OPINION
Chief Justice ZAPPALA.
This case is before the Court, following remand, for a determination of whether Pennsylvania National Mutual Casualty Insurance Co.’s (PNI) use of tax increment financing pursuant to the Tax Increment Financing Act, 53 P.S. §§ 1661-1676 (TIF Act), to fund, in part, the construction costs of its office tower and parking garage facilities makes such project a “public work” for purposes of the Prevailing Wage Act (Wage Act), 43 P.S. §§ 165-1-165-17. The Commonwealth Court held that the use of tax increment financing does implicate the Prevailing Wage Act, and thus, requires the payment of prevailing wages. We agree, and, accordingly, affirm.
Sometime in late 1991, PNI, a Pennsylvania mutual insurance ' company, determined that its existing headquarters, within the city of Harrisburg (City), were inadequate. Thus, PNI began to explore the feasibility of moving its facilities, and up to 900 employees, to a new suburban location. The city’s mayor, Stephen Reed, made several proposals to PNI in an attempt to make PNI’s remaining in the city a viable option. The first two proposals did not include tax increment financing and PNI rejected them. The third proposal that Mayor Reed offered included tax increment financing and sites for PNI’s construction of an office tower and parking garage at a central downtown location. PNI accepted this proposal.
Thereafter, the City and/or the Harrisburg Redevelopment Authority (HRA) entered into a Development Agreement with PNI dated January 24, 1994. Pursuant to the agreement, the City and HRA were responsible for site preparation following which they were to convey to PNI the project site as bare [99] ground. In order to do this, the City and HRA first had to acquire the properties that made up the project site and demolish existing structures on those properties.
Over the course of several years, the City and/or HRA acquired a number of properties in downtown Harrisburg. The City’s land acquisition costs were financed partially by a $1,500,000 Economic Development Partnership (EDP) grant issued to the City by the Pennsylvania Department of Commerce under the Housing and Redevelopment Assistance Law, 35 P.S. §§ 1661-1676. Initially, the City intended to apply some of the EDP grant toward the demolition costs, however, since the actual land acquisition costs exceeded prior estimates, all of the EDP grant was applied toward the cost of land acquisition and administration of the grant.1
Once the land acquisition phase of the project was completed, as part of the site preparation, the City began to ready the site for construction. Thus, the City entered into a $109,000 asbestos removal contract with CMC Environmental Hazard Abatement, Inc. It also entered into an agreement with a demolition contractor to perform site preparation work other than the asbestos removal.
Pursuant to the Development Agreement, once demolition was completed, the City conveyed the “bare ground” to PNI and PNI constructed its new headquarters and parking garage. Construction of the office tower and garage was financed, in part, pursuant to the TIF Act. The City, the County of Dauphin and the Harrisburg School District (collectively, the taxing bodies) approved the creation of a tax increment district pursuant to Section 5 of the TIF Act, 35 P.S. § 6930.5, and, by adopting resolutions to that effect, agreed to participate in the tax increment district.2
[100] Thereafter, the Prevailing Wage Division of the Pennsylvania Department of Labor and Industry, by letter dated September 9, 1994, issued a determination concluding that the PNI building project, in its entirety, was not subject to the Wage Act. This decision was the subject of our prior opinion in this case and, therein, we stated the following regarding the procedural history of the matter:
On September 13, 1994, the Pennsylvania State Building and Construction Trades Council, AFL-CIO and the Central Pennsylvania Building Trades. Council (the “Unions”), which are councils of labor unions representing employees in the building and construction industry throughout Pennsylvania and central Pennsylvania, respectively, filed a grievance with the Board, pursuant to 43 P.S. § 165.2.2(e)(1) of the Act, regarding the Division’s determination.
After consideration of a joint request for expedited relief, the Board, by order dated October 18, 1994, inter alia, set a briefing schedule, and ordered that the parties address the issue of whether the Unions had standing to challenge the Division’s determination in this case. Subsequently, PNI, the City and HRA intervened in the grievance proceedings in support of the Division’s position. Although the parties could not agree on stipulated facts, an evidentiary hearing was not held; only documentary evidence was presented for the Board’s consideration. The Board heard orál argument on November 3, 1994 and rendered a decision and order on January 13,1995.
In its unanimous decision reversing the Division’s determination, the Board concluded that the Unions had standing to file their grievances and that because the asbestos removal constituted “public work” as defined in the [Wage] Act, the [Wage] Act applies to the entire PNI building project. Appellants appealed this determination and the Division filed a separate appeal of the Board’s order. The Commonwealth Court consolidated the appeals, and affirmed the Board’s order.
[101] Pennsylvania National Mutual Casualty Ins. Co. v. Department of Labor and Industry, 552 Pa. 385, 715 A.2d 1068, 1070 (1998) (footnote omitted).
Our Court granted allowance of appeal, limited to the following three issues: 1) whether the Unions had standing to file a grievance in this case; 2) whether the Wage Act applies to the entire building project because public bodies initially paid for the asbestos removal project; and 3) whether the Wage Act applies to the entire building project because it is financed under the TIF Act, the Urban Redevelopment Act, or the Housing and Redevelopment Assistance Law.
In our decision, we concluded that the Unions had standing to file their grievance in this case. Regarding the second issue, we noted the following:
43 P.S. § 165-5 of the [Wage] Act requires that:
Not less than the prevailing minimum wages as determined hereunder shall be paid to all workmen employed on public work.
Thus, only workmen who labor on “public work” must be paid the minimum prevailing wage. Section 2(5) of the [Wage] Act, 43 P.S. § 165-2(5), defines “public work” as:
Construction, reconstruction, demolition, alteration and/or repair work other than maintenance work, done under contract and paid for in whole or in part out of the funds of a public body where the estimated cost of the total project is in excess of twenty-five thousand dollars ($25,000), but shall not include work performed under a rehabilitation or manpower training program.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
Chief Justice ZAPPALA.
This case is before the Court, following remand, for a determination of whether Pennsylvania National Mutual Casualty Insurance Co.’s (PNI) use of tax increment financing pursuant to the Tax Increment Financing Act, 53 P.S. §§ 1661-1676 (TIF Act), to fund, in part, the construction costs of its office tower and parking garage facilities makes such project a “public work” for purposes of the Prevailing Wage Act (Wage Act), 43 P.S. §§ 165-1-165-17. The Commonwealth Court held that the use of tax increment financing does implicate the Prevailing Wage Act, and thus, requires the payment of prevailing wages. We agree, and, accordingly, affirm.
Sometime in late 1991, PNI, a Pennsylvania mutual insurance ' company, determined that its existing headquarters, within the city of Harrisburg (City), were inadequate. Thus, PNI began to explore the feasibility of moving its facilities, and up to 900 employees, to a new suburban location. The city’s mayor, Stephen Reed, made several proposals to PNI in an attempt to make PNI’s remaining in the city a viable option. The first two proposals did not include tax increment financing and PNI rejected them. The third proposal that Mayor Reed offered included tax increment financing and sites for PNI’s construction of an office tower and parking garage at a central downtown location. PNI accepted this proposal.
Thereafter, the City and/or the Harrisburg Redevelopment Authority (HRA) entered into a Development Agreement with PNI dated January 24, 1994. Pursuant to the agreement, the City and HRA were responsible for site preparation following which they were to convey to PNI the project site as bare [99] ground. In order to do this, the City and HRA first had to acquire the properties that made up the project site and demolish existing structures on those properties.
Over the course of several years, the City and/or HRA acquired a number of properties in downtown Harrisburg. The City’s land acquisition costs were financed partially by a $1,500,000 Economic Development Partnership (EDP) grant issued to the City by the Pennsylvania Department of Commerce under the Housing and Redevelopment Assistance Law, 35 P.S. §§ 1661-1676. Initially, the City intended to apply some of the EDP grant toward the demolition costs, however, since the actual land acquisition costs exceeded prior estimates, all of the EDP grant was applied toward the cost of land acquisition and administration of the grant.1
Once the land acquisition phase of the project was completed, as part of the site preparation, the City began to ready the site for construction. Thus, the City entered into a $109,000 asbestos removal contract with CMC Environmental Hazard Abatement, Inc. It also entered into an agreement with a demolition contractor to perform site preparation work other than the asbestos removal.
Pursuant to the Development Agreement, once demolition was completed, the City conveyed the “bare ground” to PNI and PNI constructed its new headquarters and parking garage. Construction of the office tower and garage was financed, in part, pursuant to the TIF Act. The City, the County of Dauphin and the Harrisburg School District (collectively, the taxing bodies) approved the creation of a tax increment district pursuant to Section 5 of the TIF Act, 35 P.S. § 6930.5, and, by adopting resolutions to that effect, agreed to participate in the tax increment district.2
[100] Thereafter, the Prevailing Wage Division of the Pennsylvania Department of Labor and Industry, by letter dated September 9, 1994, issued a determination concluding that the PNI building project, in its entirety, was not subject to the Wage Act. This decision was the subject of our prior opinion in this case and, therein, we stated the following regarding the procedural history of the matter:
On September 13, 1994, the Pennsylvania State Building and Construction Trades Council, AFL-CIO and the Central Pennsylvania Building Trades. Council (the “Unions”), which are councils of labor unions representing employees in the building and construction industry throughout Pennsylvania and central Pennsylvania, respectively, filed a grievance with the Board, pursuant to 43 P.S. § 165.2.2(e)(1) of the Act, regarding the Division’s determination.
After consideration of a joint request for expedited relief, the Board, by order dated October 18, 1994, inter alia, set a briefing schedule, and ordered that the parties address the issue of whether the Unions had standing to challenge the Division’s determination in this case. Subsequently, PNI, the City and HRA intervened in the grievance proceedings in support of the Division’s position. Although the parties could not agree on stipulated facts, an evidentiary hearing was not held; only documentary evidence was presented for the Board’s consideration. The Board heard orál argument on November 3, 1994 and rendered a decision and order on January 13,1995.
In its unanimous decision reversing the Division’s determination, the Board concluded that the Unions had standing to file their grievances and that because the asbestos removal constituted “public work” as defined in the [Wage] Act, the [Wage] Act applies to the entire PNI building project. Appellants appealed this determination and the Division filed a separate appeal of the Board’s order. The Commonwealth Court consolidated the appeals, and affirmed the Board’s order.
[101] Pennsylvania National Mutual Casualty Ins. Co. v. Department of Labor and Industry, 552 Pa. 385, 715 A.2d 1068, 1070 (1998) (footnote omitted).
Our Court granted allowance of appeal, limited to the following three issues: 1) whether the Unions had standing to file a grievance in this case; 2) whether the Wage Act applies to the entire building project because public bodies initially paid for the asbestos removal project; and 3) whether the Wage Act applies to the entire building project because it is financed under the TIF Act, the Urban Redevelopment Act, or the Housing and Redevelopment Assistance Law.
In our decision, we concluded that the Unions had standing to file their grievance in this case. Regarding the second issue, we noted the following:
43 P.S. § 165-5 of the [Wage] Act requires that:
Not less than the prevailing minimum wages as determined hereunder shall be paid to all workmen employed on public work.
Thus, only workmen who labor on “public work” must be paid the minimum prevailing wage. Section 2(5) of the [Wage] Act, 43 P.S. § 165-2(5), defines “public work” as:
Construction, reconstruction, demolition, alteration and/or repair work other than maintenance work, done under contract and paid for in whole or in part out of the funds of a public body where the estimated cost of the total project is in excess of twenty-five thousand dollars ($25,000), but shall not include work performed under a rehabilitation or manpower training program.
Therefore, we must look at the work performed on the PNI project to determine whether it is deemed to constitute “public work,” and, thus, subject to the Act. Initially, we note, as did the Board, that the fact pattern before us is unique. The circumscribed role of the City in the building project was to prepare and deliver vacant land. Once the City completed its contracts for asbestos removal and demolition, and conveyed the property to PNI, its limited involvement in the development of the property ceased altogether. [102] The City will evidently not be a party to any post-conveyance construction contract. Other than possible state financing addressed in issue three below, no post-conveyance construction contracts will be paid for in whole or in part until public funds. Thus, the factual scenario before us is unlike other situations in which a public body contracts for work which is to be paid for entirely with public monies.
Again, to constitute “public work” four elements must be satisfied:
(1) there must be certain work;
(2) such work must be under contract;
(3) such work must be paid for in whole or in part with public funds; and
(4) the estimated cost of the total project must be in excess of $25,000.
Under the facts of this case, the lower tribunals found that the $109,000,000 asbestos removal work met this definition. The asbestos removal was the kind of work covered by the Act, i.e., demolition work, it was under contract, and as determined by the lower tribunals, was paid for in whole or in part out of the funds of a public body. The $25,000 threshold was clearly met. The lower tribunals then found that because the asbestos removal constituted public work, the entire PNI building project, i.e., the remaining work, constituted public work for purposes of the Act.
Id. at 1073-74 (emphasis added).
We noted that the Board, in accepting the Union’s argument, found that the Wage Act speaks to the “total project,” and not individual contracts or phases, and establishes coverage where any work is public work. In rejecting this analysis, we noted the following:
We do not agree with the Board’s interpretation of the definition of “public work.” Assuming, arguendo, that the “total project” is the $30 million PNI building project, the term “total project,” is referred to in the definition of “public work” only in the context of establishing a monetary threshold which excludes from coverage of the Act, projects [103] costing less than $25,000. We do not interpret this prong to confer public work status to work which otherwise fails to satisfy the other three elements of the definition of “public work.” Rather, all elements of the definition must be satisfied for work to constitute “public work.”
Id. at 1074. Thus, we concluded that “under the distinct facts of this case” that “the entire PNI building project is not covered by the [Wage] Act simply because asbestos removal was deemed to be public work.” Id. at 1075.
In addressing the third issue, we noted that neither the Board nor the Commonwealth Court addressed the issue of statutory financing and whether or not its use implicated the Wage Act. We noted that the Board failed to conduct an evidentiary hearing and, thus, did not provide detailed factual findings regarding the use of statutory financing. In particular, we noted the following in this regard:
Specifically, no detailed findings of fact were made by the Board as to, inter alia, funding streams; what specific entities utilized tax monies and grants; for what specific work the tax and grant monies were used; the process through which tax increment bonds were issued and what role if any public entities played in the issuance of the bonds; what purpose interest income generated from the bonds is used for; what entities are ultimately responsible for payment of the bonds and debt service on the same; whether a public entity’s credit was pledged in connection with the bonds; whether tax monies were merely foregone or whether these monies were actually collected by public entities and redistributed; and whether the public entity has access to such monies.
Id. n. 11. Thus, we remanded the matter to the Board to hold further proceedings, conduct an evidentiary hearing, and to make specific findings and conclusions of law regarding:
whether the [Wage] Act applies to the entire PNI building project because it is financed under the Tax Increment [104] Financing Act, the Urban Redevelopment Act, and/or the Housing and Redevelopment Assistance Law.