Performance Contracting, Inc. v. Rapid Response Construction, Inc.

267 F.R.D. 422, 2010 U.S. Dist. LEXIS 27331
CourtDistrict Court, District of Columbia
DecidedMarch 23, 2010
DocketCivil Action No. 2009-0639
StatusPublished
Cited by21 cases

This text of 267 F.R.D. 422 (Performance Contracting, Inc. v. Rapid Response Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Performance Contracting, Inc. v. Rapid Response Construction, Inc., 267 F.R.D. 422, 2010 U.S. Dist. LEXIS 27331 (D.D.C. 2010).

Opinion

MEMORANDUM OPINION

COLLEEN KOLLAR-KOTELLY, District Judge.

This action arises out of a contract dispute between Plaintiff Performance Contracting, Inc. (“Performance”) and Defendant Rapid Response Construction, Inc. (“Rapid”). Performance alleges that it accidentally overpaid Rapid for its work under a construction subcontract and that Rapid has refused to repay the excess money. Presently pending before the Court is Rapid’s [11] Motion to Dismiss the Complaint with Prejudice, which raises a statute of limitations defense. Performance has filed an opposition, and Rapid has filed a reply, so the motion is ripe for adjudication. However, because Rapid raised a new argument in its reply based on a settlement agreement that Performance attached to its opposition, the Court shall DENY WITHOUT PREJUDICE Rapid’s Motion to Dismiss and permit Rapid to file a new dispositive motion addressing the settlement agreement and its statute of limitations defense.

I. BACKGROUND

Performance and Rapid are both construction subcontractors authorized to do business in the District of Columbia. Compl. ¶¶ 1-2. The facts of this case revolve around a subcontract between Performance and Rapid for services related to the construction of the Embassy Suites Hotel at 1000 K Street, N.W., Washington, D.C. (the “Project”). The general contractor for the Project, Hunt Construction Group, Inc. (“Hunt”), entered into a subcontract with Performance to provide certain labor, supervision, material, and equipment for, among other things, earthworks and concrete work for the Project. Id. ¶¶ 6-7. Performance, in turn, entered into a lower-tier subcontract (the “Subcontract”) with Rapid, under which Rapid was to perform, among other things, certain earthwork and concrete work. Id. ¶ 8. Performance has attached excerpts from the Subcontract as an exhibit to the Complaint. See Compl, Ex. 1 (Subcontract Excerpts). The base value for the Subcontract was originally $4,676,355. Compl. ¶ 8. The Subcontract included a provision that Performance would withhold five percent (5%) of the final payment to Rapid until Performance was paid for this amount, called the retention, by the upper tier contractor. Compl. ¶ 9 & Ex. 1, Subcontract Attachment C § 7. As part of the Subcontract, Rapid also agreed to give Performance a security interest in its receivables, inventory, equipment, records, and other materials. Compl. ¶ 10 & Ex. 1, Subcontract Attachment G § 8.

Initially, Rapid and a company called Blake & Day Concrete Construction (“B & D”) subcontracted as a joint venture to Performance. Id. ¶ 11. However, a dispute ensued between B & D and Rapid, and B & D filed a lawsuit against Rapid, Performance, and Hunt. Id. The parties eventually settled, and as part of the settlement agreement, Hunt and Performance agreed to escrow all proceeds from contracts relating to Rapid, with Rapid and B & D to determine independently how to distribute the escrowed proceeds. Id. As a result of the settlement, as well as change order and other modifications, •the value of Rapid’s Subcontract increased to $5,292,041. Id. ¶¶ 8,11.

After the Project was closed out in 2006, Performance performed a routine audit and, in September 2006, discovered that Performance had inadvertently paid Rapid the same $166,147 retention amount twice. Compl. ¶¶ 12, 20. Performance promptly informed *424 Rapid about the double payment and sought to make arrangements for the return/refund of the extra $166,147. Id. ¶ 13. Thereafter, Performance met with officials from Rapid, who acknowledged the overpayment and began negotiating how Rapid could make the repayment to Performance. Id. ¶ 14. On February 24, 2009, Performance sent a letter via United Parcel Service (UPS) to Rapid regarding the overpayment, including documentation. Id. ¶ 15 & Ex. 3 (2/24/2009 Letter & exhibits). UPS delivered the letter package to Rapid on February 25. Compl. ¶ 15. A month later, the package was returned, having been opened and taped shut, with a notation from UPS that “RECEIVER DID NOT WANT, REFUSED DELIVERY” and indicating that the original receiver was “RAPID RESPONSE.” Id. & Ex. 5 (UPS return).

Rapid has failed or otherwise refused to refund the overpayment of $166,147. Compl. ¶ 16. In its Complaint, Performance claims that Rapid’s refusal to remit the overpayment after being notified of the double payment is a material breach of the Subcontract. See Compl. ¶¶ 17-23. Performance also claims that Rapid did not earn the $166,147 and therefore Rapid has been unjustly enriched by the accidental overpayment. See id. ¶¶ 24-30. Performance thus states claims for breach of contract (Count I) and unjust enrichment (Count II). Performance demands judgment against Rapid for $166,147.00, plus interest, attorneys’ fees, costs, and any other relief the Court deems appropriate.

II. LEGAL STANDARD

The Federal Rules of Civil Procedure require that a complaint contain “ ‘a short and plain statement of the claim showing that the pleader is entitled to relief,’ in order to ‘give the defendant fair notice of what the ... claim is and the grounds upon which it rests.’ ” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007) (quoting Conley v. Gibson, 355 U.S. 41, 47, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957)); accord Erickson v. Pardus, 551 U.S. 89, 93, 127 S.Ct. 2197, 167 L.Ed.2d 1081 (2007) (per curiam). Although “detailed factual allegations” are not necessary to withstand a Rule 12(b)(6) motion to dismiss, to provide the “grounds” of “entitle[ment] to relief,” a plaintiff must furnish “more than labels and conclusions” or “a formulaic recitation of the elements of a cause of action.” Id. at 1964-65; see also Papasan v. Allain, 478 U.S. 265, 286, 106 S.Ct. 2932, 92 L.Ed.2d 209 (1986). Instead, a complaint must contain sufficient factual matter, accepted as true, to “state a claim to relief that is plausible on its face.” Twombly, 550 U.S. at 570, 127 S.Ct. 1955. “A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, — U.S. —, 129 S.Ct. 1937, 1949, 173 L.Ed.2d 868 (2009) (citing Twombly, 550 U.S. at 556, 127 S.Ct. 1955).

In evaluating a Rule 12(b)(6) motion to dismiss for failure to state a claim, the court must construe the complaint in a light most favorable to the plaintiff and must accept as true all reasonable factual inferences drawn from well-pleaded factual allegations. In re United Mine Workers of Am. Employee Benefit Plans Litig., 854 F.Supp. 914, 915 (D.D.C.1994); see also Schuler v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lemus v. Shaffner
District of Columbia, 2023
Hu v. K4 Solutions, Inc
District of Columbia, 2020
Smith v. Mnuchin
District of Columbia, 2020
Air Transp. Ass'n of Am., Inc. v. U.S. Dep't of Agric.
303 F. Supp. 3d 28 (D.C. Circuit, 2018)
Pauling v. Dist. of Columbia
286 F. Supp. 3d 179 (D.C. Circuit, 2017)
Pauling v. District of Columbia
District of Columbia, 2017
Smith v. Rubicon Advisors, LLC
254 F. Supp. 3d 245 (District of Columbia, 2017)
Saunders v. Mills
172 F. Supp. 3d 74 (District of Columbia, 2016)
Kifafi v. Hilton Hotels Retirement Plan
107 F. Supp. 3d 154 (District of Columbia, 2015)
Baker DC, LLC v. National Labor Relations Board
102 F. Supp. 3d 194 (District of Columbia, 2015)
Loumiet v. United States of America
65 F. Supp. 3d 19 (District of Columbia, 2014)
Peart v. Latham and Watkins LLP
985 F. Supp. 2d 72 (District of Columbia, 2013)
Pricer v. Deutsche Bank
842 F. Supp. 2d 162 (District of Columbia, 2012)
Newland v. Aurora Loan Services, LLC
806 F. Supp. 2d 65 (District of Columbia, 2011)
Sykes v. US ATTORNEY FOR THE DIST. OF COLUMBIA
770 F. Supp. 2d 152 (District of Columbia, 2011)
LING YUAN HU v. George Washington University
766 F. Supp. 2d 236 (District of Columbia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
267 F.R.D. 422, 2010 U.S. Dist. LEXIS 27331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/performance-contracting-inc-v-rapid-response-construction-inc-dcd-2010.