FRIEDMAN, Judge.
The Pennsylvania Department of Transportation (DOT) and James D. Morrissey, Inc. (Morrissey), for and on behalf of W.P. Dickerson and Son, Inc. (Dickerson), cross-appeal from an order of the Pennsylvania Board of Claims (Board) entering an award of damages in the amount of $826,000.00, plus six percent interest from September 16, 1988, in favor of Morrissey and Dickerson.1 Each of the parties asserts that the Board did not award the proper measure of damages.
In July of 1987, DOT issued a Notice to Bidders (Notice) for a contract (Contract) calling for the construction of a 4.4 mile-long section of Interstate 476 in Delaware County, Pennsylvania (Project). (Board’s Findings of Fact, Nos. 4 and 7.) The Notice was subsequently amended and supplemented by a total of five addenda, issued between July of 1987 and the Contract’s December 3, 1987 bid date; these addenda became part of the bid documents and, ultimately, the Contract. (Board’s Finding of Fact, No. 5.) The Project included the construction of various structures, including a number of bridges, culverts and retaining walls. (Board’s Finding of Fact, No. 8.) Among the retaining walls required by the Contract were fourteen “R-Walls” of varying lengths and heights needed to widen the existing roadway along a 2.1 mile-long segment of the Project.2 [11]*11(Board’s Findings of Fact, Nos. 9 and 11.) These R-Walls are the subject of this action.
Dickerson, a structures contractor, investigated the Project and decided to submit a subcontract bid for construction of the Project’s various structures to Morrissey. Mor-rissey, a general contractor with whom Dickerson had previously worked, expressed an interest in the Project, and the two companies sent representatives to a pre-bid conference on August 25,1987. During the conference, DOT did not mention any changes in the Notice requirements with respect to the R-Walls. (Board’s Findings of Fact, Nos. 13, 22 and 41.)
However, on October 5, 1987, October 14, 1987 and November 24, 1987, DOT issued Addenda Nos. 2, 3 and 4 respectively,3 so that as of the December 3,1987 bid date, the Special Provisions portion of the amended Notice provided as follows with regard to the types of proprietary wall systems which could be used to construct the R-Walls under the Contract:
(a)Construct Reinforced Concrete Retaining Wall or Proprietary Retaining Wall Alternate, either a re-enforced Earth Wall, Retained Earth Wall, Doublewal or Experimental Evergreen wall (use Evergreen wall as an alternate on [the R-Walls]) meeting the requirements of the Special Provision titled “PROPRIETARY WALLS”, and as herein specified.
(b) The Special Provisions section of the Notice also contained a five-page write-up, under the subheading “EVERGREEN WALL”, which provided a technical description of how the Evergreen walls were to be fabricated, installed and backfilled.
(c) The schematic drawings for the R-Walls contained a note which stated:
1. Construct Reinforced Concrete Retaining Wall or Proprietary Retaining Wall or Alternate, either a Reinforced Earth Wall, Retained Earth Wall or Doublewal.
(Board’s Finding of Fact, No. 34.)
On December 3,1987, Dickerson submitted a quotation to Morrissey in the amount of $42,617,542.80 to construct the Project’s structures. (Board’s Finding of Fact, No. 15.) Understanding that Evergreen walls were permitted by the Contract, and having determined that Evergreen walls would be $825,000.00 less expensive than Doublewal, Dickerson based its bid to Morrissey on its plan to use Evergreen walls for the Project’s fourteen R-Walls.4 (Board’s Findings of [12]*12Fact, Nos. 16-17, 86.) Morrissey then incorporated Dickerson’s bid into its own bid to DOT. (Board’s Finding of Fact, No. 86.)
Morrissey was the successful bidder and, on January 13, 1988, Morrissey entered into a written contract with DOT based upon its bid; the original Contract amount was $88,-432,273.27. (Board’s Findings of Fact, Nos. 88-89.) In late January, Jeff Wendel of DOT told Dickerson for the first time that Evergreen walls could not be used on the Project. (Board’s Finding of Fact, No. 96.) This was confirmed at a February 1, 1988 pre-construction conference, at which DOT representatives told Dickerson that it would not be allowed to use the Evergreen walls as presented in the conceptual drawings submitted for DOT approval; DOT stated that the Evergreen walls had been disallowed by Addendum No. 4.5 (Board’s Finding of Fact, No. 96.)
Dickerson sought review of the matter before DOT’s District Claims Review Committee (Committee), arguing that the Contract permitted use of Evergreen walls and that Dickerson would incur substantial costs if forced to use another proprietary retaining wall system. In March 1988, the Committee rejected Dickerson’s request to use Evergreen walls and denied Dickerson’s claim for additional funds to compensate Dickerson for the added expense of using a product other than Evergreen walls. (Board’s Findings of Fact, Nos. 97-98.)
Immediately following the Committee’s denial, Dickerson contacted the Atlantic Pipe Corporation (Atlantic), the only manufacturer of Doublewal units and the only authorized Doublewal supplier, directing Atlantic to begin the work necessary to timely furnish the R-Walls for the Project.6 (Board’s Findings of Fact, Nos. 99, 110.) Atlantic agreed to provide Dickerson with Doublewal for the Project; however, Atlantic would not guarantee timely delivery.7 Nevertheless, having no other choice, Dickerson was forced to work with Atlantic. (Board’s Findings of Fact, Nos. 104, 109 — Í0, 117.) Despite being told by Dickerson to begin delivering Double-wal components in August of 1988 and to complete delivery of all R-Wall units by year’s end, Atlantic delivered the first Doub-lewal units three and a half months later than requested and completed delivery almost a full year later than originally sched[13]*13uled.8 (Board’s Findings of Fact, Nos. 105-06, 116.) As a result, despite Dickerson’s best efforts, the Project’s R-Wall erection operation was inefficient and costly. (Board’s Findings of Fact, Nos. 115,118-19.)
Morrissey and Dickerson filed a claim with the Board for $1,523,124.00 in damages.9 Of that amount, $825,000.00 represented the estimated cost of substituting the Doublewal product for the Evergreen units; the balance covered the increased costs and overhead which Morrissey and Dickerson claimed were associated with the delays in using Double-wal.10 (Board op. at 20-21.) Concluding that the Contract’s specifications regarding the R-Walls were glaringly ambiguous, and that Dickerson reasonably relied upon an investigation and DOT’s own advice to use the Evergreen wall quotation in its bid to Morrissey, the Board determined that DOT breached the Contract by disallowing use of the Evergreen product after awarding the Contract. (Board’s Findings of Fact, Nos. 121-24; Board’s Conclusions of Law, Nos. 3-10.)
However, the Board determined that Dickerson was only entitled to damages equalling the under-bid amount of $825,000.00, plus 6% interest; the Board did not award damages for the remaining costs alleged by Dickerson as associated with the use of the Doublewal system. Citing Taylor v.
Free access — add to your briefcase to read the full text and ask questions with AI
FRIEDMAN, Judge.
The Pennsylvania Department of Transportation (DOT) and James D. Morrissey, Inc. (Morrissey), for and on behalf of W.P. Dickerson and Son, Inc. (Dickerson), cross-appeal from an order of the Pennsylvania Board of Claims (Board) entering an award of damages in the amount of $826,000.00, plus six percent interest from September 16, 1988, in favor of Morrissey and Dickerson.1 Each of the parties asserts that the Board did not award the proper measure of damages.
In July of 1987, DOT issued a Notice to Bidders (Notice) for a contract (Contract) calling for the construction of a 4.4 mile-long section of Interstate 476 in Delaware County, Pennsylvania (Project). (Board’s Findings of Fact, Nos. 4 and 7.) The Notice was subsequently amended and supplemented by a total of five addenda, issued between July of 1987 and the Contract’s December 3, 1987 bid date; these addenda became part of the bid documents and, ultimately, the Contract. (Board’s Finding of Fact, No. 5.) The Project included the construction of various structures, including a number of bridges, culverts and retaining walls. (Board’s Finding of Fact, No. 8.) Among the retaining walls required by the Contract were fourteen “R-Walls” of varying lengths and heights needed to widen the existing roadway along a 2.1 mile-long segment of the Project.2 [11]*11(Board’s Findings of Fact, Nos. 9 and 11.) These R-Walls are the subject of this action.
Dickerson, a structures contractor, investigated the Project and decided to submit a subcontract bid for construction of the Project’s various structures to Morrissey. Mor-rissey, a general contractor with whom Dickerson had previously worked, expressed an interest in the Project, and the two companies sent representatives to a pre-bid conference on August 25,1987. During the conference, DOT did not mention any changes in the Notice requirements with respect to the R-Walls. (Board’s Findings of Fact, Nos. 13, 22 and 41.)
However, on October 5, 1987, October 14, 1987 and November 24, 1987, DOT issued Addenda Nos. 2, 3 and 4 respectively,3 so that as of the December 3,1987 bid date, the Special Provisions portion of the amended Notice provided as follows with regard to the types of proprietary wall systems which could be used to construct the R-Walls under the Contract:
(a)Construct Reinforced Concrete Retaining Wall or Proprietary Retaining Wall Alternate, either a re-enforced Earth Wall, Retained Earth Wall, Doublewal or Experimental Evergreen wall (use Evergreen wall as an alternate on [the R-Walls]) meeting the requirements of the Special Provision titled “PROPRIETARY WALLS”, and as herein specified.
(b) The Special Provisions section of the Notice also contained a five-page write-up, under the subheading “EVERGREEN WALL”, which provided a technical description of how the Evergreen walls were to be fabricated, installed and backfilled.
(c) The schematic drawings for the R-Walls contained a note which stated:
1. Construct Reinforced Concrete Retaining Wall or Proprietary Retaining Wall or Alternate, either a Reinforced Earth Wall, Retained Earth Wall or Doublewal.
(Board’s Finding of Fact, No. 34.)
On December 3,1987, Dickerson submitted a quotation to Morrissey in the amount of $42,617,542.80 to construct the Project’s structures. (Board’s Finding of Fact, No. 15.) Understanding that Evergreen walls were permitted by the Contract, and having determined that Evergreen walls would be $825,000.00 less expensive than Doublewal, Dickerson based its bid to Morrissey on its plan to use Evergreen walls for the Project’s fourteen R-Walls.4 (Board’s Findings of [12]*12Fact, Nos. 16-17, 86.) Morrissey then incorporated Dickerson’s bid into its own bid to DOT. (Board’s Finding of Fact, No. 86.)
Morrissey was the successful bidder and, on January 13, 1988, Morrissey entered into a written contract with DOT based upon its bid; the original Contract amount was $88,-432,273.27. (Board’s Findings of Fact, Nos. 88-89.) In late January, Jeff Wendel of DOT told Dickerson for the first time that Evergreen walls could not be used on the Project. (Board’s Finding of Fact, No. 96.) This was confirmed at a February 1, 1988 pre-construction conference, at which DOT representatives told Dickerson that it would not be allowed to use the Evergreen walls as presented in the conceptual drawings submitted for DOT approval; DOT stated that the Evergreen walls had been disallowed by Addendum No. 4.5 (Board’s Finding of Fact, No. 96.)
Dickerson sought review of the matter before DOT’s District Claims Review Committee (Committee), arguing that the Contract permitted use of Evergreen walls and that Dickerson would incur substantial costs if forced to use another proprietary retaining wall system. In March 1988, the Committee rejected Dickerson’s request to use Evergreen walls and denied Dickerson’s claim for additional funds to compensate Dickerson for the added expense of using a product other than Evergreen walls. (Board’s Findings of Fact, Nos. 97-98.)
Immediately following the Committee’s denial, Dickerson contacted the Atlantic Pipe Corporation (Atlantic), the only manufacturer of Doublewal units and the only authorized Doublewal supplier, directing Atlantic to begin the work necessary to timely furnish the R-Walls for the Project.6 (Board’s Findings of Fact, Nos. 99, 110.) Atlantic agreed to provide Dickerson with Doublewal for the Project; however, Atlantic would not guarantee timely delivery.7 Nevertheless, having no other choice, Dickerson was forced to work with Atlantic. (Board’s Findings of Fact, Nos. 104, 109 — Í0, 117.) Despite being told by Dickerson to begin delivering Double-wal components in August of 1988 and to complete delivery of all R-Wall units by year’s end, Atlantic delivered the first Doub-lewal units three and a half months later than requested and completed delivery almost a full year later than originally sched[13]*13uled.8 (Board’s Findings of Fact, Nos. 105-06, 116.) As a result, despite Dickerson’s best efforts, the Project’s R-Wall erection operation was inefficient and costly. (Board’s Findings of Fact, Nos. 115,118-19.)
Morrissey and Dickerson filed a claim with the Board for $1,523,124.00 in damages.9 Of that amount, $825,000.00 represented the estimated cost of substituting the Doublewal product for the Evergreen units; the balance covered the increased costs and overhead which Morrissey and Dickerson claimed were associated with the delays in using Double-wal.10 (Board op. at 20-21.) Concluding that the Contract’s specifications regarding the R-Walls were glaringly ambiguous, and that Dickerson reasonably relied upon an investigation and DOT’s own advice to use the Evergreen wall quotation in its bid to Morrissey, the Board determined that DOT breached the Contract by disallowing use of the Evergreen product after awarding the Contract. (Board’s Findings of Fact, Nos. 121-24; Board’s Conclusions of Law, Nos. 3-10.)
However, the Board determined that Dickerson was only entitled to damages equalling the under-bid amount of $825,000.00, plus 6% interest; the Board did not award damages for the remaining costs alleged by Dickerson as associated with the use of the Doublewal system. Citing Taylor v. Kaufhold, 368 Pa. 538, 84 A.2d 347 (1951), the Board stated, “When a breach in contract occurs, the party sustaining damages is entitled to recover such damages provided; 1. The damages were such as would naturally and ordinarily result from the breach. 2. They were reasonable [sic] foreseeable and within the contemplation of the parties at the time they made the contract. 3. They could be proven with reasonable certainty.” (Board op. at 24.) The Board reasoned that, had Dickerson based its bid on the Doublewal system, the bid would have been $825,000.00 higher and, therefore, this difference was a natural and ordinary result of the breach. However, the Board viewed the balance of the damages claimed by Morrissey and Dickerson, i.e., those costs stemming from the Doublewal manufacturer’s inability to supply its product in a timely fashion, as neither reasonably foreseeable nor within the contemplation of the parties. (Board op. at 24.) The parties cross-appealed from this decision.
On appeal to this court,11 Morrissey and Dickerson argue that: (1) Dickerson is entitled to recover the difference between the actual costs reasonably incurred by Dickerson in using the Doublewal system instead of the Evergreen wall system allowed by the Contract ($1,410,300.00); and (2) Morrissey is entitled to an award equal to 8% of Dickerson’s award as a general contractor mark-up [14]*14($112,824.00). On the other hand, in its appeal,12 DOT argues that Dickerson is entitled to only $600,000.00, plus 6% interest. DOT maintains that the record lacks substantial evidence to support the Board’s finding that Dickerson underbid by $825,000.00; in fact, DOT points to evidence which shows that Dickerson only lowered that bid by $600,-000.00.13 Thus, using the same reasoning employed by the Board, DOT contends that Dickerson only lost $600,000.00 as a natural and ordinary result of the breach, and any damages sought by Dickerson over and above this amount were neither foreseeable nor within the contemplation of the parties at the time they made the Contract.
In the law of contracts, remedies for breach of contract are designed to protect either a party’s: (1) expectation interest, by attempting to put him in as good a position as he would have been had there been no breach; (2) reliance interest, by attempting to put him back in the position in which he would have been had the contract not been made; or (3) restitution interest, by requiring the other party to disgorge the benefit he received by returning it to the party who conferred it. Trosky v. Civil Service Commission, 539 Pa. 356, 652 A.2d 813 (1995) (citing Restatement (Second) of Contracts § 344, comment a). Although the parties here agree that the correct measure of damages in this case is to place Dickerson and Morrissey as nearly as possible in the same position they would have occupied had there been no breach, (DOT’s brief at 10; Morris-sey’s brief at 18), the parties disagree as to the amount that would achieve this goal. After consideration of both positions, we agree with Morrissey and Dickerson.
At the time Dickerson submitted its bid, it was aware that performing the work using Evergreen walls would cost considerably less than using Doublewal. In fact, because the Contract allowed Dickerson to use either wall system, Dickerson actually performed an analysis comparing the cost of the two systems and concluded, based upon the information available to it at the time, that Evergreen walls would be $825,000.00 less expensive than Doublewal. (Board’s Finding of Fact, No. 85.) Dickerson elected to bid the R-Walls based on its use of the Evergreen wall system, but was forced to switch to Doublewal when DOT subsequently breached the Contract. Due to product delivery delays beyond Dickerson’s control, the actual cost of using Doublewal was much greater than anticipated in December 1987 when Dickerson originally performed its cost analysis and formulated its bid.
In limiting Dickerson’s recovery to the $825,000.00 cost differential as estimated at the time of the bid, the Board concluded that Atlantic’s delivery delays, and the accompanying increased costs to Dickerson, did not stem from the ambiguity in the Contract but, rather, represented the type of unforeseeable and unanticipated contingencies for which a contractor ordinarily assumes responsibility. In reaching this conclusion, the Board noted that there was no indication that Dickerson would have submitted anything other than an [15]*15$825,000.00 difference even if the Contract had clearly allowed only the Doublewal system and, further, the Board determined that these delivery delay costs still would have arisen had Dickerson utilized his original bid based on Doublewal. (Board op. at 24-25.) We cannot accept this reasoning.
First, we point out that if the Contract had clearly allowed only for the use of Doublewal, Dickerson would have known at the time of the bid that he would be forced to deal with a single-source supplier; therefore, he could have reflected the assumption of that risk in the bid amount.14 (See R.R. at 210a-13a.) Because of the Contract’s ambiguity, however, Dickerson reasonably believed that he could elect to use the Evergreen wall system, and he did. Thus, on December 3, 1987, the only risk that Dickerson contemplated and, therefore, the only risk for which he could be held responsible, was the risk of using Evergreen walls.
Moreover, contrary to the Board’s assumption, the record indicates that the delivery delays might not have arisen if Dickerson actually had submitted his original bid based on Doublewal because, in that event, Dickerson would have begun to deal with Atlantic much sooner. The fact that Dickerson was forced by DOT’s breach to deal with Atlantic at a later date negatively impacted on Atlantic’s delivery schedule. Indeed, when Dickerson met with Atlantic in an effort to resolve the delivery problems, Atlantic was candid in telling Dickerson that they had other contractors whose orders were in front of his and whose projects would be given precedence over this Project. (Board’s Findings of Fact, Nos. 107-08.)
Thus, the Board erred both by assessing Dickerson’s damages as of the December 3, 1987 bid date and by limiting those damages to the estimated difference between the costs of the Evergreen and Doublewal systems on that date. Clearly, damages do not arise until a contract is breached; in this case, DOT did not breach the Contract until some seven weeks after the bid date, after the Contract had been executed and Dickerson and its Evergreen wall supplier had begun preparing the drawings and calculations required by the Contract for review by DOT prior to installation of the walls. Accordingly, Dickerson’s damages could not have been properly assessed until DOT breached the Contract. Moreover, as a result of DOT prohibiting Morrissey from using the Evergreen walls permitted under the original Contract, DOT, in effect, substituted that Contract with one requiring Morrissey to use only Doublewal. Because Atlantic was the sole supplier of Doublewal, the breach re[16]*16quired that Dickerson endure whatever delivery problems and extra costs might arise as a consequence of dealing with a sole supplier.15 DOT knew or should have known that Atlantic was the sole supplier of Doublewal, the only system it would accept under the substitute contract occasioned by its breach, and that such problems and costs are risks attendant to ordering from a sole supplier; therefore, DOT is liable for all costs of using Doublewal as a foreseeable result of Atlantic’s performance.
Dickerson should be placed as nearly as possible in the same economic position he would have occupied had there been no breach. “In other words, [it] is entitled to be reimbursed for the money actually paid out and for all reasonable and proper expenses incurred on the faith of the contract.” Harman v. Chambers, 358 Pa. 516, 521, 57 A.2d 842, 845 (1948). Based on the Contract here, Dickerson properly elected to construct the R-Walls using the Evergreen wall system; having done so, it is entitled to the benefit of that bargain. Thus, Dickerson should recover damages equal to the difference between what it actually cost Dickerson to construct the R-Walls using Doublewal and what it would have cost to construct the R-Walls had Dickerson been allowed to use Evergreen walls. This conclusion is particularly compelling where, as here, the Board found that Dickerson did everything it could to try to mitigate the impact of the problem. (Board’s Finding of Fact, No. 119.)
Morrissey and Dickerson also contend that the Board’s damage award, aside from being insufficient, is incorrect in that it only accounts for the damages which Dickerson, as subcontractor, would be entitled to recover, but does not include any award of damages to compensate Morrissey, as general contractor, for its own increased costs and damages. Morrissey and Dickerson maintain that Morrissey is entitled to an amount equal to eight percent (8%) of any award to Dickerson as a general contractor’s mark-up for Morrissey. We agree. In fact, the evidence, unchallenged by DOT, established that this markup was very reasonably included as part of Dickerson’s calculation of its actual costs. (R.R. at 99a, 160a, 474a, 560a.)
Dickerson is not required to prove its actual costs with mathematical certainty; rather, it need only introduce evidence which affords a sufficient basis for estimating the damages with reasonable certainty. Although guesses and speculation are not permitted, estimates which have a basis in reason are legally sufficient to support an award of damages for breach of contract. Burly Construction Corp. v. Department of Justice, 4 Pa.Cmwlth. 46, 284 A.2d 841 (1971). Here, Morrissey and Dickerson have presented considerable evidence to establish that the actual cost to construct the R-Walls using Doublewal was $4,642,450.00, and that a reasonable estimate of what it would have cost to construct the R-Walls using Evergreen walls was $3,233,150.00, for a difference of $1,410,300.00. Because Morrissey is entitled to a reasonable general contractor’s markup of 8% of this amount, or $112,824.00, Morris-sey and Dickerson claim entitlement to damages totaling $1,523,124.00. For its part, although DOT argued that Dickerson can recover only $600,000.00 of these costs, DOT did not dispute the accuracy of Dickerson’s calculations of actual cost, nor did DOT pres[17]*17ent any evidence to contradict these figures. Therefore, the evidence presented by Dickerson, unchallenged by DOT, is sufficient to establish an award of damages.
Accordingly, because these figures have been established, we do not remand for the trial court to determine the amount of damages; rather, in the interest of judicial economy, we now reverse and modify the Board’s award of damages in favor of Morrissey and Dickerson, increasing it from an award of $825,00.00, with 6% interest from September 16.1988, to an award of $1,523,124.00, representing $1,410,300.00 in actual costs and $112,824.00 as an 8% general contractor markup, with 6% interest .from September 16.1988.
ORDER
AND NOW, this 8 th day of August, 1996, the order of the Pennsylvania Board of Claims, dated July 14, 1995, in favor of James D. Morrissey, Inc., for and on behalf of W.P. Dickerson and Son, Inc., and against the Commonwealth of Pennsylvania, Department of Transportation, in the amount of $825,00.00, with 6% interest from September 16, 1988, is hereby affirmed to the extent that it holds the Department of Transportation liable for the payment of damages. With regard to the amount of damages for which the Department of Transportation is liable, the order is reversed and modified, increasing the damage award to $1,523,-124.00, representing $1,410,300.00 in actual costs and $112,824.00 as an 8% general contractor markup, with 6% interest from September 16,1988.