project until 1999 or 2000. Shortly thereafter, Interstate decided to withdraw from the Carroll County project.

The AU found that Interstate’s decisions to participate in and withdraw from the Carroll County project were prudent, considering the circumstances at the time of those decisions, and recommended allowing amortization of expenses over five years and rate base treatment of unam-ortized expenses. The AU reasoned that much of Interstate’s delay in withdrawing from the project was the result of the inevitable regulatory lag attendant upon the implementation of such a large project.

The Commission agreed that Interstate’s original decision to invest was prudent, but found that all expenses after the “preliminary planning stage” were unnecessary. The Commission therefore disallowed amortization of all but preliminary planning expenses.

Guthrie County Project.

In 1979, based upon delays in the Carroll County project and peak load growth experienced in the ”1970’s, Interstate entered into a joint project with three Iowa utilities to build a coal-fired generating facility at Guthrie County, Iowa.

*804 The ALJ found that Interstate’s decision to participate in the Guthrie County project was reasonable and prudent, because Interstate was forecasting an annual peak load growth of approximately three percent at the time. The ALJ therefore allowed Interstate to amortize test year expenses for the project.

The Commission disagreed, concluding that Interstate’s forecasting methods were not reasonable, and that Interstate’s decision to join the Guthrie project, based upon these forecasting methods, was imprudent. The Commission found that an evident shift in the pattern of peak load growth had followed the oil embargo of 1973, and that Interstate’s forecasting method of using historical peak loads to predict future peak loads had not taken into consideration factors such as conservation, which Interstate had acknowledged was occurring. The Commission concluded that Interstate should have changed its forecasting methods by 1979 to incorporate factors such as conservation.

Allowance for Funds Used During Construction.

In 1980, Interstate entered into a project, known as the “White-Eldorado project,” which involved a transmission line to be jointly constructed and owned by Interstate and three other Iowa utilities. This project was also subsequently cancelled.

The Commission found that Interstate’s decisions to participate in and withdraw from the White-Eldorado project were prudent, but disallowed amortization of interest characterized as allowance for funds used during construction (AFUDC) on the White-Eldorado project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petition of Interstate Power Co.
419 N.W.2d 803 (Court of Appeals of Minnesota, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
416 N.W.2d 800, 1987 Minn. App. LEXIS 5101, 1987 WL 22232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petition-of-interstate-power-co-minnctapp-1987.