Marathon Pipe Line Company v. M/v Sea Level II v. Oceanonics, Inc.

806 F.2d 585, 1986 U.S. App. LEXIS 35013
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 23, 1986
Docket86-3038
StatusPublished
Cited by46 cases

This text of 806 F.2d 585 (Marathon Pipe Line Company v. M/v Sea Level II v. Oceanonics, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marathon Pipe Line Company v. M/v Sea Level II v. Oceanonics, Inc., 806 F.2d 585, 1986 U.S. App. LEXIS 35013 (5th Cir. 1986).

Opinion

CLARK, Chief Judge:

Defendants Sea Level International, Inc. (Sea Level), and C.S.I. International, Inc. (C.S.I.), appeal the judgment of the district court finding them liable for damages sustained to a pipeline owned by the plaintiff, Marathon Pipe Line Company (Marathon). Sea Level and C.S.I. contend that co-defendant Oceanonics, Inc. (Oceanonics), is contractually obligated to indemnify them for their liability stemming from the pipeline damage. Sea Level and C.S.I. also contend that the district court failed to make material findings regarding Oceanon-ics’ contractual duties and duty to exercise reasonable care. Finally, Sea Level and C.S.I. contest the amount of damages claimed by Marathon and awarded by the court and the award of prejudgment interest. We affirm the judgment of the district court in all respects.

I. Background

In July 1983, Texas Eastern Transmission Corporation (TETCO) commenced work on a project to change the protective system guarding one of its natural gas pipelines in the Gulf of Mexico. TETCO contracted with Sea-Con Services, Inc. (Sea-Con), to perform the necessary construction work. Sea-Con, in turn, secured the services of the workboat M/V SEA LEVEL II to transport material and personnel and to function as a work platform for the construction project. The SEA LEVEL II was owned and operated by appellants Sea Level and C.S.I.

TETCO’s pipeline was connected to the northeastern side of a fixed platform located in East Cameron Block 321. Marathon also owned two pipelines connected to the same fixed platform. The pipeline that ultimately sustained the damage ran in a southeasterly direction along the Gulf floor. TETCO contracted with Oceanonics to locate all submerged pipelines in the vicinity of the platform and mark them with buoys. Before the SEA LEVEL II arrived at East Cameron Block 321, an Oceanonics survey crew, aboard the M/V RAINDROP, located and marked the pipelines in the area with styrofoam buoys dropped at 500 to 800 feet intervals along the pipeline routes.

The SEA LEVEL II arrived at the platform site on July 2, 1983. Peter McCormick, the Oceanonics employee responsible for locating and marking the pipelines, boarded the vessel to confer with the SEA LEVEL II’s captain, Gerald Turner, about the location of the various pipelines. Turner then set out the SEA LEVEL II’s four anchors in the vicinity of the platform without incident.

It was later decided that the vessel should be repositioned. On the morning of July 3, 1983, McCormick boarded the SEA LEVEL II in order to discuss the repositioning of the vessel. Representatives from both TETCO and Sea-Con were also present. Turner advised McCormick and the other representatives that the vessel had to be repositioned in such a way that one of the vessel’s anchors would cross one of Marathon’s pipelines. Turner asked McCormick to verify the position of one of the buoys, which he estimated was 400 feet away from the SEA LEVEL II. McCormick advised against dropping the anchor so close to the pipeline, since it was Ocean-onics’ policy, for safety purposes, to maintain a distance of at least 1,000 feet be *588 tween a pipeline and an anchor when the anchor line crossed the pipeline. Despite McCormick’s advice and Turner’s own concern regarding the placement of the anchor, Turner decided to position the anchor across the pipeline at this location.

Shortly after the anchors were set, work ceased on the construction project and the SEA LEVEL II was ordered to return to shore for supplies. Turner ordered the retrieval of the four anchors. The crew raised three of the anchors routinely, but could not retrieve the fourth which had been dropped across Marathon’s pipeline. After much speculation as to what was causing the problem and several unsuccessful attempts to winch the anchor aboard, the anchor cable was cut.

On July 20, 1983, Marathon commissioned a sidescan sonar of the seabed in the vicinity of the lost anchor. The sidescan sonar confirmed that the anchor was lodged in Marathon’s pipeline and further indicated that 400 feet of the pipeline had been displaced from its trench to a maximum distance of 25 feet. On August 9, 1983, Marathon sent a diver down to inspect the damaged portion of the pipeline and to conduct ultrasonic testing at various locations along the displaced portion. During the course of this inspection, the diver found damage to the protective coating of the pipeline. The diver further reported finding two “flat spots” along the displaced portion of the pipeline. Finally, on August 16, 1985, Marathon retained Brown and Root, a survey firm, to perform a stress analysis on the pipeline with respect to its relocation and displacement. As a result of its analysis, Brown and Root concluded that the pipe had exceeded its yield strength during the movement. Brown and Root verbally recommended that some 60 feet of the pipeline be replaced.

Based in large part on this report, Marathon decided to replace rather than repair the damaged pipeline. It further decided to replace the entire 400-foot section of the pipeline displaced by the anchor rather than replace only the 60-foot portion and incur the additional expense of repairing the coating damage along the remaining portion.

The district court found that defendants TETCO and Sea-Con were not liable for the damage to the pipeline and that Oceanonics was not responsible for Marathon’s damages. It found that Oceanonics was hired only to locate and mark the pipelines, not to place the SEA LEVEL II’s anchors. The court reasoned that if Oceanonics had to place the anchors, the cost would have been greater, more sophisticated equipment would have been used, and Oceanon-ics would have taken control of the vessel and given the order where to position the anchors. The court noted that Captain Turner gave the order to drop the anchor based on his own decision, and found that any advice on McCormick’s part with respect to the proper positioning of the anchors was gratuitous. In addition, the court observed that McCormick expressed his disapproval of the planned anchoring operation.

With respect to the amount of damages, the district court found Marathon’s decision to replace the entire 400-foot segment of the pipeline to be reasonable under the circumstances. The court thus awarded Marathon the total amount it had expended in replacing the damaged segment, which was $530,607.67. The court also awarded prejudgment interest from the date of the casualty.

Sea Level and C.S.I. appeal the judgment with respect to both liability and damages.

II. Cross-Claims Against Oceanonics

Sea Level and C.S.I. raise a variety of issues in their attack on the district court’s holding that Oceanonics was not responsible for the pipeline damage. They contend that the court erred in characterizing McCormick’s advice on the positioning of the SEA LEVEL II’s anchors as “gratuitous.” They assert that Oceanonics’ activities with respect to the anchor placement were subject to the provisions of the TET-CO/Oceanonics contract. They argue that, since the activities were within the scope of the contract, the contract obligated Ocean-onics to indemnify Sea Level and C.S.I., as *589

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gic Services, L.L.C. v. Freightplus USA, Incorpora
866 F.3d 649 (Fifth Circuit, 2017)
Simmons v. Transocean Offshore Deepwater Drilling, Inc.
551 F. Supp. 2d 471 (E.D. Louisiana, 2008)
Nichols v. Weeks Marine, Inc.
513 F. Supp. 2d 627 (E.D. Louisiana, 2007)
Gisclair v. Galliano Marine Service
484 F. Supp. 2d 518 (E.D. Louisiana, 2007)
Perkins v. American Electric Power Fuel Supply, Inc.
91 F. App'x 370 (Sixth Circuit, 2004)
Falgout v. Louis-Jeune
799 So. 2d 610 (Louisiana Court of Appeal, 2001)
Tidewater Marine, Inc. v. Sanco International, Inc.
113 F. Supp. 2d 987 (E.D. Louisiana, 2000)
Karim v. Finch Shipping Co. Ltd.
94 F. Supp. 2d 727 (E.D. Louisiana, 2000)
Krummel v. Bombardier Corp.
206 F.3d 548 (Fifth Circuit, 2000)
Hetrick v. AIR LOGISTICS, INC.
55 F. Supp. 2d 663 (S.D. Texas, 1999)
Johnson v. Louisiana Power & Light Co.
740 So. 2d 720 (Louisiana Court of Appeal, 1999)
Paktank Corp.—Deer Park Terminal v. M/V M.E. Nunez
35 F. Supp. 2d 521 (S.D. Texas, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
806 F.2d 585, 1986 U.S. App. LEXIS 35013, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marathon-pipe-line-company-v-mv-sea-level-ii-v-oceanonics-inc-ca5-1986.