Pennsylvania Engineering Corp. v. Islip Resource Recovery Agency

714 F. Supp. 634, 1989 U.S. Dist. LEXIS 6610, 1989 WL 63925
District Court, E.D. New York·Decided June 12, 1989·No. CV 88-2733·Published·Cited by 3 cases

Opinion

WEXLER, District Judge.

The present action arises out of a contractual dispute between Pennsylvania Energy Resources Company (“PERC”), Pennsylvania Engineering Corporation (“PEC”) and the Islip Resource Recovery Agency (the “Agency”). Plaintiffs asserted four causes of action against defendants. In response defendants filed nine counterclaims against plaintiffs and Victor Posner, a counterclaim defendant.

Pursuant to Fed.R.Civ.P. 56 defendants moved for summary judgment on plaintiffs’ entire case and on their first three counterclaims. By order dated April 12, 1989, 710 F.Supp. 456, the Court dismissed plaintiffs’ case in its entirety and granted summary judgment on defendants’ first three counterclaims. Now plaintiffs seek to negate the effect of the Court’s order by moving to reargue and by seeking to amend their complaint and then moving to relate back the timing of the amended complaint to the date of the original complaint. Fed.R.Civ.P. 15(c). Before reaching the merits of plaintiffs’ motions, it is necessary to describe this case’s tortured history.

PERC is a wholly owned subsidiary of PEC. In 1985 PERC entered into a contractual agreement (the “Agreement”) with the Agency to build a waste disposal co-generation plant in Islip, New York. PEC agreed to guarantee PERC’s performance. However, PERC experienced financial difficulties in building the plant, and the Agency became dissatisfied with PERC’s performance. By letter dated May 3, 1988, the Agency informed PERC that a dispute existed within the terms of the Agreement. The Agency informed PERC that this dispute would be submitted and resolved by an “Independent Construction Engineer” (the “Arbitrator”), as described by the arbitration clause in the Agreement. Along with the letter, the Agency submitted the names of certain engineering firms, and asked PERC to pick one as the Independent Construction Engineer. PERC picked Roger S. Hechlinger of Roy F. Weston Company (“Weston”) as the Arbitrator. Both sides submitted relevant documents and on *636 June 24,1988, the Arbitrator decided, inter alia:

(A) PERC is not entitled to an extension of the Scheduled Performance Achievement Date.
(B) PERC is not entitled to an increase in the Construction Price.
(C) PERC is in default under the Agreement and liable for delay damages from the date the default occurred.

See Arbitrator’s Decision dated June 24, 1988. On June 29, 1988 the Agency terminated PERC.

On August 30, 1988 plaintiffs commenced this lawsuit. As detailed more fully in the Court’s prior order, it should have been clear to plaintiffs that the preclusive effect of the Arbitrator’s decision would be this case’s central issue. In their complaint, which contains 312 paragraphs, plaintiffs briefly mentioned certain aspects of the Independent Construction Engineer’s decision. See Plaintiffs’ Complaint at 111186-87. Nevertheless, plaintiffs did not indicate that the Arbitrator’s determination wielded any legal significance. Moreover, plaintiffs did not move to vacate the Arbitrator’s award as required by the Federal Arbitration Act, 9 U.S.C. § 10 (the “Act”). Instead plaintiffs filed this lawsuit in which they attempted to relitigate the very same issues presented to the Arbitrator, along with other claims.

On November 7, 1988, defendants filed a motion for summary judgment. Largely arguing that the doctrines of res judicata and collateral estoppel precluded plaintiffs from relitigating the issues raised before the Arbitrator, defendants sought to confirm the Arbitrator’s decision, and moved for summary judgment on plaintiffs’ entire case, and for summary judgment on their first three counterclaims. In responding briefs dated January 4, 1989 plaintiffs, for the first time, objected to the arbitration award on the grounds that the Arbitrator was biased. Although plaintiffs did not formally move to vacate the arbitration award, they submitted documents indicating that before the Agency awarded PERC the right to build the Facility, Weston had written a feasibility study which stated that PERC could build the Facility within the time limits that PERC itself proposed. PERC argued that one of the issues before the Arbitrator was its contention that it could not build the Facility on time. Moreover, PERC stated that it did not know of Weston’s feasibility study, and if it had known it would never have chosen Weston as the Arbitrator.

In response to plaintiffs’ argument, defendants submitted documents taken from PERC’s own files which strongly indicated that PERC was fully aware of Weston’s feasibility study. See Cahill Reply Affidavit, Ex. B.

Nevertheless, in the Court’s order dated April 12, 1989 the Court disregarded plaintiffs’ contention of bias by the Arbitrator. The Court stated that the Act allows a party opposing an arbitration to move to vacate the award up till three months after the rendering of the award. The first time plaintiffs raised any objections to the arbitration was in their January 4, 1989 brief in response to defendants’ summary judgment motion, approximately six months after the arbitration. Accordingly, the Court concluded that the Act precluded plaintiffs from raising any objections to confirming the arbitration. Therefore, the Court confirmed the Arbitrator’s award. Mainly due to the preclusive effect of the Arbitrator’s decision, the Court granted defendants’ motion for summary judgment dismissing plaintiffs’ entire case and for summary judgment on defendants’ first three counterclaims.

A few days before the Court rendered its decision, plaintiffs submitted a motion to amend their complaint. In this new complaint plaintiffs seek to add a cause of action to vacate the Arbitrator’s decision on the grounds of bias. Plaintiffs presented what they termed “newly discovered evidence.” Plaintiffs contend that this evidence indicates that Weston not only wrote the feasibility study but indemnified the Agency for its accuracy. Thus, plaintiffs conclude that the Arbitrator was clearly biased and his decision should be vacated.

Free access — add to your briefcase to read the full text and ask questions with AI

Pennsylvania Engineering Corp. v. Islip Resource Recovery Agency, 714 F. Supp. 634, 1989 U.S. Dist. LEXIS 6610, 1989 WL 63925 (E.D.N.Y. 1989).

714 F. Supp. 634 (Pennsylvania Engineering Corp. v. Islip Resource Recovery Agency) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Untitled Case
S.D. New York, 2026
Untitled Case
S.D. New York, 2025
Chilcott Entertainment L.L.C. v. John G. Kinnard Co.
10 P.3d 723 (Colorado Court of Appeals, 2000)
In re the Arbitration between Disston Co. & Aktiebolag
187 A.D.2d 283 (Appellate Division of the Supreme Court of New York, 1992)