Pennzoil Producing Co. v. Offshore Express, Inc.

735 F. Supp. 195, 1990 A.M.C. 1895, 1990 U.S. Dist. LEXIS 238
CourtDistrict Court, E.D. Louisiana
DecidedJanuary 5, 1990
DocketCiv. A. 86-5753, 87-1296
StatusPublished
Cited by2 cases

This text of 735 F. Supp. 195 (Pennzoil Producing Co. v. Offshore Express, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennzoil Producing Co. v. Offshore Express, Inc., 735 F. Supp. 195, 1990 A.M.C. 1895, 1990 U.S. Dist. LEXIS 238 (E.D. La. 1990).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

BEER, District Judge.

This case involves a claim for damages arising from the apparent contact between M/V GREEN CANYON EXPRESS and a pipeline owned by United Gas Pipeline Company on March 24, 1986 in an area where the pipeline crossed under the Houma Navigation Canal. It was tried before the Court commencing on September 28, 1989, for a determination of liability and damages. Final briefs were filed on December 4, 1989, at which time the Court took the case under consideration.

FINDINGS OF FACT

1. On March 24, 1986, Offshore Express, Inc. owned and operated M/V GREEN CANYON EXPRESS, an offshore supply vessel, 185 feet in length, 38 feet in breadth and drawing approximately 6'3" forward and 9'6" aft.

2. On March 24, 1986, United Gas Pipeline Company owned and operated a twelve inch natural gas pipeline (the DuLarge pipeline) which was constructed to cross under the Houma Navigation Canal (“the Canal”) approximately one quarter of a mile north of the Dulac Pontoon Bridge.

3. Pennzoil Producing Company, ARCO, Mobil, Harry Bourg Corporation, John T. Velkas, and C.T. Carden, are co-owners of the A.L. Voisin No. 1 Well (“Voisin Well”) in Terrebonne Parish and are mineral lessees of the land on which the well is located. Their ownership is in the following percentages: Pennzoil — 37.21%; ARCO— 36.38%; Harry Bourg, C.T. Carden and John T. Velkas — 21.42%; Mobil — 4.98%.

4. Prior to March 24, 1986, the Voisin Well was producing from the 12,300' reservoir. The 12,300' reservoir produced gas, condensate, and water through a drive mechanism described as a “water drive". The energy used to induce flow to the surface was created by the water expanding in an attempt to replace the gas withdrawn from the reservoir. The well was “flow critical” and/or “rate sensitive". Any interruption or reduction in flow from the well was considered to be a condition that could lead to its early demise.

5. Gas produced from the Voisin Well had, since production began, entered the DuLarge pipeline owned by United Gas. At a point approximately two miles from the Voisin Well, the DuLarge pipeline passes beneath the Canal. Thus, the contact between the pipeline and M/V GREEN CANYON EXPRESS occurred about that distance from the well itself.

6. The DuLarge pipeline predates the 1961 construction of the Canal. To accommodate the dredging of the Canal, United Gas lowered the portion of the pipeline which was to pass beneath the channel. “Do not dredge” signs were posted on the original banks of the waterway to warn about the existing pipeline.

7. Since its construction in 1961, the Canal has widened considerably as a result of erosion. By March 1986, the Canal, at the point of the DuLarge pipeline crossing, had widened from its original 150' width to over 600' in some places. United Gas was aware of this.

8. Because the pipeline predated the Canal, a Corps of Engineers permit was not *197 required for this particular water crossing. The pipeline is authorized and maintained pursuant to a “grandfather” regulation found at 33 C.F.R. § 330.3. This provision authorizes the structure as long as “there is no interference with navigation.”

9. United Gas did not have a regularly scheduled inspection program to check for mud cover over its pipeline, however the pipeline had been probed for mud depth in October 1985.

10. The October 1985 probe was not done with the assistance of a diver, but was done by probing with an unmarked bar from the surface. United Gas estimated that the pipeline was covered with approximately two feet of mud at the time of the probing. However, the main purpose of the probe was to locate the pipeline, not to determine mud depth.

11. Immediately after the October 1985 probe, the Corps of Engineers dredged the channel. The pipeline was not probed to determine the depth of mud covering after the dredging.

12. Despite its awareness of the erosion in the Canal, United Gas never lowered the pipeline on the approaches to the dredged channel before March 24, 1986.

13. After the accident the pipeline was removed and barnacle growth was found on some of the segments of pipeline which had broken away as a result of the accident. Barnacle growth normally occurs on a pipeline when it is not covered by mud. Thus, it is more likely than not that immediately preceding the accident the pipeline at or near the point of impact was at least partially uncovered.

14. On March 24, 1986, at approximately 0300 hours, M/V GREEN CANYON EXPRESS was proceeding northbound in the Houma Navigation Canal and had just passed the Dulac bridge. The visibility that night was very much impaired by fog.

15. Captain Corey who was at the helm of M/V GREEN CANYON EXPRESS was conning with the aid of a lookout positioned in the wheelhouse. He was using radar to locate the east and west banks of the canal. Shortly after 0320 hours on March 24, 1986, the vessel apparently veered away from the north-south configuration of the deep water channel and almost immediately after the veering took place, struck the DuLarge pipeline.

16. M/V GREEN CANYON EXPRESS struck and ruptured the DuLarge pipeline approximately 25' outside or away from the deep water channel.

17. The port side of the vessel struck the pipeline and then slid along the pipeline, thereafter, the escaping gas erupted into flames and engulfed the stern area of the vessel.

18. The damage to the vessel indicates that the collision occurred at a point three to four feet below the waterline of the vessel. 1 The depth of water was five to six feet at the point of impact. Since the pipeline is 12" in diameter, it is more likely than not that the pipeline was at least partially above the mud line.

19. Captain Corey’s conning of the vessel in such a manner as to cause the vessel to veer away from the deep water channel, was negligent, in view of the fact that he was proceeding underway with markedly restricted visibility, made no use of the vessel’s fathometer and/or spotlight, and proceeded at a speed greater than was prudent under the circumstances.

20. Immediately following the collision and rupture the Voisin Well automatically shut-in as a result of the loss of pressure in the DuLarge pipeline. Pennzoil became aware the Voisin Well had shut-in on the same day as the casualty.

21. The shut-in occurred due to the nature of the operation of the reservoir. The point of contact between the gas and water in the reservoir, the interface, was beneath the well perforations while the well was producing. The interface was being restrained in its movement by the flow of gas from the well. When the flow ceased as a result of the collision, the interface moved to point above the perforations in the well-bore, thereby preventing gas flow from being reinstituted. The interface between *198 the gas and the water in the reservoir was in equilibrium prior to the collision, but was changed as a result of the collision and shut-in.

22.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
735 F. Supp. 195, 1990 A.M.C. 1895, 1990 U.S. Dist. LEXIS 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennzoil-producing-co-v-offshore-express-inc-laed-1990.