People Ex Rel. Peters v. Murphy-Knight

618 N.E.2d 459, 248 Ill. App. 3d 382, 187 Ill. Dec. 868
CourtAppellate Court of Illinois
DecidedJune 4, 1993
Docket1 — 90—1982
StatusPublished
Cited by54 cases

This text of 618 N.E.2d 459 (People Ex Rel. Peters v. Murphy-Knight) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People Ex Rel. Peters v. Murphy-Knight, 618 N.E.2d 459, 248 Ill. App. 3d 382, 187 Ill. Dec. 868 (Ill. Ct. App. 1993).

Opinion

PRESIDING JUSTICE GORDON

delivered the opinion of the court:

This appeal arises from the dismissal pursuant to section 2 — 615 of the Code of Civil Procedure (Ill. Rev. Stat. 1991, ch. 110, par. 2— 615) of count X of plaintiff’s complaint for damages arising from the design, manufacture and installation of the heating, ventilation and air conditioning (HVAC) system in the State of Illinois Center (SOIC) in Chicago.

The first nine counts of plaintiff’s complaint, which are incorporated by reference into count X, seek recovery against the architects, engineers, construction managers, the general contractor and several subcontractors and materialmen, under the theories of professional malpractice, breach of contract, and breach of express and implied warranties. Count X seeks recovery under a theory of fraud from Chester-Jensen, which supplied, through a subcontractor, thermal banks, or ice builders, for the HVAC system.

Among the allegations from counts I through IX incorporated into count X are the following. In March 1981, the Capital Development Board (hereafter CDB) awarded a contract to furnish and install the HVAC system for the SOIC, to Economy Mechanical Industries of Illinois (hereafter EMI), a plumbing, heating and air conditioning contractor. Under the provisions of its contract with CDB, EMI was to furnish eight thermal banks and ancillary equipment meeting the State’s criteria.

On March 30, 1981, Chester-Jensen submitted a proposal to EMI for thermal banks and ancillary equipment for the HVAC system. In a submittal letter accompanying the proposal, James Donovan wrote that he was presenting Chester-Jensen’s “written proposal covering the eight (8) Ice Builders, as called for in the specifications.” The proposal stated:

“We propose to furnish the equipment specified in the following, and further described in the enclosed literature:
Model: XM — 14—14—100, eight (8) required.
Capacity: 100,000 pounds of ice at a 2½ inches ice thickness, (1200 tons latent storage).”

The literature referenced in the proposal was a brochure from Chester-Jensen entitled “Air Agitated Ice Builders” which described the principles underlying the use of ice builders as an economical and efficient method of cooling, and listed various models of ice builders offered by Chester-Jensen. The brochure included a model M — 14—14— 100, but did not list model XM — 14—14—100 as proposed by defendant.

EMI entered into a subcontract agreement with R&D Development Company, Inc. (hereafter R&D), a corporation engaged in the piping, heating, and plumbing business, for the purchase and installation of the thermal banks. EMI issued a purchase order to R&D for the purchase of eight thermal banks and ancillary equipment, and R&D, in turn, purchased the thermal banks from Chester-Jensen. The thermal banks were delivered in the spring of 1982 and installed in the SOIC sometime thereafter.

Tenants began to move into the SOIC in early 1985. That summer and the next, extremely high temperatures caused by “an inadequately designed and defectively installed and constructed air conditioning system” made the building “virtually uninhabitable.” Damages suffered as a result of the high temperatures include the expenditure of at least $10 million on modifications and repairs to the system. Plaintiff also suffered other damages of at least $5 million as a result of the extreme heat in the building, including lost rent from commercial tenants, lost work days from State employees who became ill as a result of the heat, lost productivity from State employees and excessive electrical consumption caused by the widespread use of portable electrical fans by employees and tenants.

In count X, plaintiff alleges that defendant represented in its proposal and March 30, 1981, letter to EMI, that defendant’s equipment was “capable of building one hundred pounds of ice per thermal bank in a uniform thickness of 2½ inches along each refrigerant coil, in a period of twelve hours.” These parameters constituted “Performance Specifications” developed by the CDB which proposed equipment was required to meet. Those performance specifications included the following concerning the thermal banks:

“Performance: Each of the 8 thermal banks shall be capable of making 100,000 pounds of ice in 2-½ inch thickness on the coils in 12 hours under the following conditions:
1. Initial water temperature: 42F
2. Refrigerant R-22 with 3:1 overfeed
3. Evaporating temperature: 18F
4. Nominal bank size: 10 feet high, 10 feet wide, 40 feet long.”

Plaintiff further alleged that defendant’s own literature represented that the thermal banks would perform according to the CDB’s performance specifications. The literature included the following:

“STANDARD RATING DATA
1. All ice builders are rated at 1000 pounds of ice per ton of refrigeration with nominal 12 hour building time. This means normal freezing or evaporation rate is 12,000 BTU per hour for 12 hours time to build each 1000 pounds of ice. Evaporation is usually at 20° F (3 psig.) Ice Builder capacity is based on 2½ ice thickness.
2. Maximum evaporation rate with agitation is approximately 200% of nominal rating. At maximum evaporation rate normal Ice Builder capacity could be realized in approximately 6 hours.”

Count X further alleged that defendant knew both at the time it made the above representations and when the equipment was delivered that its equipment could not meet the performance specifications set forth by the CDB. Plaintiff alleged that this knowledge is shown by a letter sent by defendant in November 1981 to another contractor concerning thermal banks proposed for a different project. In that letter, defendant wrote, “In our estimation, it is doubtful that you could recover the full complement of the Ice Builder in 12 hours when that full capacity requires a thickness of 2½ inches.”

The complaint further alleged that plaintiff was a third-party beneficiary of the contract between EMI and defendant, and that these misrepresentations were made for the purpose of inducing EMI to purchase defendant’s thermal banks. Plaintiff also alleges that it purchased the thermal banks in reliance on defendant’s misrepresentations.

Finally, plaintiff alleged that

“the thermal banks, as installed, did not meet the Performance Specifications *** in numerous ways, which included, but were not limited to the following:
a. The thermal banks were incapable of building 100,000 pounds of ice in a 12 hour time period; and
b. The thermal banks were incapable of building ice in a uniform 2½ inches thickness along the refrigerant coils.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Polinski v. Olszewski
2025 IL App (1st) 230936-U (Appellate Court of Illinois, 2025)
Owoseni v. Allstate Indemnity Co.
2025 IL App (5th) 240419-U (Appellate Court of Illinois, 2025)
FPM, LLC v. Ollmann Associates Architects, P.C.
2024 IL App (4th) 230623-U (Appellate Court of Illinois, 2024)
Süd Family Ltd. Partnership v. Otto Baum Co.
2024 IL App (4th) 220782 (Appellate Court of Illinois, 2024)
Ray v. R.A. Mechanical, Inc.
2023 IL App (1st) 221639-U (Appellate Court of Illinois, 2023)
Muhammad v. Adams Family Trucking
2023 IL App (1st) 221251-U (Appellate Court of Illinois, 2023)
Carcharadon,LLC v. Askey
N.D. Illinois, 2022
Slep-Tone Entertainment Corp. v. Elwood Enterprises, Inc.
165 F. Supp. 3d 705 (N.D. Illinois, 2015)
Slep-Tone Entertainment Corp. v. Kalamata, Inc.
75 F. Supp. 3d 898 (N.D. Illinois, 2014)
Muir v. Playtex Products, LLC
983 F. Supp. 2d 980 (N.D. Illinois, 2013)
Merrilees v. Merrilees
2013 IL App (1st) 121897 (Appellate Court of Illinois, 2013)
Pearson v. Garrett-Evangelical Theological Seminary, Inc.
790 F. Supp. 2d 759 (N.D. Illinois, 2011)
Hall v. Martin Engineering Co.
597 F. Supp. 2d 651 (S.D. West Virginia, 2009)
Village of Bensenville v. City of Chicago
Appellate Court of Illinois, 2009

Cite This Page — Counsel Stack

Bluebook (online)
618 N.E.2d 459, 248 Ill. App. 3d 382, 187 Ill. Dec. 868, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-ex-rel-peters-v-murphy-knight-illappct-1993.