Pelco Construction, Inc. v. Dannenbaum Engineering Corp.

404 S.W.3d 48, 2013 WL 1488025, 2013 Tex. App. LEXIS 4601
CourtCourt of Appeals of Texas
DecidedApril 11, 2013
DocketNo. 01-12-00421-CV
StatusPublished
Cited by19 cases

This text of 404 S.W.3d 48 (Pelco Construction, Inc. v. Dannenbaum Engineering Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pelco Construction, Inc. v. Dannenbaum Engineering Corp., 404 S.W.3d 48, 2013 WL 1488025, 2013 Tex. App. LEXIS 4601 (Tex. Ct. App. 2013).

Opinion

OPINION

LAURA CARTER HIGLEY, Justice.

Peleo Construction, Inc. appeals the trial court’s granting of two motions that dismissed Peleo Construction’s claims against Dannenbaum Engineering Corporation, Dannenbaum Engineering Company— Houston, LLC, Steven Lloyd McGarraugh, Alan D. Hirshman, Kurt Amundson, and Amundson Consulting, Inc. The dismissals were all based on Peleo Construction’s failure to file a certificate of merit along with its petition. In one issue, Peleo Construction argues that the trial court erred by dismissing its claims against appellees because a certificate of merit was not required for the claims it brought.

We affirm, in part, and reverse and remand, in part.

Background

The Oak Island Volunteer Fire Department’s fire station was destroyed by Hurricane Ike in 2008. Chambers County sought funding from the Federal Emergency Management Agency (“FEMA”) to reconstruct the fire station.

Chambers County entered into a master services agreement (“MSA”) with Dannenbaum Engineering Company— Houston, LLC to oversee the design and reconstruction of the fire station. Alan Hirshman, a licensed engineer, and Steven McGarraugh, a licensed architect, provided their services to Dannenbaum Engineering Company-Houston, LLC through another company: Dannenbaum Engineering Corporation. The parties draw no distinction between the two Dannenb-aum companies in their briefs and nothing in our analysis requires a differentiation. Accordingly, for the purposes of this appeal, we will treat the two companies as a single entity, “Dannenbaum Engineering.”

According to the terms of the MSA, the services provided by Dannenbaum Engineering were divided into two phases. The first phase consisted of assessment and design of the fire station. The second phase consisted of oversight of the construction of the fire station. The MSA provided, “Phase II shall not commence until the permanent repair project has been approved and funds have been provided by FEMA.”

As it neared the second phase of the MSA, Dannenbaum Engineering entered into a Staff Support Agreement with Amundson Consulting, Inc. Under the contract, Amundson Consulting provided the services of Kurt Amundson. Amund-son worked as an emergency management consultant. He had “28 years[’] experience in assisting local governments [with] obtaining FEMA] Public Assistance Grants to complete projects to repair damages sustained from natural disasters.” His work involved overseeing the bidding [51]*51process and, when the bid was awarded to Peleo Construction, monitoring Peleo Construction’s “progress in constructing the Project to ensure that Peleo constructed the Project according to the contract terms, conditions, and specifications.” As provided in the contract, Amundson worked “under the supervision, direction and control of Dannenbaum Engineering. For all of his work, Amundson reported to Hirshman.

Peleo Construction was one of the businesses that submitted a sealed bid to construct the fire station. Before submitting a bid, Peleo Construction met with representatives of Chambers County, Hirshman, and Amundson in a pre-bid conference. At the conference, Hirshman “discussed the construction plans and specifications for the reconstruction” of the fire station. Peleo Construction alleges that Hirshman and Amundson, among others, told it that FEMA funding for the fire station project had been approved.

Chambers County ultimately awarded the construction contract to Peleo Construction. One provision of Peleo Construction’s contract required Chambers County,

at the written request of [Peleo Construction], prior to commencement of the Work and thereafter, [to] furnish [Peleo Construction] reasonable evidence that financial arrangements have been made to fulfill [Chamber County’s] obligations under the Contract. Furnishing of such evidence shall be a condition precedent to commencement or continuation of the Work. After such evidence has been furnished, the Owner shall not materially vary such financial arrangements without prior notice to [Peleo Construction].

The parties dispute whether, at the time that Peleo Construction was awarded the contract, FEMA had approved the eon-struetion for reimbursement. Regardless, around the time that Chambers County began accepting bids on the contract, Amundson was working to obtain approval of an amendment with FEMA for increased costs. One of the reasons asserted for increased cost construction was “the building design had to be changed to meet new [Americans with Disabilities Act (‘ADA’) ] requirements. The new ADA requirements required that there be an ADA ramp inside the building not just on the outside of the building.” Adding the interior ramp would require increasing the size of the building.

At least by June 15, 2010, FEMA had determined that the interior ramp was not required under the law and, accordingly, “the request for an increase in building size for the interior ADA ramp is not eligible for FEMA funding.” Nevertheless, on July 8, Chambers County and appellees provided Peleo Construction with a construction plan, which included the interior ramp. The plan was stamped “approved for construction.” Dannenbaum told Peleo Construction to begin construction, and Peleo Construction began work on July 14 even though FEMA had not approved the final plan or funding for the interior ramp.

Over the next four months, as Peleo Construction continued work on the fire station, Chambers County and appellees continued to communicate with FEMA to obtain approval for the interior ramp and the corresponding increase in size of the building. At some point in September 2010, Chambers County informed FEMA that redesigning the building to remove the interior ramp was not possible because construction had already begun and a redesign would require a costly stop to the project.

On October 28, 2010, Amundson contacted Michael Ramirez, a project manager for [52]*52Peleo Construction, and told him to stop construction. The parties dispute whether Amundson stated that the order to stop working came from FEMA. Nevertheless, Peleo Construction stopped work while Chambers County continued to seek approval on the interior ramp from FEMA.

On November 17, 2010, FEMA gave tentative approval to constructing the firehouse with the interior ramp. On December 7, Hirshman, on behalf of Dan-nenbaum Engineering, instructed Peleo Construction to resume construction of the firehouse. Instead, on December 14, Peleo Construction sent Chambers County a notice of termination of the contract.

Peleo Construction filed suit against Chambers County on April 8, 2011. On November 3, 2011, Peleo Construction filed an amended petition, adding Dannenbaum Engineering, McGarraugh, Hirshman, and Amundson to the suit. Peleo Construction asserted a claim of fraudulent misrepresentation against Dannenbaum Engineering, McGarraugh, Hirshman, and Amund-son. The thrust of the claim was that Dannenbaum Engineering, McGarraugh, Hirshman, and Amundson had misrepresented that FEMA had approved the construction plans given to Peleo Construction and that Peleo Construction was injured by the order to stop work on the construction.

In March 2012, Dannenbaum Engineering, McGarraugh, and Hirshman filed a motion to dismiss on the basis that Peleo Consti’uction was required to file a certificate of merit along with the petition that brought them into the suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PGAL, Inc. v. Ian Miramon and Caroline Miramon
Court of Appeals of Texas, 2025
Pelco Construction Co. v. Chambers County
495 S.W.3d 514 (Court of Appeals of Texas, 2016)
Toby Paul Couchman and Pro-Surv v. Elizabeth Cardona
471 S.W.3d 20 (Court of Appeals of Texas, 2015)
TIC N. Central Dallas 3, L.L.C. v. Envirobusiness, Inc.
463 S.W.3d 71 (Court of Appeals of Texas, 2014)
Dunham Engineering, Incorporated v. the Sherwin-Williams Company
404 S.W.3d 785 (Court of Appeals of Texas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
404 S.W.3d 48, 2013 WL 1488025, 2013 Tex. App. LEXIS 4601, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pelco-construction-inc-v-dannenbaum-engineering-corp-texapp-2013.