FPM, LLC v. Ollmann Associates Architects, P.C.
This text of 2024 IL App (4th) 230623-U (FPM, LLC v. Ollmann Associates Architects, P.C.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
NOTICE 2024 IL App (4th) 230623-U This Order was filed under FILED Supreme Court Rule 23 and is June 12, 2024 NO. 4-23-0623 not precedent except in the Carla Bender limited circumstances allowed 4 th District Appellate under Rule 23(e)(1). IN THE APPELLATE COURT Court, IL OF ILLINOIS
FOURTH DISTRICT
FPM, LLC, ) Appeal from the Plaintiff-Appellant, ) Circuit Court of v. ) Boone County OLLMANN ASSOCIATES ARCHITECTS, P.C., d/b/a ) No. 22LA2 Ollmann Ernest Martin Architects & Engineers; ) SCANDROLI CONSTRUCTION CO.; CERONI ) PIPING COMPANY; TWIN CITY FAN COMPANIES, ) LTD., d/b/a Aerovent; and JC CROSS CO., ) Defendants, ) Honorable (Scandroli Construction Co. and Twin City Fan ) Stephen E. Balogh, Companies, Ltd., d/b/a Aerovent, Defendants-Appellees). ) Judge Presiding.
JUSTICE TURNER delivered the judgment of the court. Justices Steigmann and Knecht concurred in the judgment.
ORDER
¶1 Held: The appellate court reversed in part the trial court’s order dismissing plaintiff’s second amended complaint, holding plaintiff sufficiently pled causes of action for (1) breach of contract, (2) breach of express warranty, (3) negligence under an exception to the economic loss doctrine for sudden and dangerous events causing damages to other property, and (4) intentional and fraudulent misrepresentation.
¶2 In September 2022, plaintiff, FPM, LLC (FPM), the operator of an industrial heat
treating business, filed a second amended complaint against defendants, Ollmann Associates
Architects, P.C., d/b/a Ollmann Ernest Martin Architects & Engineers (OEM), Scandroli
Construction Co. (Scandroli), Ceroni Piping Company (Ceroni), Twin City Fan Companies,
LTD., d/b/a Aerovent (Aerovent), and JC Cross Co. (JC Cross), seeking damages based on the
failure of ventilators installed on the roof of its facility that resulted in a fire. In its complaint,
FPM alleged causes of action based on breach of contract, breach of express and implied warranties, indemnification, intentional misrepresentation, negligence, violation of the Consumer
Fraud and Deceptive Business Practices Act (Consumer Fraud Act) (815 ILCS 505/2 (West
2020)), and promissory estoppel.
¶3 Aside from OEM, all defendants moved to dismiss under section 2-615 of the
Code of Civil Procedure (Code) (735 ILCS 5/2-615 (West 2022)) for failure to state a claim.
The trial court granted the motions, dismissed the complaint with prejudice, and denied FPM’s
motion for leave to file a third amended complaint. FPM appealed, and we dismissed the appeal
against Ceroni and JC Cross for lack of jurisdiction but denied the subsequent motions to dismiss
for lack of jurisdiction brought by Scandroli and Aerovent.
¶4 On appeal, FPM contends the trial court erred by determining it failed to
sufficiently plead (1) Scandroli, as the general contractor, breached its express contractual duties
to perform the work in accordance with the contract documents, which required the procurement
and installation of a ventilation system and fans that could withstand extreme heat, including
temperatures up to 600 degrees Fahrenheit at the roofline; (2) Scandroli breached an express
warranty the materials used would conform to the requirements of the contract documents and be
free from defects; (3) Aerovent intentionally and fraudulently misrepresented the capabilities of
its roof ventilators in a product catalog and e-mail to OEM; and (4) negligence claims against
Scandroli and Aerovent based on the application of exceptions to the economic loss doctrine,
also known as the Moorman doctrine (see Moorman Manufacturing Co. v. National Tank Co., 91
Ill. 2d 69, 435 N.E.2d 443 (1982)). FPM also contends the court erred in denying its motion for
leave to file a third amended complaint.
¶5 We determine FPM sufficiently pled causes of action on all counts it raises on
appeal. Accordingly, we affirm in part, reverse in part, and remand the cause for further
-2- proceedings. Because we reverse in part and remand, we do not decide whether the trial court
erred in denying FPM’s motion for leave to file a third amended complaint.
¶6 I. BACKGROUND
¶7 On September 16, 2022, FPM filed its second amended complaint, which is the
subject of this appeal. The second amended complaint raised 22 counts. OEM filed an answer
to counts XXI and XXII, and the remaining defendants filed motions to dismiss. The complaint
and its attachments included the following facts.
¶8 FPM operates an independent commercial heat-treating facility. Generally, heat
treatment is the use of controlled heating and cooling operations to bring about a desired change
in the physical properties of a metal. FPM’s customers employ FPM’s heat-treating services to
improve the structural and physical properties for some particular use or for future work of the
metal. FPM’s heat treatment services typically involve heating the metal to extreme
temperatures to achieve the desired result, such as hardening or softening of the material.
¶9 In 2018, FPM began a project to renovate one of its facilities located in Cherry
Valley, Illinois (the plant), to house its critical heat-treating operations (the project). FPM’s
heat-treating work at the plant required the use of a variety of furnaces operating at internal
temperatures ranging from 400 to 2000 degrees Fahrenheit and from 100 to 600 degrees
Fahrenheit of external exhaust at the roof line. Thus, the plant required a specialized heat-and-
smoke-removal ventilation system capable of withstanding those temperatures. Such specialized
equipment was “part and parcel” to FPM’s operations and a vital component to safety at the
plant, because the failure or inadequate performance of such ventilation equipment threatened a
significant risk of catastrophic property damage and a threat to human life or severe bodily harm.
In particular, the failure or inadequate performance of the ventilation system could easily lead to
-3- fires and/or air-quality issues. A previous fire at the plant caused by a failure in the ventilation
system precipitated the need for FPM to perform the renovations at the plant. FPM alleged “[a]t
all relevant times, OEM, Scandroli, Ceroni, Aerovent, and JC Cross knew FPM’s Plant required
a specialized heat and smoke removal ventilation system that could withstand and operate under
the aforementioned extreme heat conditions.”
¶ 10 In December 2018, FPM entered into a contract with OEM (OEM Contract),
generally engaging OEM to serve as architect for the project. FPM contracted with Scandroli to
serve as the general contractor for the project (Scandroli Contract).
¶ 11 Under the OEM Contract, OEM’s scope of work included preparing design
drawings and construction specifications setting forth the quality levels of materials, systems,
and other requirements for construction of the plant. OEM’s designs and specifications for the
plant required a specialized ventilation system and fans that could withstand extreme heat
temperatures, ranging from 400 to 2000 degrees Fahrenheit internally, and from 100 to 600
degrees Fahrenheit of external exhaust at the roof line, which FPM alleged was “informed by its
review and approval of submittals from Scandroli.”
¶ 12 Regarding the Scandroli Contract, FPM alleged it relied on Scandroli’s
Free access — add to your briefcase to read the full text and ask questions with AI
NOTICE 2024 IL App (4th) 230623-U This Order was filed under FILED Supreme Court Rule 23 and is June 12, 2024 NO. 4-23-0623 not precedent except in the Carla Bender limited circumstances allowed 4 th District Appellate under Rule 23(e)(1). IN THE APPELLATE COURT Court, IL OF ILLINOIS
FOURTH DISTRICT
FPM, LLC, ) Appeal from the Plaintiff-Appellant, ) Circuit Court of v. ) Boone County OLLMANN ASSOCIATES ARCHITECTS, P.C., d/b/a ) No. 22LA2 Ollmann Ernest Martin Architects & Engineers; ) SCANDROLI CONSTRUCTION CO.; CERONI ) PIPING COMPANY; TWIN CITY FAN COMPANIES, ) LTD., d/b/a Aerovent; and JC CROSS CO., ) Defendants, ) Honorable (Scandroli Construction Co. and Twin City Fan ) Stephen E. Balogh, Companies, Ltd., d/b/a Aerovent, Defendants-Appellees). ) Judge Presiding.
JUSTICE TURNER delivered the judgment of the court. Justices Steigmann and Knecht concurred in the judgment.
ORDER
¶1 Held: The appellate court reversed in part the trial court’s order dismissing plaintiff’s second amended complaint, holding plaintiff sufficiently pled causes of action for (1) breach of contract, (2) breach of express warranty, (3) negligence under an exception to the economic loss doctrine for sudden and dangerous events causing damages to other property, and (4) intentional and fraudulent misrepresentation.
¶2 In September 2022, plaintiff, FPM, LLC (FPM), the operator of an industrial heat
treating business, filed a second amended complaint against defendants, Ollmann Associates
Architects, P.C., d/b/a Ollmann Ernest Martin Architects & Engineers (OEM), Scandroli
Construction Co. (Scandroli), Ceroni Piping Company (Ceroni), Twin City Fan Companies,
LTD., d/b/a Aerovent (Aerovent), and JC Cross Co. (JC Cross), seeking damages based on the
failure of ventilators installed on the roof of its facility that resulted in a fire. In its complaint,
FPM alleged causes of action based on breach of contract, breach of express and implied warranties, indemnification, intentional misrepresentation, negligence, violation of the Consumer
Fraud and Deceptive Business Practices Act (Consumer Fraud Act) (815 ILCS 505/2 (West
2020)), and promissory estoppel.
¶3 Aside from OEM, all defendants moved to dismiss under section 2-615 of the
Code of Civil Procedure (Code) (735 ILCS 5/2-615 (West 2022)) for failure to state a claim.
The trial court granted the motions, dismissed the complaint with prejudice, and denied FPM’s
motion for leave to file a third amended complaint. FPM appealed, and we dismissed the appeal
against Ceroni and JC Cross for lack of jurisdiction but denied the subsequent motions to dismiss
for lack of jurisdiction brought by Scandroli and Aerovent.
¶4 On appeal, FPM contends the trial court erred by determining it failed to
sufficiently plead (1) Scandroli, as the general contractor, breached its express contractual duties
to perform the work in accordance with the contract documents, which required the procurement
and installation of a ventilation system and fans that could withstand extreme heat, including
temperatures up to 600 degrees Fahrenheit at the roofline; (2) Scandroli breached an express
warranty the materials used would conform to the requirements of the contract documents and be
free from defects; (3) Aerovent intentionally and fraudulently misrepresented the capabilities of
its roof ventilators in a product catalog and e-mail to OEM; and (4) negligence claims against
Scandroli and Aerovent based on the application of exceptions to the economic loss doctrine,
also known as the Moorman doctrine (see Moorman Manufacturing Co. v. National Tank Co., 91
Ill. 2d 69, 435 N.E.2d 443 (1982)). FPM also contends the court erred in denying its motion for
leave to file a third amended complaint.
¶5 We determine FPM sufficiently pled causes of action on all counts it raises on
appeal. Accordingly, we affirm in part, reverse in part, and remand the cause for further
-2- proceedings. Because we reverse in part and remand, we do not decide whether the trial court
erred in denying FPM’s motion for leave to file a third amended complaint.
¶6 I. BACKGROUND
¶7 On September 16, 2022, FPM filed its second amended complaint, which is the
subject of this appeal. The second amended complaint raised 22 counts. OEM filed an answer
to counts XXI and XXII, and the remaining defendants filed motions to dismiss. The complaint
and its attachments included the following facts.
¶8 FPM operates an independent commercial heat-treating facility. Generally, heat
treatment is the use of controlled heating and cooling operations to bring about a desired change
in the physical properties of a metal. FPM’s customers employ FPM’s heat-treating services to
improve the structural and physical properties for some particular use or for future work of the
metal. FPM’s heat treatment services typically involve heating the metal to extreme
temperatures to achieve the desired result, such as hardening or softening of the material.
¶9 In 2018, FPM began a project to renovate one of its facilities located in Cherry
Valley, Illinois (the plant), to house its critical heat-treating operations (the project). FPM’s
heat-treating work at the plant required the use of a variety of furnaces operating at internal
temperatures ranging from 400 to 2000 degrees Fahrenheit and from 100 to 600 degrees
Fahrenheit of external exhaust at the roof line. Thus, the plant required a specialized heat-and-
smoke-removal ventilation system capable of withstanding those temperatures. Such specialized
equipment was “part and parcel” to FPM’s operations and a vital component to safety at the
plant, because the failure or inadequate performance of such ventilation equipment threatened a
significant risk of catastrophic property damage and a threat to human life or severe bodily harm.
In particular, the failure or inadequate performance of the ventilation system could easily lead to
-3- fires and/or air-quality issues. A previous fire at the plant caused by a failure in the ventilation
system precipitated the need for FPM to perform the renovations at the plant. FPM alleged “[a]t
all relevant times, OEM, Scandroli, Ceroni, Aerovent, and JC Cross knew FPM’s Plant required
a specialized heat and smoke removal ventilation system that could withstand and operate under
the aforementioned extreme heat conditions.”
¶ 10 In December 2018, FPM entered into a contract with OEM (OEM Contract),
generally engaging OEM to serve as architect for the project. FPM contracted with Scandroli to
serve as the general contractor for the project (Scandroli Contract).
¶ 11 Under the OEM Contract, OEM’s scope of work included preparing design
drawings and construction specifications setting forth the quality levels of materials, systems,
and other requirements for construction of the plant. OEM’s designs and specifications for the
plant required a specialized ventilation system and fans that could withstand extreme heat
temperatures, ranging from 400 to 2000 degrees Fahrenheit internally, and from 100 to 600
degrees Fahrenheit of external exhaust at the roof line, which FPM alleged was “informed by its
review and approval of submittals from Scandroli.”
¶ 12 Regarding the Scandroli Contract, FPM alleged it relied on Scandroli’s
specialized knowledge in selecting and procuring proper labor and materials for the plant.
Scandroli signed its contract with FPM on April 12, 2019. That contract, labeled as a standard
form agreement from the American Institute of Architects, provided the “Contract Documents”
and included drawings and specifications issued prior to execution of the agreement. It further
stated, “prior to the execution of this agreement, the Contractor has provided design and
constructability consultation on the Project,” which the contract referred to as the “Prior Work,”
and which was incorporated into the agreement and would comply with the standard of care.
-4- The contract stated the owner and Scandroli would work proactively with the other as necessary
to facilitate expedited development of the design and construction of the project. In the portion
of the contract pertaining to contract fees, a provision stated “the Contractor shall be paid a
$34,000 Preconstruction Services Fee for its participation in the design phase of the Project and
its completion of the Prior Work.”
¶ 13 Under the Scandroli Contract, Scandroli was required to “execute the Work
described in the Contract Documents.” The contract defined the term “Work” as follows:
“[T]he construction and services required by the Contract Documents, whether
completed or partially completed, and includes all other labor, materials,
equipment, and services provided or to be provided by the Contractor to fulfill the
Contractor’s obligations. The Work may constitute the whole or a part of the
Project.”
¶ 14 The contract further provided:
“The Contractor shall supervise and direct the Work, using The Contractor’s best
skill and attention. The Contractor shall be solely responsible for, and have
control over, construction means, methods, techniques, sequences, and
procedures, and for coordinating all portions of the Work under the Contract. If
the Contract Documents give specific instructions concerning construction means,
methods, techniques, sequences, or procedures, the Contractor shall evaluate the
jobsite safety thereof and shall be solely responsible for the jobsite safety of such
means, methods, techniques, sequences, or procedures.”
¶ 15 Regarding materials, the contract provided:
-5- “Unless otherwise provided in the Contract Documents, the Contractor shall
provide and pay for labor, materials, equipment, tools, construction equipment
and machinery, water, heat, utilities, transportation, and other facilities and
services necessary for proper execution and completion of the Work, whether
temporary or permanent and whether or not incorporated or to be incorporated in
the Work. The Contractor shall be responsible for safe storage and protection
against theft and damage of all materials until they have been properly
incorporated in the Work and of all tools and equipment owned by the Contractor
or any Subcontractor until removed from the Project site at completion of the
Work.”
Scandroli agreed to provide all services “with the degree of skill, care and diligence usually
exercised by and expected of nationally recognized contractors experienced in projects similar to
the Project in scope, size, complexity and nature.”
¶ 16 The Scandroli Contract authorized Scandroli to subcontract portions of the work it
did not typically perform. When it did so, Scandroli was required to obtain bids for the portions
of the work to be subcontracted, and “deliver such bids to [OEM] and [FPM] with a
recommendation as to which bids should be accepted.” The contract also provided Scandroli
“shall not be relieved of its obligations to perform the Work in accordance with the Contract
Documents either by the activities or duties of [OEM] in [OEM’s] administration of the
Contract, or by tests, inspections or approvals required or performed by persons or entities other
than [Scandroli].” Additionally, Scandroli agreed to “be responsible to [FPM] for acts and
omissions of [Scandroli’s] employees, Subcontractors and their agents and employees, and other
persons or entities performing portions of the Work for, or on behalf of, [Scandroli] or any of its
-6- Subcontractors.” Thus, FPM alleged “by nature of acting as general contractor for the Project,
Scandroli had ultimate responsibility for the performance of the Work regardless of the actions
of any other, including OEM, FPM, any subcontractors of Scandroli, or any sub-subcontractors
of Scandroli.”
¶ 17 The contract contained the following express warranty provision:
“The Contractor warrants to [FPM] and [OEM] that materials and equipment
furnished under the Contract will be of good quality and new unless the Contract
Documents require or permit otherwise. The Contractor further warrants that the
Work will conform to the requirements of the Contract Documents and will be
free from defects, except for those inherent in the quality of the Work the
Contract Documents require or permit. Work, materials, or equipment not
conforming to these requirements may be considered defective. The Contractor’s
warranty excludes remedy for damage or defect caused by abuse, alterations to
the Work not executed by The Contractor, improper or insufficient maintenance,
improper operation, or normal wear and tear and normal usage.”
In addition, Scandroli agreed that all special warranties required by the contract documents
would be issued in the name of FPM or be transferrable to FPM. The contract also contained an
indemnification provision.
¶ 18 In July 2019, Scandroli subcontracted with Ceroni to provide material and labor
for the installation of the ventilation system to evacuate heat from the plant. FPM alleged
Scandroli failed to obtain an executed warranty by Ceroni in favor of FPM, even though the
contract with Scandroli contained a template for such a warranty.
-7- ¶ 19 FPM alleged, as part of their respective scopes of work and purported expertise,
Scandroli and Ceroni were responsible for procuring and installing a ventilation system with fans
that could meet FPM’s stated needs and withstand the extremely high-heat environment of the
plant. Scandroli procured, through Ceroni, a series of ventilation fans manufactured by
Aerovent, and FPM paid Scandroli a sum that included Ceroni’s procurement and installation of
the ventilators. FPM alleged Aerovent and its agent, JC Cross, represented the ventilation fans
were capable of effectively operating in the high-heat environment of the plant. In particular,
FPM alleged Aerovent and JC Cross made express representations regarding the capabilities of
the ventilators in Aerovent’s product specification catalog and in a June 2019 e-mail from JC
Cross to OEM. FPM alleged “[s]uch representations included that the Aerovent fans were
designed, tested, and capable of withstanding extreme temperatures of 600 [degrees
Fahrenheit].”
¶ 20 FPM included Aerovent’s product specification catalog as an exhibit to the
complaint. That catalog stated the following concerning the roof ventilator at issue in this case:
“The Model SV40 combines year-round powered ventilation with smoke
and heat removal capabilities. This ventilator is designed to be used as a standard
roof exhaust fan and a high temperature smoke and heat removal fan. It is a
three-part assembly consisting of:
1. Stack cap damper assembly with fusible link kit
2. Curb base
3. High temperature, belt driven tubeaxial fan with a welded steel
propeller[.]”
The catalog also stated:
-8- “The Model SV40 high temperature roof ventilator is designed
specifically to comply with Industrial Risk Insurers’ (IRI) recommendations for
smoke and heat ventilation and is UL Certified for Smoke Control Systems.
Unit testing was conducted at Aerovent’s certified test lab using a 4
million BTU gas fired burner capable of generating airstream temperatures in
excess of 1000 [degrees Fahrenheit]. Airstream temperatures were precisely
monitored using potentiometers with chromel-alumel thermocouples.
Temperatures were monitored at several vital areas within the ventilator
assembly: inlet side of the fan wheel, fan bearings, bearing housing, belt tube, and
the motor compartment.
Based on this extensive testing, the Model SV40 is capable of
withstanding continuous operation at 600 [degrees Fahrenheit], extended
operating periods at 800 [degree Fahrenheit] and 8 hours or more with an
airstream temperature of 1000 [degrees Fahrenheit].”
Another page of the catalog stated, “SV40 Smoke and Heat Roof Ventilators shall be designed to
withstand continuous operation with internal airstream temperatures of 600 [degrees Fahrenheit]
and a minimum of 8 hours with internal airstream temperatures of 1000 [degrees Fahrenheit].” It
further stated. “Ventilators shall be tested and certified in accordance with industry accepted test
codes and guaranteed by the manufacturer to deliver at the rated published performance levels.
In addition, each unit shall be factory run tested prior to shipment.” The catalog also stated:
“High temperature construction features shall include a heat slinger cast of A240
high temperature aluminum alloy. This radial bladed heat sink fan wheel shall
draw cooling air from the exterior of the fan housing through the drive tube and
-9- over the bearings, absorbing and dissipating shaft heat. A heat shield shall be
provided to protect the motor from radiated heat.
Sheaves shall be cast iron with two heat-resistant static conducting belts.
Bearings and belts are enclosed in an air insulated housing for protection.”
¶ 21 Exhibit No. 5 which was attached to the complaint, included diagrams of two
different sizes of SV40 ventilators. The exhibit included Scandroli’s logo with a box stating
“reviewed” checked underneath. The exhibit also had a stamp from OEM with a box checked
that read “reviewed without comment.” The diagrams showed the motor and bearings housed in
a box protruding from a cylinder which contained the fan assembly. Drawings of the ventilators
included an arrow pointing up that stated “airflow” outside of the drawing of the ventilator as a
whole. One could infer from the drawing that the “airflow” is the movement of air through the
cylinder and not the box that protrudes from the side. However, other inferences could be the
“airflow” encompasses the entire assembly or is only the flow of air outside of the assembly. A
definition of “airstream” or “airflow” was not provided. One page of the exhibit included a
table labeled “Performance ‘A’ ” and included a difficult to read box with “70 [degrees
Fahrenheit]” written inside. A second page had the same table for a different size of the
ventilator but had “600 [degrees Fahrenheit]” written inside.
¶ 22 FPM alleged, “Upon information and belief, Aerovent knew at all relevant times
prior to the sale of its fans for use at the Plant that the aforementioned representations in its
product specification catalog were false and misleading.” FPM also alleged Scandroli and
Ceroni selected the fans based on the representations made by Aerovent. Based on the product
literature, Ceroni submitted Aerovent’s fans for approval to Scandroli, who approved them and
- 10 - sent them to OEM for approval. OEM then approved the submittal, allowing Scandroli to
purchase the fans for installation at the plant.
¶ 23 In a June 13, 2019, e-mail between a representative of OEM and a representative
of JC Cross, the OEM representative wrote, “I’m looking at the fan submittals and under
performance two of them have 70 [degrees Fahrenheit] as the temperature, and the other has 600
[degrees Fahrenheit] as the temperature. That’s just the air temperature the fan performance was
selected at, not the fans actual temperature rating correct?” The JC Cross representative replied,
“That is correct. The fans are all designed for 600 degrees. That’s what we were confirming
yesterday.” FPM alleged “Upon information and belief, Aerovent and JC Cross knew at all
relevant times prior to the sale of the Aerovent fans for use at the Plant that the above statement
of [JC Cross’s representative] was false and misleading.” FPM further alleged Aerovent made
the alleged misrepresentations for the purpose of inducing approval of the fans by FPM and its
contractors, and FPM relied on those misrepresentations when approving and purchasing the
fans.
¶ 24 After the fans were installed, and shortly after resuming heat-treating operations
at the plant, the Aerovent fans began to fail. FPM alleged, as of the time of the filing, 25 of the
26 Aerovent fans installed on FPM’s roof had failed. After the first three or four failures, FPM
requested the construction team, including Aerovent, to investigate the failures and determine the
root cause of the failures. An investigation done by Aerovent generally determined the fans were
failing due to their inability to continuously operate under the high-heat conditions of the plant.
As part of the investigation, Aerovent released two reports to FPM regarding the fan failures,
which FPM included as exhibits attached to the complaint.
- 11 - ¶ 25 In a report dated December 19, 2019, Aerovent noted “Heat treat process operates
24 hrs/day / 7 days/wk / 365 days/yr.” Aerovent also noted “Only (1) of the fans in each
production row has direct line‐of‐sight to process flame (radiant heat), and it appears that the
radiant heat has not raised the bearing temperature beyond the design limit of 475 [degrees
Fahrenheit].” The report stated “Failed motors have melted plastic components (cooling fan and
fan cover). Aerovent is arranging to send at least one of the failed motors for 3rd party
inspection to confirm that no other mode of failure occurred.” It also noted “VFD labeled ‘B7
HF CHARGE END EX FAN’ appeared to have been set for 29.36Hz. If this is considered
normal operation, it will reduce the speed of the fan and the cooling effect on the fan bearings
and motor casing.” For the “Root Cause” of the failures, Aerovent wrote:
“Aerovent S/N 636613‐1‐3 failed from bearing failure after exposure to an
internal bearing temperature greater than 500 [degrees Fahrenheit]. This
temperature is known to exceed the design limits of the fan. The bearings may
or may not have survived if the fusible link on the outlet damper had functioned
properly (it did not break at 165 [degrees Fahrenheit] as designed). Fusible links
are suitable only for emergency smoke exhaust applications, not for continuous
high temperature. The fusible link was added to each fan due to a BOM linking
error, which has been corrected by Aerovent as of 12/16/2019.”
Aerovent added:
“The root cause of the other (4) failed units is not yet officially determined.
Aerovent and Ceroni are working to have at least one of the failed motors
inspected by a 3rd party. We observe that the motors were exposed to
temperatures beyond their design limit, but whether the heat originated from the
- 12 - process or from internal electrical sources is unclear. Aerovent will follow up
with an addendum to this report as soon as we receive inspection results ***.”
¶ 26 In a report dated December 27, 2019, Aerovent noted, “Two (2) of the failed
motors were inspected by a 3rd party Electrical Apparatus Service Association (EASA)
accredited shop and found to have shorted windings. Further analysis is required to find root
cause of the winding shortage, and Aerovent is working with WEG to determine.” The record
does not specify the meaning of the acronym “WEG.” Aerovent also wrote:
“The root cause of the other (4) failed units were due to motor failures. The root
cause of motor failure was found to be a short in the internal electrical windings.
What caused the short is difficult to prove, but likely cause appears to be the
thermal breakdown of the plastic cooling fan cover due to radiant heat emitted
from the fan housing.”
Aerovent made various recommendations, including replacing the motors with models featuring
steel cooling fan covers, because “[t]he steel material can withstand the radiant heat and allow
the cooling fan to continue to pass ambient air over the motor components.” Aerovent also
suggested FPM consider spot checking the air temperature emitted from the belt tube of any fan
that had a motor operating below 60Hz for air balance purposes. Aerovent wrote, if the air
temperature was higher than 245 degrees Fahrenheit, FPM should consider increasing the motor
operating frequency as “this increases the cooling effect on the bearings.” Aerovent also wrote,
“If the belt tube air temperature rises above 300 [degrees Fahrenheit] for longer than an hour, it
may begin to affect the motor integrity.” Aerovent also recommended a preventative
maintenance schedule.
- 13 - ¶ 27 FPM alleged the reports established Aerovent and JC Cross initially
misrepresented the capabilities of the Aerovent fans. FPM alleged Aerovent’s position that 300
degrees Fahrenheit exceeded the maximum operation temperature for the belts was “at war with
its earlier representations and promises that the fans were designed to, and in fact could,
withstand continuous operation at internal and external temperature far exceeding 300 [degrees
Fahrenheit].” FPM also noted Aerovent’s statement the “design limit” for the fan bearings was
475 degrees Fahrenheit and alleged failures of the bearings had been observed on multiple
occasions in multiple locations at temperatures significantly less than that amount. FPM included
a photograph of a failed fan bearing. FPM alleged it requested “the testing and backup” for
Aerovent’s asserted “design limit” for the bearings, but Aerovent responded it did not have that
data.
¶ 28 FPM also noted Aerovent admitted one of its fans failed because the temperatures
inside the fan exceeded 500 degrees Fahrenheit, which exceeded the design limits of the fan.
FPM alleged that admission showed “Aerovent’s fans were never designed to operate with
internal temperatures exceeding 500 [degrees Fahrenheit].” Thus, FPM argued the admission
plainly established Aerovent’s prior representations the fans were designed to withstand
continuous temperatures of at least 600 degrees Fahrenheit were knowingly false.
¶ 29 FPM further stated it had “reason to believe that Aerovent’s representations
regarding its testing of the subject fans were false and misleading given its inability to provide
documentation as requested.” FPM alleged, after the fans began to fail, FPM asked Aerovent to
produce evidence of the “ ‘extensive testing’ ” it purportedly conducted to ensure the fans were
“ ‘capable of withstanding continuous operation at 600 [degrees Fahrenheit], extended operating
periods at 800 [degrees Fahrenheit] and 8 hours or more with an airstream temperature of 1000
- 14 - [degrees Fahrenheit],’ as represented in its product specification catalog.” In response, Aerovent
informed FPM that it could not locate any supporting documentation. FPM alleged, “Aerovent’s
response leads FPM to believe that Aerovent never conducted any such testing and, therefore,
that the statement in Aerovent’s product specification catalog regarding its ‘extensive testing’ of
the fans was at all times blatantly false.” Thus, FPM further alleged Aerovent, and its agent JC
Cross, knew before selling the Aerovent ventilators for use at the plant the fans were not capable
of performing under extreme heat conditions, as represented and required.
¶ 30 On January 7, 2021, Aerovent fans failed, causing a sudden and dangerous fire to
break out at the plant. FPM alleged the fire caused damage to “other property,” including
burning and/or charring to the interior surface of the belt rooms at the plant. The fire also caused
damage to roof curbs and wood nailers, and it forced FPM to shut down operations, causing
damage to FPM property other than the fans themselves of over $250,000. The failure of the
fans also led to air quality issues at the plant. In order to protect its employees, and under
Occupational Safety and Health Administration requirements, FPM was forced to take
emergency measures, including shutting down equipment and ventilating the area with surface
fans and structure openings to remediate the air quality issues. FPM alleged, had it “not taken
emergent protective measures in response to the various aforementioned fan failures, there would
have been extreme risk of catastrophic, life-threatening personal injury, and entire loss of
property at the Plant.”
¶ 31 Based on its factual allegations against Scandroli, FPM alleged breach of contract,
breach of express warranty, breach of implied warranty, indemnification, and negligence.
Against Aerovent, FPM alleged negligence, negligent misrepresentation, intentional
- 15 - misrepresentation/fraud, promissory estoppel, and a violation of the Consumer Fraud Act. It also
alleged similar causes of action against the other defendants.
¶ 32 OEM filed an answer, and the remaining defendants filed motions to dismiss
under section 2-615 of the Code for failure to state a claim (see 735 ILCS 5/2-615 (West 2022)).
In support of its motion to dismiss counts I through V, Scandroli argued FPM failed to state a
claim for breach of contract because the contract did not require Scandroli to choose the
ventilation fans. Instead, as the general contractor, Scandroli was required to install the fans
selected by OEM, and FPM did not allege they were installed incorrectly. Scandroli further
argued it did not fail to obtain a warranty from Ceroni because its contract with Ceroni contained
a standard warranty, and neither Ceroni nor Scandroli could be held responsible for
misrepresentation or concealment of facts by another party or for materials they had no control
over selecting. Likewise, Scandroli argued it could not provide an express warranty for material
specifications it had no control in designing or selecting.
¶ 33 Regarding the existence of an implied warranty, Scandroli noted it was not the
seller of the goods, and FPM did not rely on its skill or judgment to select the goods, because it
expected Scandroli to subcontract for work it did not normally perform. Scandroli further argued
FPM did not allege negligent installation, and thus, Scandroli had no duty to indemnify FPM.
Finally, Scandroli argued FPM could not state a claim for negligence because, under the
economic loss doctrine as stated in Moorman, FPM could not assert tort claims to cover
economic losses. Scandroli argued an exception to the doctrine for sudden and calamitous
events causing damage to other property was not applicable because the fans deteriorated over
time instead of in a sudden event.
- 16 - ¶ 34 In a memorandum in support of its motion to dismiss counts XI through XV,
Aerovent also argued FPM failed to state claims for negligence under the economic loss
doctrine. Aerovent argued the promissory estoppel claim failed for the same reason because it
was also a repackaged negligence claim and, in the alternative, no promise had been alleged. As
to fraudulent misrepresentation and the Consumer Fraud Act, Aerovent argued FPM failed to
state its claim with sufficient particularity or specificity. Aerovent also provided a diagram from
the exhibits attached to the complaint with added hand-drawn markings and an argument the fact
that individual components of the ventilators could not withstand 600 degrees Fahrenheit did not
show the ventilator as a whole could not operate at 600 degrees Fahrenheit.
¶ 35 At the hearing on the motions, the trial court expressed concern FPM was
attempting to hold Scandroli, acting as the general contractor, liable for knowing the fans would
not operate under temperatures reaching 600 degrees, stating OEM approved the fans, and
Scandroli was simply given the equipment and told to install it. In a written order, the court
granted the motions to dismiss. The court generally found the economic loss doctrine barred the
negligence claims against all parties and no exception applied. As to Scandroli, the court found,
reading the contract as a whole, while Scandroli was to ensure materials and equipment were of
good quality and in conformance with the contract documents, it did not agree to undertake
anything more than supervisory authority. The court found there was no allegation Scandroli
should have known anything about the design of the ventilators or that the contract documents
allowed Scandroli to deviate from specifications for them. In particular, addressing FPM’s
argument the ventilators were not in conformance with contract specifications, the court wrote,
“What FPM does not allege, however, is that Scandroli either had or agreed to have any
involvement in the details—the design and manufacture—of the equipment.” The court also
- 17 - found there was no allegation the ventilators were not installed in conformance with the contract
documents. Regarding warranties, the court next found Scandroli was not the seller of the
ventilators and did not promise the ventilators would conform to the contract documents, and
there was no evidence that it even knew what the specific description of the assembled
ventilators entailed. The court also found FPM had no contractual right of indemnification.
¶ 36 As to Aerovent, the trial court found FPM’s claim of misrepresentation failed
because Aerovent’s recommendation of its product was a mere opinion and not actionable as
fraud. Citing People ex rel. Peters v. Murphy-Knight, 248 Ill. App. 3d 382, 388-89, 618 N.E.2d
459, 464 (1993), the court further stated FPM failed to plead anything factual to show Aerovent
did anything “other than express the capabilities of its products based on application of
mathematical formulae and physical properties” of the plant “and the known characteristics of its
own industrial ventilators.” The court then noted the product catalog referred to the ability of the
ventilation system to operate continuously with “internal airstream temperatures” of 600 degrees
Fahrenheit. The court wrote:
“The brochure also explains that the internal components of the system, including
the motor, are isolated from the airstream, protected by a heatshield and cooled by
a ‘radial bladed heat sink fan wheel’ which draws cooling air from the exterior of
the fan housing through the drive tube and over those components.”
Referring to exhibit No. 5, the court stated, “Review of the drawings reveals the isolated—out of
the airstream—components of the system where the problems are believed to have occurred.”
The court also noted the investigation reports referred to failed internal components and heat
above the designed operating temperatures within the internal component housing. The court
stated the reports did not make reference to the failure of any component within the airstream of
- 18 - the system and did not identify a cause of the failures but did make recommendations regarding
improved shielding and preventive maintenance.
¶ 37 The trial court then wrote:
“The alleged misrepresentation was that Aerovent represented that the systems
could operate continuously with an internal airstream temperature of 600 [degrees
Fahrenheit]. There is a difference, as evidenced in the drawings and
specifications, between the internal airstream of the ventilator and the internal
components of the ventilator which are outside of the airstream, protected by
cooling a fan, a cross draft of outside air and a heatshield.
Taking the pleadings as a whole and including the exhibits, FPM has pled,
very specifically, that Aerovent represented that its system would operate with an
internal airstream (the air within the duct) of up to 1000 [degrees Fahrenheit] for
up to eight hours. There is nothing affirmatively pled or in the exhibits that tends
to show that this specific representation is untrue. To the contrary, the brochure
and specifications in Aerovent’s proposal, both of which are part of the pleadings,
are very specific and clearly separate the operating characteristics of the system’s
internal airstream from those shielded and cooled internal components of the vent.
In context, ‘[u]nder the allegations of the complaint, the representations
concerned a machine of known physical characteristics and its capabilities based
upon the application of certain mathematical formulae and laws of physics to
those physical properties.’ Peters, 248 Ill. App. 3d at 388-89.”
The court further found FPM failed to sufficiently plead knowledge, holding FPM’s allegation
Aerovent knew or should have known the representations were false at the time they were made,
- 19 - without factual support, was an “unsupported conclusion.” The court next rejected FPM’s
promissory estoppel and Consumer Fraud Act claims.
¶ 38 On April 20, 2023, FPM filed motions for reconsideration and for leave to file a
third amended complaint, with the proposed third amended complaint attached as an exhibit.
That complaint sought to add new claims under the Uniform Commercial Code (810 ILCS 5/1-
101 et seq. (West 2020)). FPM also sought to clarify Scandroli was paid for its warranty and
supervision of subcontractors’ work, and had recommended and approved the Aerovent
ventilators. FPM also added allegations Scandroli breached its warranty by improperly installing
the ventilators.
¶ 39 JC Cross and Ceroni moved for a finding under Illinois Supreme Court Rule
304(a) (eff. March 8, 2016) that there was no just reason to delay enforcement or appeal of the
order dismissing the complaint against them. On April 24, 2023, the trial court granted that
motion and made such a finding.
¶ 40 On June 15, 2023, the trial court denied the motion to reconsider, stating at the
end of its order, “The court has noted twice that FPM’s remedies, if any, are found in contract
under the Uniform Commercial Code.” The court, in the same order, without analysis, denied
the motion for leave to file a third amended complaint “without prejudice.” The court added,
under Rule 304(a), there was no just cause for delay of enforcement or appeal.
¶ 41 On June 28, 2023, FPM moved for clarification regarding the denial of the motion
for leave to amend and jurisdiction. On June 30, 2023, the parties met for a hearing and
discussed concerns about the interplay of filing amended pleadings against all defendants while
also seeking to appeal. The trial court stated, had it granted the motion to reconsider, it would
have allowed the amended pleading. The court entered an amended order stating the motion for
- 20 - leave to file an amended complaint was denied, removing the “without prejudice” language, and
listing the order as final as to JC Cross, Ceroni, Scandroli, and Aerovent.
¶ 42 This appeal followed. We granted motions to dismiss for lack of jurisdiction
made by Ceroni and JC Cross. As such, the trial court’s dismissal of counts VI through X and
XVI through XX are no longer at issue in this appeal. However, we denied motions to dismiss
made by Scandroli and Aerovent. Accordingly, we address only FPM’s arguments concerning
Scandroli and Aerovent on appeal.
¶ 43 II. ANALYSIS
¶ 44 On appeal, FPM contends the trial court erred by granting defendants’ motions to
dismiss under section 2-615 the Code and determining FPM failed to sufficiently plead
(1) Scandroli, as the general contractor, breached its express contractual duties to perform the
work in accordance with the contract documents, which required the procurement and
installation of a ventilation system and fans that could withstand extreme heat, including
temperatures up to 600 degrees Fahrenheit at the roofline; (2) Scandroli breached an express
warranty the materials used would conform to the requirements of the contract documents and be
free from defects; (3) Aerovent intentionally and fraudulently misrepresented the capabilities of
its roof ventilators in a product catalog and an e-mail to OEM; and (4) negligence claims against
Scandroli and Aerovent based on application of the economic loss doctrine. FPM also contends
the court erred in denying its motion for leave to file a third amended complaint. On appeal,
FPM does not challenge the dismissal of the claims asserting breach of implied warranty (count
III), indemnification (count IV), promissory estoppel (count XIV), and a violation of the
Consumer Fraud Act (count XV). Accordingly, we do not address the court’s dismissal of those
claims.
- 21 - ¶ 45 A motion to dismiss under section 2-615 of the Code challenges only the legal
sufficiency of the complaint. Schloss v. Jumper, 2014 IL App (4th) 121086, ¶ 20, 11 N.E.3d 57.
In ruling on a section 2-615 motion to dismiss, “the question is ‘whether the allegations of the
complaint, when construed in the light most favorable to the plaintiff, are sufficient to establish a
cause of action upon which relief may be granted.’ ” Green v. Rogers, 234 Ill. 2d 478, 491, 917
N.E.2d 450, 458-59 (2009) (quoting Vitro v. Mihelcic, 209 Ill. 2d 76, 81, 806 N.E.2d 632, 634
(2004)). The trial court should not grant a motion to dismiss “unless it is clearly apparent that no
set of facts can be proved that would entitle the plaintiff to relief.” Tedrick v. Community
Resource Center, Inc., 235 Ill. 2d 155, 161, 920 N.E.2d 220, 223 (2009).
¶ 46 When ruling on a section 2-615 motion, “[t]he only matters to be considered ***
are the allegations of the pleadings themselves.” Illinois Graphics Co. v. Nickum, 159 Ill. 2d
469, 485, 639 N.E.2d 1282, 1289 (1994); see Cwikla v. Sheir, 345 Ill. App. 3d 23, 29, 801
N.E.2d 1103, 1109 (2003) (“In ruling on a section 2-615 motion, the court may not consider
affidavits, products of discovery, documentary evidence not incorporated into the pleadings as
exhibits, or other evidentiary materials.”). A document that is attached to a complaint as an
exhibit is “considered to be part of the pleading, and facts stated in the exhibit are considered as
having been alleged in the complaint.” Tucker v. Soy Capital Bank & Trust Co., 2012 IL App
(1st) 103303, ¶ 22, 974 N.E.2d 820. “[M]atters contained in such exhibits which conflict with
allegations of the complaint negate any contrary allegations of the complaint.” (Internal
quotation marks omitted.) Tucker, 2012 IL App (1st) 103303, ¶ 23. We review a dismissal
under section 2-615 de novo. Beacham v. Walker, 231 Ill. 2d 51, 57, 896 N.E.2d 327, 331
(2008).
¶ 47 A. Breach of Contract Claims Against Scandroli (Count I)
- 22 - ¶ 48 FPM first contends the trial court erred in dismissing its breach of contract claims
against Scandroli. FPM argues it sufficiently pled the contract documents made Scandroli
responsible for “the Work” and “the Prior Work,” which included Scandroli’s expertise in the
selection, installation, and warranty related to the ventilation equipment for the facility. FPM
further notes it alleged reliance on Scandroli’s expertise and contracted to pay Scandroli for
participation in the design phase of the project as part of the prior work. FPM argues Scandroli
was at least partly responsible for recommending and procuring a ventilation system that could
meet the needs of the plant, and Scandroli approved the submittal of the fans from Ceroni and
submitted those fans to OEM, who then approved the submittal based on Scandroli’s advice.
Scandroli, however, argues it did not design the project and was not given project specifications.
Instead, Scandroli argues, under the definition of “the Work” in the contract, all it was required
to do was adhere to the design specifications as identified by OEM and build according to the
designs and specifications it was given.
¶ 49 The elements to state a cause of action for breach of contract are (1) offer and
acceptance, (2) consideration, (3) definite and certain terms, (4) performance by the plaintiff of
all required conditions, (5) breach, and (6) damages. Barille v. Sears Roebuck & Co., 289 Ill.
App. 3d 171, 175, 682 N.E.2d 118, 121 (1997). At issue here is whether FPM sufficiently pled
there was a breach, which is dependent on whether it sufficiently pled Scandroli agreed to
procure fans sufficient to meet the needs of the plant.
¶ 50 The determination of the intent of the parties to a contract may either be a
question of law or fact. Terracom Development Group, Inc. v. Coleman Cable & Wire Co., 50
Ill. App. 3d 739, 743, 365 N.E.2d 1028, 1031 (1977). If the language in a contract is ambiguous,
then the determination of its meaning is a question of fact and not to be resolved by a section 2-
- 23 - 615 motion to dismiss. Monroe Dearborn Ltd. Partnership v. Board of Education of City of
Chicago, 271 Ill. App. 3d 457, 462, 648 N.E.2d 1055, 1058 (1995). If, however, the language in
the contract is unambiguous, then the construction of the alleged contract is a question of law.
Monroe Dearborn, 271 Ill. App. 3d at 462, 648 N.E.2d at 1058. In addition, the Illinois Supreme
Court has stated:
“The primary object in construing a contract is to give effect to the
intentions of the parties involved. Their intent must be determined solely from
the language used when no ambiguity in its terms exists, and a strict construction
of that language which reaches a different result from that intended by the parties
should not be adopted.” Schek v. Chicago Transit Authority, 42 Ill. 2d 362, 364,
247 N.E.2d 886, 888 (1969).
¶ 51 Here, the trial court found, while Scandroli was to ensure the materials and
equipment were of good quality and in conformance with the contract documents, it did not
agree to any involvement in the design and manufacture of equipment for the project. The court
further found there was no allegation Scandroli should have known anything about the design of
the ventilators or that the contract documents allowed Scandroli to deviate from the
specifications for the ventilators. The court also found there was nothing pled or in the exhibits
suggesting Scandroli had or undertook anything more than general supervisory authority.
However, those findings ignored portions of the contract stating explicitly otherwise.
¶ 52 Contrary to the trial court’s finding, FPM did specifically allege Scandroli was
directly involved with the design and specifications of the project. Per the contract, the “contract
documents” included drawings and specifications issued prior to execution of the agreement. It
further stated, “prior to the execution of this agreement, [Scandroli] has provided design and
- 24 - constructability consultation on the Project,” which the contract referred to as the “Prior Work.”
In addition, the contract provided a substantial payment for preconstruction participation in the
design phase of the project and the prior work. In its complaint, FPM alleged it relied on
Scandroli’s expertise and specifically alleged Scandroli and Ceroni were responsible for
procuring a specialized heat and smoke removal ventilation system that could meet FPM’s stated
needs. Scandroli approved the submittal of the ventilators from Ceroni and submitted those to
OEM, who approved the submittal. The court made no mention of these provisions, which
contradict the court’s determination and provide allegations Scandroli was contracted to use its
expertise to recommend and provide ventilators sufficient to meet the needs of the project. Thus,
while the court was correct that Scandroli did not design the Aerovent ventilation system, it
failed to recognize that FPM alleged Scandroli was instrumental in selecting and recommending
the system as part of its contractual obligations.
¶ 53 Nevertheless, in the trial court, and in its brief on appeal, Scandroli asserted it did
not “come up with the design” and was not given the specifications for the design. It also asserts
the contract stated Scandroli was to adhere to the design specifications in the contract
documents, as identified by the architects and engineers at OEM. Scandroli does not provide a
citation to the location in the contract for those assertions other than pointing to its own argument
to the court at the hearing on the motion to dismiss. We have found no such provisions in the
contract. In any event, even if the contract contained such provisions, Scandroli’s argument
ignores FPM’s allegations that Scandroli did indeed take part in the design of the project and was
paid for its “Prior Work” in doing so. At best, Scandroli’s arguments raise issues of fact as to the
intent of the parties concerning the contract, which are not appropriately decided in a section 2-
615 motion to dismiss.
- 25 - ¶ 54 Had the contract not contained provisions concerning “Prior Work,” and had there
been no allegations or evidence Scandroli contracted to provide design consultation for the
project and recommend equipment based on its expertise, the trial court’s determination would
arguably have been well founded. But here, where FPM alleged Scandroli was involved in the
design and tasked with recommending and procuring proper equipment to meet that design based
on its specific expertise, and that equipment later turned out not to function to specifications,
with an inference that was perhaps through a misunderstanding of the abilities of equipment,
FPM alleged sufficient facts to plead a cause of action for breach of the contract. To be sure, the
full extent of Scandroli’s participation in the design of the project and choice of the ventilators is
not fully known, as it is unknown whether the equipment itself was faulty, the choice in
procuring it was poorly made by Scandroli or another party, or if user error on the part of FPM
led to the failures. But at this juncture, we must take the facts pled by FPM as true. When we do
so, it is not clearly apparent that no set of facts can be proved that would entitle plaintiff to relief.
Accordingly, the court’s dismissal of the breach of contract claim at this juncture was in error.
¶ 55 B. Express Warranty Claims Against Scandroli (Count II)
¶ 56 FPM next argues the trial court erred in dismissing its express warranty claim
against Scandroli. The court denied the warranty claim, stating an express warranty is made by a
seller to a buyer based on a contractual promise the goods shall conform to their description.
The court found FPM did not allege Scandrioli promised anything about whether the ventilators
would conform to their description or even knew what the specific description of the ventilators
entailed.
¶ 57 As previously discussed, FPM alleged Scandroli took part in the design of the
project and recommended and procured the ventilators. Scandroli’s approval appears on an
- 26 - exhibit showing the design and specifications of the ventilators. Meanwhile, Scandroli was not
warranting the ventilators as a seller, but instead as a contractor guaranteeing his work. In that
regard, FPM needed only to allege Scandroli failed to comply with the guarantees set forth in the
contract, as it has been held a contractor is responsible for the work guaranteed, whether the
defect is due to the contractor’s work or that of a third person. Intaglio Service Corp. v. J. L.
Williams & Co., 95 Ill. App. 3d 708, 712, 20 N.E.2d 634, 637 (1981). In particular, the First
District, in Intaglio, stated:
“No reason is perceived why contractors may not guarantee against all defects,
whatever their origin, whether they arise from insufficiency of the materials
supplied, from unskillfulness of workmen, or from unfitness of the plan or design,
whether devised by the one or the other of the parties to the contract, or by some
other person. In case of a contract with such warranty, it will be presumed that
the consideration for the guaranty was included in the price agreed to be paid for
the work to be done. It is not unreasonable to suppose that one desiring a fabric
or structure, or an apparatus, or a piece of mechanism to be made, the idea of
which is his own or that of his servant or agent, may wish to take the judgment as
to its practicability, usefulness and durability, of some person or persons who
have a practical knowledge and experience in the construction of things of that
sort, and in such case the requirement of a guaranty would be an effectual way of
getting the benefit of such judgment. It is the province of the courts to enforce the
contract which the [parties] have made, not to make a contract for them. It must
be presumed, that had it been their intention to limit the guaranty to the
workmanship of the contractors and their servants, and to the materials furnished,
- 27 - such intention would have been expressed in the contract.” (Internal quotation
marks omitted.) Intaglio, 95 Ill. App. 3d at 712-13, 20 N.E.2d at 638.
¶ 58 Here, Scandroli warranted the “Work,” which under the Scandroli Contract
included all labor, materials, and equipment. FPM alleged Scandroli took part in recommending
and procuring the ventilators, and the Scandroli Contract included a warranty the “Work,”
materials, and equipment would conform to the requirements of the contract documents and be
free from defects. The contract further provided equipment not conforming to those
requirements may be considered defective. FPM alleged the ventilators did not conform to the
contract documents, which included the provision of ventilators capable of operating at
temperatures of 600 degrees Fahrenheit. Thus, FPM sufficiently pled facts to support a claim for
breach of warranty based on the alleged failure of the ventilators, which it asserted was
encompassed by the terms “Work,” materials, or equipment under the contract.
¶ 59 C. Intentional Misrepresentation Claim Against Aerovent (Count XIII)
¶ 60 FPM next argues the trial court erred in determining it failed to sufficiently plead
Aerovent knowingly made false statements of material fact. Citing primarily Spiegel v. Sharp
Electronics Corp., 125 Ill. App. 3d 897, 466 N.E.2d 1040 (1984), and Peters, the court noted
mere recommendations of a product or opinion were not representations of fact actionable as
fraud. The court found FPM failed to plead anything factual tending to show Aerovent did
anything other than express the capabilities of its products based on application of mathematical
formulae and known characteristics of the ventilators, and FPM failed to plead Aerovent knew or
should have known those representations were false at the time they were made. Analyzing
exhibits attached to the complaint, the court further found Aerovent represented the ventilation
systems operate continuously with an internal airstream temperature of 600 degrees Fahrenheit,
- 28 - but the drawings and specifications showed a difference between the internal airstream and the
internal components of the ventilator that were outside of the airstream. Based on that, the court
determined the exhibits did not show Aerovent’s representations were untrue.
¶ 61 1. Expressions of Opinion Versus Statements of Fact
¶ 62 “The elements of a cause of action for fraudulent misrepresentation are ‘(1) a
false statement of a material fact; (2) known or believed to be false by the party making it;
(3) intent to induce the other party to act; (4) action by the other party in reliance on the truth of
the statement; and (5) damage to the other party resulting from such reliance.’ ” Peters, 248 Ill.
App. at 387, 618 N.E.2d at 463 (1993) (quoting Soules v. General Motors Corp., 79 Ill. 2d 282,
286, 402 N.E.2d 599, 601 (1980)). The facts constituting fraud must be pled with specificity and
particularity, including what representations were made, when they were made, who made the
representations, and to whom they were made. Peters, 248 Ill. App. 3d at 387, 618 N.E.2d at
463.
¶ 63 “To support an action for fraud, the alleged misrepresentation must be one of fact
and not an expression of opinion.” Peters, 248 Ill. App. 3d at 387, 618 N.E.2d at 463.
“Statements regarding future events are considered opinions, not statements of fact.” Peters, 248
Ill. App. 3d at 387, 618 N.E.2d at 463. “ ‘[T]he general rule denies recovery for fraud based
upon a false representation of intention or future conduct.’ ” Peters, 248 Ill. App. 3d at 387, 618
N.E.2d at 463 (quoting Steinberg v. Chicago Medical School, 69 Ill. 2d 320, 334, 371 N.E.2d
634, 641 (1977)). “Even a false promise of future conduct with no current intent to fulfil that
promise will not constitute fraud.” Peters, 248 Ill. App. 3d at 387, 618 N.E.2d at 463. “In
determining whether a statement is one of fact or of opinion, we look to all the circumstances of
the particular case.” Peters, 248 Ill. App. 3d at 388, 618 N.E.2d at 463-64.
- 29 - ¶ 64 In Peters, the First District held representations by defendant contractors that a
cooling system could perform to certain specifications were statements of fact, not statements
regarding future events or opinions. There, the defendants supplied thermal banks for a heating,
ventilation, and air conditioning (HVAC) system. After the HVAC system failed to meet
performance specifications, plaintiffs sued defendants for fraudulent misrepresentation, alleging
defendants had misrepresented their equipment could meet the performance specifications.
Peters, 248 Ill. App. 3d at 388, 618 N.E.2d at 464. The allegedly fraudulent statements were the
thermal banks were “ ‘as called for in the specifications,’ ” and had a capacity of “100,000
pounds of ice at 2 1/2 [inch] thickness in 12 hours under certain conditions.” Peters, 248 Ill.
App. 3d at 388, 618 N.E.2d at 464.
¶ 65 The Peters defendants argued the statements were not actionable as fraud because
the statements related to future events. The appellate court disagreed. It stated, although the
alleged representations related to the performance of the thermal banks upon their installation as
part of the HVAC system, the representations should be treated as ones of present fact rather
than future performance. Peters, 248 Ill. App. 3d at 388-89, 618 N.E.2d at 464-65. The court
found, according to the allegations of the complaint, the representations “concerned a machine of
known physical characteristics and its capabilities based upon the application of certain
mathematical formulae and laws of physics to those physical properties.” Peters, 248 Ill. App.
3d at 388-89, 618 N.E.2d at 464. The court further stated the representations concerned “the
capabilities of a machine which was either in existence at the time the statements were made, or
one of a known, specified, and certain type.” Peters, 248 Ill. App. 3d at 389, 618 N.E.2d at 464.
As such, the statements must be considered representations of existing fact, and thus actionable
as fraud. Peters, 248 Ill. App. 3d at 388-89, 618 N.E.2d at 464-65.
- 30 - ¶ 66 In reaching its determination, the court relied on similar cases from other
jurisdictions illustrating the difference between factual representations supporting an action for
fraud and mere opinion or “sales talk” involving future promises concerning a product. See
Peters, 248 Ill. App. 3d at 389, 618 N.E.2d at 464 (“ ‘Representations by an expert on power to
one not having equal knowledge as to the amount of energy which standard makes of motors and
engines will develop are not future promises, but are statements with reference to known facts
based on tests and mathematical computations. Such representations differ materially from
“sellers’ talk” or mere opinion expressed to one having equal knowledge or equal opportunities
for knowledge.’ ” (quoting Maxwell Ice Co. v. Brackett, Shaw & Lunt Co., 116 A. 34, 36, 80
N.H. 236 (1921))); see also Bareham & McFarland, Inc. v. Kane, 228 A.D. 396, 398, 240 N.Y.S.
123, 127 (1930) (representations that a heater, when installed in a home, would heat the building
to 70 degrees in zero-degree weather, that fuel would cost no more than $350 per season, and
that gas for the pilot light would not exceed $1 per month held to “relate to the inherent capacity,
character and quality of the heater, and what it was actually capable of doing,” and thus
constitute “positive statements of existing facts” rather than mere “ ‘dealer’s talk’ ”); Traylor
Engineering & Manufacturing Co. v. National Container Corp., 70 A.2d 9, 13-14, 45 Del. 143,
152-54 (1949) (representations that a kiln would consume less than 65 gallons of oil per ton of
lime produced and that the kiln would easily produce 70 tons of high-quality lime per day held to
be actionable as fraud).
¶ 67 The court in Peters further noted the representations at issue were not dependent
upon any future conduct of the defendants. Peters, 248 Ill. App. 3d at 389, 618 N.E.2d at 465.
The court distinguished the circumstances from Spiegel, in which representations that a copier
would produce “ ‘picture perfect copies,’ ” were held to be “ ‘mere commendation or opinion.’ ”
- 31 - Peters, 248 Ill. App. 3d at 388, 618 N.E.2d at 464 (quoting Spiegel, 125 Il. App. 3d at 902, 466
N.E.2d at 1044). The court also distinguished LaScola v. US Sprint Communications, 946 F.2d
559, 568 (7th Cir. 1991), a case in which a company represented it has a “ ‘lucrative
compensation plan,’ that executives were ‘straight shooters’ and the company is ‘ethical.’ ”
Peters, 248 Ill. App. 3d at 389, 618 N.E.2d at 465. There, the statements were “too general and
difficult to substantiate to be considered statements of fact.” Peters, 248 Ill. App. 3d at 389, 618
N.E.2d at 465. The Peters court noted, in both Spiegel and LaScola, the representations were
subjective, difficult to prove, and could be considered “ ‘dealer talk; ” or “ ‘puffing.’ ” Peters,
248 Ill. App. 3d at 389-90, 618 N.E.2d at 465. In contrast, in the case before it, the
representations were specific and of an objective, quantifiable, and verifiable nature. Peters, 248
Ill. App. 3d at 390, 618 N.E.2d at 465. Thus, the defendants made misrepresentations of material
fact by stating that their thermal banks could meet the performance specifications. Peters, 248
Ill. App. 3d at 389-90, 618 N.E.2d at 465.
¶ 68 Here, the trial court misapplied Peters to hold representations about a machine of
known physical characteristics and its capabilities based upon the application of certain
mathematical formulae and laws of physics to those physical properties were statements of
opinion that required dismissal. Peters held the opposite. Under Peters, such statements were
considered representations of existing fact, as opposed to representations of opinions dependent
on future action, sales talk, or puffery, and thus were actionable as fraud. As in Peters, the
statements made by Aerovent were specific and based on allegedly extensive and specific
testing. Aerovent stated in its product catalog that, based on the testing, the ventilators were
“capable of withstanding continuous operation at 600 [degrees Fahrenheit], extended operating
periods at 800 [degree Fahrenheit] and 8 hours or more with an airstream temperature of 1000
- 32 - [degrees Fahrenheit].” Another page of the catalog also stated, “SV40 Smoke and Heat Roof
Ventilators shall be designed to withstand continuous operation with internal airstream
temperatures of 600 [degrees Fahrenheit] and a minimum of 8 hours with internal airstream
temperatures of 1000 [degrees Fahrenheit].” These are specific representations of an objective,
quantifiable, and verifiable nature and, as such, were representations of existing fact, as opposed
to mere statements of opinion concerning future action, sales talk, or puffery.
¶ 69 2. Reliance
¶ 70 Aerovent also argues Peters requires this court to affirm the trial court’s dismissal
because, in Peters, the appellate court ultimately affirmed the trial court’s dismissal based on the
plaintiff’s failure to adequately plead reliance on the misrepresentations. Peters, 248 Ill. App. 3d
at 391, 618 N.E.2d at 465-66. In Peters, the appellate court noted the plaintiff alleged reliance in
a conclusory fashion, without presenting facts indicating it was ever shown a letter, proposal, or
brochure in which the alleged misrepresentations were made. Such is not the case here, where
FPM attached the product catalog to the complaint and specifically alleged its contractors
recommended the Aerovent fans based on the product literature. Thus, we conclude FPM also
sufficiently alleged reliance.
¶ 71 3. Knowledge
¶ 72 The trial court also found FPM failed to sufficiently plead knowledge, holding
FPM’s allegation Aerovent knew or should have known the representations were false at the time
they were made, without factual support, was an “unsupported conclusion.”
¶ 73 “Illinois is a fact-pleading state, which means that, although pleadings are to be
liberally construed and formal or technical allegations are not necessary, a complaint must,
nevertheless, contain facts to state a cause of action.” Blevins v. Marcheschi, 2018 IL App (2d)
- 33 - 170340, ¶ 29, 101 N.E.3d 807. “A complaint is deficient when it fails to allege facts necessary
for the plaintiff to recover.” Blevins, 2018 IL App (2d) 170340, ¶ 29. “But a pleader is not
required to set out his evidence. Only the ultimate facts to be proved should be alleged and not
the evidentiary facts tending to prove such ultimate facts.” Blevins, 2018 IL App (2d) 170340,
¶ 29. “ ‘A statement of a defendant’s knowledge is an allegation of ultimate fact and not a
conclusion.’ ” Blevins, 2018 IL App (2d) 170340, ¶ 29 (quoting Ward v. Community Unit
School District No. 220, 243 Ill. App. 3d 968, 974, 614 N.E.2d 102, 106 (1993)). “The plaintiff
need not plead the evidentiary facts that he will use to prove the defendant’s knowledge.”
Blevins, 2018 IL App (2d) 170340, ¶ 29.
¶ 74 Here, FPM alleged Aerovent knew its statements about the capabilities of the
ventilators were false. This satisfies the pleading requirement that plaintiffs need allege only
ultimate facts, not evidentiary facts. See Blevins, 2018 IL App (2d) 170340, ¶ 30 (holding
defendants in a case involving fraudulent misrepresentation of water damage sufficiently alleged
knowledge by alleging the defendants knew of water infiltration and damage in or about a
damaged wallboard).
¶ 75 Further, even if we were to require more, FPM made additional allegations
inferring knowledge when it alleged Aerovent could not produce evidence of the testing of its
ventilators as set forth in both its brochure and reports and alleged Aerovent made various
admissions. FPM specifically alleged it requested “the testing and backup” for Aerovent’s
asserted “design” limit of 475 degrees Fahrenheit for the bearings, but Aerovent responded that it
did not have that data. FPM also asked Aerovent to produce evidence of the “ ‘extensive
testing’ ” it purportedly conducted to ensure the fans were “ ‘capable of withstanding continuous
operation at 600 [degrees Fahrenheit], extended operating periods at 800 [degrees Fahrenheit]
- 34 - and 8 hours or more with an airstream temperature of 1000 [degrees Fahrenheit],’ as represented
in its product specification catalog.” In response, Aerovent informed FPM that it could not
locate any supporting documentation.
¶ 76 FPM further noted Aerovent admitted one of its fans failed because the
temperatures inside the fan exceeded 500 degrees Fahrenheit, which exceeded the design limits
of the fan. FPM alleged that admission showed “Aerovent’s fans were never designed to operate
with internal temperatures exceeding 500 [degrees Fahrenheit].” Thus, FPM argued the
admission plainly established Aerovent’s prior representations the fans were designed to
withstand continuous temperatures of at least 600 degrees Fahrenheit were knowingly false.
Thus, FPM sufficiently pled knowledge in order to bring its claim for fraudulent
misrepresentation against Aerovent.
¶ 77 4. The Trial Court’s Consideration of Exhibits
¶ 78 The trial court also found the exhibits contradicted or disproved FPM’s
allegations of fraud based on differences between the components within the internal airstream
of the ventilator and the components outside of the airstream. Essentially, the trial court drew a
distinction between representations Aerovent made about components arguably within the
airstream, such as the fans, and those arguably outside the airstream, such as the motors,
ultimately finding Aerovent’s representations were applicable only to components within the
airstream, which the court determined were inside of the cylinder containing the fan. The court
specifically found “the drawings” revealed the problem occurred in the components outside of
the airstream, such as with the motors. FPM argues the court’s determination based on the
exhibits was inappropriate fact finding and in error.
- 35 - ¶ 79 We note the exhibits do not define the term “airstream” or clearly delineate its
location or its effect on components within or outside the airstream. One could infer from the
location of an arrow labeled as “airflow” shown outside the depiction of the ventilator in exhibit
No. 5 that the “airflow” is the movement of air through the cylinder containing the fan and not
the box that protrudes from the side containing the motor and other components. However,
another inference could be the “airflow” encompasses the entire assembly, either inside or
outside of it. Thus, the exhibit does not definitively support the trial court’s finding.
¶ 80 Further, even if the “airstream” encompassed only the portion of the ventilator
inside the cylinder depicted in the exhibit, Aerovent made representations arguably covering
components both within and outside such an “airstream” when its product specification catalog
stated the ventilator model was “capable of withstanding continuous operation at 600 [degrees
Fahrenheit], extended operating periods at 800 [degrees Fahrenheit] and 8 hours or more with an
airstream temperature of 1000 [degrees Fahrenheit].” Given the use of a comma after “600
[degrees Fahrenheit]” and lack of comma thereafter, that statement arguably separated
representations about the “airstream temperature” from the broader representation of the
ventilator’s ability to sustain “continuous operation at 600 [degrees Fahrenheit].” However,
elsewhere, the catalog stated the ventilators “shall be designed to withstand continuous operation
with internal airstream temperatures of 600 [degrees Fahrenheit] and a minimum of 8 hours with
internal airstream temperatures of 1000 [degrees Fahrenheit].” Meanwhile, when referring to
airstream testing in excess of 1000 degrees Fahrenheit, Aerovent’s product specification catalog
also stated, “Temperatures were monitored at several vital areas within the ventilator assembly:
inlet side of the fan wheel, fan bearings, bearing housing, belt tube, and the motor compartment.”
Thus, nothing clearly or definitively showed components of the ventilators aside from the fans,
- 36 - such as the motors, were not considered part of the representations made by Aerovent concerning
the ability of the ventilators as a whole, or the fans as an individual component, to perform
continuously at 600 degrees Fahrenheit both within and outside the “airstream.” Instead, the
product specification catalog is ambiguous on the matter. Moreover, reports from Aerovent
broadly indicated the fans were not capable of operating at the temperatures stated in the product
specification catalog. In addition, Aerovent’s own reports did not definitively determine the
cause of all of the failures. Further, FPM presented an e-mail communication from a
representative of Aerovent to a representative of OEM broadly stating the fans were capable of
performing at 600 degrees Fahrenheit, without reference to the “airstream.”
¶ 81 In general, it appears the trial court may have relied on Aerovent’s argument
related to its motion to dismiss where Aerovent added its own hand-drawn markings to the
depiction of the ventilator from exhibit No. 5 and provided its argument and interpretation of the
exhibit based on those added markings. Aerovent has also provided the same in its brief on
appeal. However, those additional markings and interpretation were not part of FPM’s pleadings
and were not facts to be considered at that stage of the proceedings. Thus, we disagree the
exhibits contradict the allegations in the complaint such that the issue may be determined as a
matter of law. Whether the Aerovent’s representations were actually false is ultimately an issue
of evidentiary fact to be determined at later stages in the proceedings. Based on the allegations
before us, it is not apparent any set of facts cannot be proved that would entitle FPM to relief.
Accordingly, we hold the court erred in dismissing the intentional and fraudulent
misrepresentation claim against Aerovent.
¶ 82 D. Negligence and the Economic Loss Doctrine (Counts V, XI, and XII)
- 37 - ¶ 83 FPM next contends the trial court erred when it determined the general negligence
claims against both Scandroli and Aerovent and the negligent misrepresentation claim against
Aerovent were barred by the economic loss doctrine. FPM contends it sufficiently pled
exceptions to the doctrine for sudden and dangerous events causing damage to other property or
for fraud or misrepresentation.
¶ 84 “The Moorman doctrine, also known as the economic loss doctrine, states that
there can be no recovery in tort for purely economic losses.” Flores v. Aon Corp., 2023 IL App
(1st) 230140, ¶ 56 (citing Moorman, 91 Ill. 2d at 88, 435 N.E.2d at 451-52). “Economic loss is
defined as ‘damages for inadequate value, costs of repair and replacement of the defective
product, or consequent loss of profits—without any claim of personal injury or damage to other
property.’ ” (Internal quotation marks omitted.) Flores, 2023 IL App (1st) 230140, ¶ 56
(quoting Moorman, 91 Ill. 2d at 82, 435 N.E.2d at 449). “The [economic loss] doctrine is
founded on the theory that ‘parties to a contract may allocate their risks by agreement and do not
need the special protections of tort law to recover damages caused by a breach of contract.’ ”
Flores, 2023 IL App (1st) 230140, ¶ 56 (quoting Mars, Inc. v. Heritage Builders of Effingham,
Inc., 327 Ill. App. 3d 346, 351, 763 N.E.2d 428, 434 (2002)). In particular, the court in
Moorman held, “Tort theory is appropriately suited for personal injury or property damage
resulting from a sudden or dangerous occurrence,” while the “remedy for economic loss, loss
relating to a purchaser’s disappointed expectations due to deterioration, internal breakdown or
nonaccidental cause, on the other hand, lies in contract.” Moorman, 91 Ill. 2d at 86, 435 N.E.2d
at 450. Thus, the economic loss doctrine denies a tort remedy for those whose complaint is
rooted in the disappointment of commercial or contractual expectations. Sienna Court
Condominium Ass’n v. Champion Aluminum Corp., 2018 IL 122022, ¶ 21, 129 N.E.3d 1112.
- 38 - ¶ 85 There are three exceptions to the economic loss doctrine: (1) where the plaintiff
sustained damage, such as personal injury or property damage, resulting from a sudden,
dangerous, or calamitous occurrence; (2) where the plaintiff’s damages are proximately caused
by a defendant’s intentional, false misrepresentation; and (3) where the plaintiff’s damages are
proximately caused by a negligent misrepresentation by a defendant in the business of supplying
information for the guidance of others in their business transactions. 1324 W. Pratt Condo.
Ass’n v. Platt Construction Group, Inc., 404 Ill. App. 3d 611, 618, 936 N.E.2d 1093, 1100
(2010); In re Chicago Flood Litigation, 176 Ill. 2d 179, 199, 680 N.E.2d 265, 275 (1997). FPM
does not argue the third exception applies.
¶ 86 First, as previously discussed, the trial court erred in dismissing FPM’s
intentional, fraudulent misrepresentation claim against Aerovent. Thus, the court also erred in
determining FPM failed to plead such an exception was applicable to the economic loss doctrine
in regard to Aerovent. As to FPM’s remaining negligence claims against Scandroli, and to the
extent it may later be determined Aerovent did not misrepresent the capabilities of the
ventilators, FPM argues the fire resulting from the defective fans resulted from a sudden and
dangerous event that caused damage to property other than the ventilators themselves.
¶ 87 “In order to apply the ‘sudden or dangerous occurrence’ exception and recover
economic damages in negligence, (1) the economic damages must result from ‘a sudden,
dangerous, or calamitous event,’ and (2) the event must also cause ‘personal injury or property
damage.’ ” 1324 W. Pratt Condo. Ass’n, 404 Ill. App. 3d at 618, 936 N.E.2d at 1100 (quoting
Chicago Flood Litigation, 176 Ill. 2d at 200-01, 680 N.E.2d at 275).
¶ 88 1. Sudden and Dangerous or Calamitous Event
- 39 - ¶ 89 “Damages which are the proximate result of a sudden and calamitous occurrence
that causes harm to other property are compensable in tort.” American Xyrofin, Inc. v. Allis-
Chalmers Corp., 230 Ill. App. 3d 662, 671, 595 N.E.2d 650, 657 (1992). Courts have defined a
sudden or dangerous occurrence as “a sudden event, consistent with a tortious act,” that is
“ ‘highly dangerous and presents the likelihood of personal injury or injury to other property.’ ”
(Emphasis omitted.) Mars, 327 Ill. App. 3d at 353, 763 N.E.2d at 435-36.
¶ 90 “The type of harm attendant to a sudden and calamitous event does not flow from
disappointed commercial expectations; rather, it arises from ‘[h]azards peripheral to the
product’s [intended] function.’ ” American Xyrofin, 230 Ill. App. 3d at 671-72, 595 N.E.2d at
657 (quoting Moorman, 91 Ill. 2d at 97, 435 N.E.2d at 455 (Simon, J., specially concurring)).
“When characterizing an event as sudden and calamitous the focus is upon ‘the
suddenness of the occurrence of an event—the point when the injury occurs
***—where such occurrence causes personal injury or damage to property
external to the defective product which exposes a party to an unreasonable risk of
injury to himself or his property, rather than the suddenness or length of time
within which the defect or cause of the occurrence develops *** and manifests
itself in the sudden and calamitous occurrence.’ ” (Emphases in original.)
American Xyrofin, 230 Ill. App. 3d at 671-72, 595 N.E.2d at 657 (quoting United
Air Lines, Inc. v. CEI Industries of Illinois, Inc., 148 Ill. App. 3d 332, 339, 499
N.E.2d 558, 562 (1986)).
“Additionally, a history of repairs prior to the occurrence does not necessarily detract from its
characterization as sudden and calamitous where there is evidence to support the finding that the
product failed in a sudden and calamitous manner.” American Xyrofin, 230 Ill. App. 3d at 672,
- 40 - 595 N.E.2d at 657 (citing Vaughn v. General Motors Corp., 102 Ill. 2d 432, 436-37, 466 N.E.2d
195, 197 (failure of brakes on truck sudden and calamitous even though plaintiff was aware of
condition of brakes for 19 months prior to accident)); see Seegers Grain Co. v. United States
Steel Corp., 218 Ill. App. 3d 357, 366-67, 577 N.E.2d 1364, 1369-70 (1991) (implosion of grain
storage tank sudden and calamitous even though repairs to foundation and access doors of grain
storage tank were performed three months prior to occurrence); United Air Lines, 148 Ill. App.
3d at 340-341, 499 N.E.2d at 562-63 (roof collapse was sudden and calamitous even though
plaintiff was aware of water accumulation resulting from roof leaks); see also Mars, 327 Ill. App.
3d at 353, 763 N.E.2d at 436 (the collapse of a building frame during a thunderstorm was a
sufficiently sudden and dangerous occurrence to fall within the scope to the exceptions).
¶ 91 As the court explained in United Air Lines,
“when a sudden and dangerous event occurs resulting in personal injury or
property damage, as well as economic loss, an otherwise qualitative defect, which
develops or manifests itself either gradually or suddenly, loses its inflexible
classification as such in the realm of the economic loss doctrine, and tort, rather
than contract, law is the appropriate remedy for damages caused by the defect.”
United Air Lines, 148 Ill. App. 3d at 340, 499 N.E.2d at 562-63.
¶ 92 In United Air Lines, a gradual accumulation of water resulted in a sudden roof
collapse, damaging office equipment. Looking to the suddenness of the event causing injury, the
court found the event was sudden and calamitous and acted as an exception to the economic loss
doctrine. United Air Lines, 148 Ill. App. 3d at 339-40, 499 N.E.2d at 562-63. The court further
held the fact United Air Lines was aware of the continuing leakage problem was only relevant to
- 41 - the assumption of the risk or comparative negligence, which was not the issue before the court.
United Air Lines, 148 Ill. App. 3d at 340, 499 N.E.2d at 563.
¶ 93 Here, FPM pled a sudden fire occurred when one of the ventilators failed. The
courts in Moorman and United Air Lines recognized a fire as a sudden and highly dangerous
occurrence, held to be recoverable in tort. Moorman, 91 Ill. 2d at 84, 435 N.E.2d at 450; United
Air Lines, 148 Ill. App. 3d at 338-39, 499 N.E.2d at 561-62; see American Drug Stores, Inc. v.
AT & T Technologies, Inc., 222 Ill. App. 3d 153, 155, 583 N.E.2d 694, 696 (1991) (“[A] sudden
and calamitous fire may be a proper type of occurrence from which to bring an action in tort
***.”).
¶ 94 Despite cases holding a fire is a sudden and dangerous event, applying Hecktman
v. Pacific Indemnity Co., 2016 IL App (1st) 151459, ¶ 18, 59 N.E.3d 868, the trial court found
the fire was not a sudden and dangerous or calamitous event because the ventilators failed over a
period of time. Scandroli argues the same, contending the cause of the event was the condition
of the ventilators failing over time instead of the sudden fire.
¶ 95 In Hecktman, condominium owners filed a negligence action against entities
associated with the construction of their building. The plaintiffs alleged, after they moved into
their home in 2009, portions of the hardwood flooring began to bow upward, preventing doors
from opening and causing damage. The plaintiffs alleged the cause of the problem was water
infiltration caused by (1) inadequate construction of the window system of their units, permitting
water to enter the units from the outside and (2) inadequate design, installation, and operation of
the HVAC system, which failed to properly remove humidity from the ambient air of the
building and the plaintiffs’ units. Hecktman, 2016 IL App (1st) 151459, ¶¶ 4-5. Specifically
noting the plaintiffs alleged their hardwood floors became deformed over time, the appellate
- 42 - court found the plaintiffs failed to allege a sudden, dangerous, or calamitous event. Hecktman,
2016 IL App (1st) 151459, ¶ 18.
¶ 96 We find Hecktman distinguishable. There, the event causing damage was a
bowing of the floors over time caused by a slow infiltration of water. There was no sudden event
such as a flood. Scandroli would have us look to the multiple failures of the ventilators over
time to hold Hecktman applies, but that is not the fact at issue. Instead, we look at the
suddenness of the occurrence of an event at the point when the injury occurred. Here, that was a
sudden fire. Indeed, the Hecktman court recognized how the case before it differed from such a
sudden event, noting that United Air Lines held “the gradual accumulation of water that resulted
in a sudden roof collapse constituted a calamitous event” (emphasis in original) (citing United
Air Lines, 148 Ill. App. 3d at 340, 499 N.E.2d at 563), and Electronics Group, Inc. v. Central
Roofing Co., 164 Ill. App. 3d 915, 918-19, 518 N.E.2d 369, 370-71 (1987), held “a roof leak that
caused a substantial amount of water to pour into a warehouse in [a] single day was a calamitous
event.” (Emphasis in original). Hecktman, 2016 IL App (1st) 151459, ¶ 18. Here the fire was
sudden and dangerous. The next question is whether the event caused personal injury or damage
other than to the ventilators themselves.
¶ 97 2. Damage to Other Property
¶ 98 FPM next argues it alleged damage to property other than the ventilators
themselves. Meanwhile, Scandroli and Aerovent argue FPM alleged damage that was integrated
with the ventilators such that “other property” was not involved.
¶ 99 For the sudden-and-dangerous-event exception to the economic loss doctrine to
apply, the sudden and dangerous event must result in personal injury or property damage.
Chicago Flood Litigation, 176 Ill. 2d at 199-200, 680 N.E.2d at 275. The property damage
- 43 - cannot relate to the defective product itself—there must be damage to “other property.” Trans
States Airlines v. Pratt & Whitney Canada, Inc., 177 Ill. 2d 21, 41-42, 682 N.E.2d 45, 54-55
(1997). “Simply put, a product that damages only itself cannot be the subject of a suit for
damages.” Mars, 327 Ill. App. 3d at 354, 763 N.E.2d at 436 (2002) (citing Moorman, 91 Ill. 2d
at 85, 435 N.E.2d at 450 (“[W]here only the defective product is damaged, economic losses
caused by qualitative defects falling under the ambit of a purchaser’s disappointed expectations
cannot be recovered under a strict liability theory.”)).
¶ 100 Chicago Flood Litigation provides an example of an economic loss that is above
and beyond a plaintiff’s commercial expectations. There, our supreme court concluded the
economic loss doctrine did not bar recovery in tort for the plaintiffs, who lost perishable
inventory as a result of interrupted electrical service, finding such a loss was above and beyond
the plaintiffs’ disappointed commercial expectation in continuous electrical service. Chicago
Flood Litigation, 176 Ill. 2d at 202, 680 N.E.2d at 276.
¶ 101 In Trans States Airlines, our supreme court addressed whether an airplane engine
and its airframe constituted two separate products or were so integrated as to be considered a
single product. There, an aircraft manufacturer bought an airplane engine from the defendant
and incorporated it into one of its airframes. While the aircraft was flying, the engine failed and
caught fire, damaging both the engine and the surrounding airframe. In seeking recovery for
damages to the airframe, the plaintiff argued the engine was a separate entity from the airframe,
and thus, the airframe was “other property.” Trans States Airlines, 177 Ill. 2d at 23-26, 682
N.E.2d at 46-48.
¶ 102 The court held a product and one of its component parts can constitute two
separate products such that a plaintiff may recover in tort when a defect in one causes damage to
- 44 - the other. Trans States Airlines, 177 Ill. 2d at 51, 682 N.E.2d at 59. The court found, to
determine whether a defective product caused damage to “other property,” the focus must be on
the injured party’s bargained-for expectation. Trans States Airlines, 177 Ill. 2d at 46, 682 N.E.2d
at 57. If a party bargained separately for individual components, then those components
constitute separate products. Trans States Airlines, 177 Ill. 2d at 47, 682 N.E.2d at 57. If a
defective component constituting a separate and distinct product causes damage to another
component or to the whole, then the plaintiff lost more than it bargained for, and it can recover
under a tort theory. Trans States Airlines, 177 Ill. 2d at 49-50, 682 N.E.2d at 57-58. However,
the court ultimately determined the engine and the airframe was a single product because the
plaintiff had bargained for a fully integrated aircraft, rather than for a separate engine and
airframe. Trans States Airlines, 177 Ill. 2d at 50-51, 682 N.E.2d at 58.
¶ 103 This court applied Trans States Airlines in Mars. There, the plaintiff brought a
negligence suit against a contractor and subcontractors for damages associated with the
construction of a warehouse frame that collapsed during a storm. This court found the plaintiff
failed to plead damage to property that could be separated from the product itself because the
plaintiff bargained for a completed warehouse, which included the damaged frame. In doing so,
we noted, “Had the complaint alleged the frame fell and damaged the existing warehouse, or
vehicles belonging to [plaintiff], our analysis might be different.” Mars, 327 Ill. App. 3d at 357,
763 N.E.2d at 439.
¶ 104 Here, FPM alleged the ventilator failures caused extensive damage to other
property at the plant, including roof curbs, wood nailers, and belt rooms. It also alleged the plant
was required to shut down operations. While there is some indication the ventilators were
designed to integrate with the roof, nothing specifies FPM contracted with Scandroli or Aerovent
- 45 - for roof curbs, wood nailers, or belt rooms. As a result, FPM sought damages for those items
and specifically noted it was not seeking damages under a negligence theory for the ventilators
themselves. Thus, focusing on the injured party’s bargained-for expectation, which, as currently
pled, was solely for the ventilation system, we determine FPM adequately pled damage to “other
property” so as to bring it under the exception to the economic loss doctrine.
¶ 105 E. Amendment of the Complaint
¶ 106 Finally, FPM contends the trial court erred in denying it leave to amend its
complaint. Given the court’s indication it denied the motion for leave to amend due to
jurisdictional concerns, and because we reverse and remand this cause for further proceedings,
we determine the issue of the previous motion to amend is moot. On remand, FPM will have the
opportunity to seek to file an amended complaint, if it chooses, which can be considered by the
court under the current circumstances of the case.
¶ 107 III. CONCLUSION
¶ 108 For the reasons stated, we reverse the trial court’s dismissal of counts I, II, V, XI,
XII, and XIII of plaintiff’s second amended complaint, affirm the court’s judgment in all other
respects, and remand the cause for further proceedings.
¶ 109 Affirmed in part and reversed in part; cause remanded.
- 46 -
Related
Cite This Page — Counsel Stack
2024 IL App (4th) 230623-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fpm-llc-v-ollmann-associates-architects-pc-illappct-2024.