Performance Plastering v. Richmond American Homes of California, Inc.

63 Cal. Rptr. 3d 537, 153 Cal. App. 4th 659, 2007 Cal. App. LEXIS 1208
CourtCalifornia Court of Appeal
DecidedJuly 24, 2007
DocketC052768
StatusPublished
Cited by43 cases

This text of 63 Cal. Rptr. 3d 537 (Performance Plastering v. Richmond American Homes of California, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Performance Plastering v. Richmond American Homes of California, Inc., 63 Cal. Rptr. 3d 537, 153 Cal. App. 4th 659, 2007 Cal. App. LEXIS 1208 (Cal. Ct. App. 2007).

Opinion

Opinion

ROBIE, J.

In this case we deal with the falling out between a homebuilder, Richmond American Homes of California, Inc., one of its subcontractors, Performance Plastering, 1 and the subcontractor’s insurer, CalFarm Insurance Company.

*662 The problems underlying this case began when Performance Plastering was suspended as a corporation and Richmond began receiving complaints of defective construction work done by Performance Plastering on some of Richmond’s homes. In an attempt to resolve liability, Richmond and Performance Plastering entered into the so-called El Niño settlement agreements, and Richmond and CalFarm entered into the so-called Air Design settlement agreement. The El Niño settlement agreements released Performance Plastering and its insurers from claims related to 65 homes in Elk Grove in exchange for Performance Plastering paying Richmond $57,000. The Air Design settlement agreement dismissed Performance Plastering from all claims, gave Performance Plastering a release of all claims identified on a “subcontractor allocation,” and obligated Richmond to give five business days’ notice to CalFarm “of any potential indemnity claims,” all in exchange for CalFarm’s paying Richmond $8,700.

A few years later, CalFarm and Performance Plastering sued Richmond for breach of contract and declaratory relief based on Richmond’s alleged violation of the El Niño and Air Design settlement agreements.

Richmond demurred to the first amended complaint. The trial court sustained the demurrer without leave to amend, ruling that neither plaintiff could pursue the lawsuit because Performance Plastering is a suspended corporation and CalFarm had no standing to bring claims based on agreements to which it was neither a party nor a third party beneficiary. The court also granted Richmond’s request for attorney fees based on a prevailing party theory.

On appeal, we reverse the judgment sustaining the demurrer without leave to amend because CalFarm had standing to bring the lawsuit as it was a party to the Air Design settlement agreement and was a third party beneficiary of the El Niño settlement agreements. Accordingly, we also reverse the award of attorney fees to Richmond.

FACTUAL AND PROCEDURAL BACKGROUND

Performance Plastering subcontracted with Richmond in June 1994 to perform stucco work on homes being built by Richmond in Sacramento County. The subcontract agreement contained a prevailing party attorney fee clause that stated, “if contractor initiates legal action and prevails against *663 subcontractor under this Agreement, subcontractor shall pay all litigation costs incurred by contractor in prosecuting that action.” The subcontract agreement also contained a modification clause that stated, “[t]his Agreement . . . can only be modified by written amendment executed by authorized agents of the parties hereto.”

Following the El Niño rains in 1997, Richmond asserted construction defect claims against Performance Plastering for work Performance Plastering had done on some of Richmond’s homes in Elk Grove.

In November 1998, the Secretary of State suspended Performance Plastering as a corporation. Subsequently, the Franchise Tax Board also suspended Performance Plastering because it failed to pay taxes.

In June 2001, Richmond and Performance Plastering entered into the El Niño settlement agreements. According to the terms of the two settlement agreements, Performance Plastering would pay Richmond a total of $57,000 and, in exchange, Richmond would “released and forever discharge[] Subcontractor and its insurers . . . from any and all past, present or future claims, demands, obligations or causes of action . . . which Richmond has or which may later accrue to Richmond with respect to the Claim.” There was one claim attached to each settlement agreement: the first one listed 26 homes in the Rosegarden subdivision in Elk Grove, and the second one listed 39 homes in the Legacy Park subdivision in Elk Grove.

Richmond sued Performance Plastering for more alleged construction defects. In March 2003, that lawsuit settled orally at a settlement conference under what became known as the Air Design settlement agreement. Present at the settlement conference were attorneys for Richmond and CalFarm along with Richmond and CalFarm “representative[s].” CalFarm agreed to pay Richmond $8,700 and, in return, Richmond agreed to “dismiss[] . . . Performance of all claims,” release all claims “as to the properties identified on [the subcontractor] allocation,” “reserv[e] its right to indemnity” for “any claim” not identified on the subcontractor allocation, and give CalFarm “five business days’ notice” “of any potential indemnity claims” and if it did not “the indemnity claim is lost.”

In April 2003, Richmond was sued for construction defects arising from Performance Plastering’s work in a lawsuit that became know as the Tasker case. Richmond filed a cross-complaint against Performance Plastering (case *664 No. 04AS03269). Performance Plastering answered the cross-complaint and alleged that the claims were barred because Richmond failed to give five business days’ notice, in violation of the Air Design settlement agreement and because the Tasker cross-complaint involved liability regarding homes covered in the El Niño settlement agreements.

In June 2005, Richmond, CalFarm, and Performance Plastering “by and through” CalFarm, entered into a settlement contribution agreement in the Tasker case. CalFarm agreed to pay $18,000 to Richmond in exchange for Richmond’s agreement to release Performance Plastering from all claims for damages that arise out of the Tasker case. The agreement also reserved the parties’ right to seek judicial determination of the applicability and enforceability of the El Niño and Air Design settlement agreements to the Tasker case.

Thereafter, CalFarm and Performance Plastering “by and through” CalFarm sued Richmond for breach of contract and declaratory relief based on Richmond’s alleged violation of the El Niño and Air Design settlement agreements (case No. 05AS01309). According to the allegations in the first amended complaint, Richmond violated the El Niño settlement agreements by suing Performance Plastering in the Tasker case for claims involving homes that were part of the El Niño settlement agreements. Richmond also violated the Air Design settlement agreement by failing to give CalFarm five business days’ notice of the claims made in the Tasker case.

Richmond demurred to the first amended complaint. The court sustained the demurrer without leave to amend and entered a judgment of dismissal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Moreno v. DeSantis CA4/1
California Court of Appeal, 2025
Kelly v. Boxer & Gerson CA1/3
California Court of Appeal, 2025
Kalu v. Okeani CA2/4
California Court of Appeal, 2025
Gutlin v. U.S. Bank, National Assn. CA2/1
California Court of Appeal, 2025
Saghian v. U.S. Bank National Assn. CA2/3
California Court of Appeal, 2024
Meyer v. Dept. of Water Resources CA3
California Court of Appeal, 2024
Vera v. Imperial Valley Housing Authority CA4/1
California Court of Appeal, 2024
Perez v. Century Indemnity Co. CA1/2
California Court of Appeal, 2024
Coleman v. Frontier Mission Fellowship CA2/3
California Court of Appeal, 2023
Provence v. Newsom CA3
California Court of Appeal, 2023
Kravchuk v. Trelles CA6
California Court of Appeal, 2023
Teed v. Chen
N.D. California, 2022
Rotter v. Feng CA2/6
California Court of Appeal, 2022
Mewawalla v. Middleman
N.D. California, 2022
Chacon v. Union Pacific Railroad
California Court of Appeal, 2020
Modisette v. Apple Inc.
California Court of Appeal, 2018
Modisette v. Apple Inc.
241 Cal. Rptr. 3d 209 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
63 Cal. Rptr. 3d 537, 153 Cal. App. 4th 659, 2007 Cal. App. LEXIS 1208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/performance-plastering-v-richmond-american-homes-of-california-inc-calctapp-2007.