Pelco Construction Company v. Chambers County, Texas, Kurt Amundson, and Amundson Consulting, Inc.

CourtCourt of Appeals of Texas
DecidedSeptember 3, 2015
Docket01-14-00317-CV
StatusPublished

This text of Pelco Construction Company v. Chambers County, Texas, Kurt Amundson, and Amundson Consulting, Inc. (Pelco Construction Company v. Chambers County, Texas, Kurt Amundson, and Amundson Consulting, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pelco Construction Company v. Chambers County, Texas, Kurt Amundson, and Amundson Consulting, Inc., (Tex. Ct. App. 2015).

Opinion

Opinion issued September 3, 2015

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-14-00317-CV ——————————— PELCO CONSTRUCTION COMPANY, Appellant V. CHAMBERS COUNTY, TEXAS, KURT AMUNDSON, AND AMUNDSON CONSULTING, INC., Appellees

On Appeal from the 344th District Court Chambers County, Texas Trial Court Case No. CV-26356

OPINION

Pelco Construction Company filed suit against Chambers County, Texas,

Kurt Amundson, and Amundson Consulting, Inc. over a construction contract.

Chambers County counter-sued. The trial court granted summary judgment on

liability in favor of Chambers County and Amundson Consulting on all claims in the suit. The parties then proceeded to trial on Chambers County’s damages for its

breach of contract claim. The jury awarded Chambers County $151,879.50. The

trial court granted Chambers County’s motion for judgment notwithstanding the

verdict and rendered a verdict of $404,179.31 in damages. In five issues on

appeal, Pelco argues the trial court erred by (1) granting summary judgment in

favor of Chambers County on both parties’ breach of contract claims, (2) granting

the judgment notwithstanding the verdict, (3) refusing to include a proper

mitigation question in the jury charge, (4) granting summary judgment on Pelco’s

claims against Amundson Consulting, and (5) awarding attorneys’ fees.

We reverse and remand for a new trial.

Background

In 2008, Hurricane Ike landed on the Texas coast. Among the damage, the

Oak Island firehouse was destroyed. Chambers County developed plans to rebuild

the firehouse based on funding from the Federal Emergency Management Agency

(“FEMA”). Chambers County solicited bids. As a part of that process, officials

from Chambers County along with representatives of its architect, Dannenbaum

Engineering Corp., and representatives of Amundson Consulting met with

representatives of Pelco to discuss the project. Pelco alleges that, during that

meeting, Amundson represented that FEMA had approved funding for the

construction project.

2 Pelco bid on the project and was awarded the contract. During construction

of the firehouse, Pelco submitted two applications for payment based on money it

had already expended and earned. More than two months after Pelco submitted the

first application for payment, Dannenbaum certified 90% of the application for

payment. Chambers County paid the certified amount three days before

certification. Over one month after Pelco submitted the second application for

payment, Dannenbaum certified 90% of the application for payment. Chambers

County paid the certified amount seven days after certification.

On October 28, 2010, Amundson called Pelco, instructing them to stop work

on the project. According to Pelco, Amundson stated that FEMA had ordered the

work to stop due to the project plans not being approved for funding. That same

day, Dannenbaum sent a letter to Pelco instructing Pelco to stop work on the

project. Dannenbaum explained in the letter that “[t]he ceasing of the construction

operation is required while required administrative paper work for the construction

of the project is reviewed and approved by FEMA.” Dannenbaum said it would

inform Pelco when work could resume.

Forty days later, Dannenbaum sent Pelco a letter instructing it to resume

construction on the project. Pelco sent Dannenbaum a letter in response giving

notice of its termination of the contract based on a certain provision of the contract.

3 Pelco subsequently filed suit against Chambers County, Dannenbaum,

Amundson Consulting, and Amundson. The trial court dismissed Dannenbaum

from the suit based on Pelco’s failure to file a certificate of merit, and we

affirmed. 1 Pelco asserted, among other things, a breach of contract claim against

Chambers County. Pelco asserted fraudulent misrepresentation and negligent

misrepresentation claims against Amundson and Amundson Consulting.

Chambers County asserted a breach of contract counter-claim against Pelco.

In the course of litigation, the parties filed multiple motions for summary

judgment. Ultimately, the trial court granted summary judgment against Pelco on

its breach of contract claim. It also granted summary judgment on liability in favor

of Chambers County on its breach of contract claim. Subsequently, the trial court

granted summary judgment in favor of Amundson and Amundson Consulting on

Pelco’s fraudulent misrepresentation and negligent misrepresentation claims.

After all of the motions for summary judgment, the only issue remaining

was Chambers County’s damages on its breach of contract claim. After a jury

trial, the trial court granted a motion notwithstanding the verdict and awarded

Chambers County its full claim for damages and attorneys’ fees.

1 See Pelco Constr., Inc. v. Dannenbaum Eng’g Corp., 404 S.W.3d 48, 57 (Tex. App.—Houston [1st Dist.] 2013, no pet.).

4 Summary Judgment

In its first issue, Pelco asserts that the trial court erred by granting summary

judgment on liability against Pelco and in favor of Chambers County on both

parties’ breach of contract claims. In its fourth issue, Pelco asserts that the trial

court erred by granting summary judgment against Pelco on its fraudulent

misrepresentation and negligent misrepresentation claims against Amundson and

Amundson Consulting.

A. Standard of Review

The summary-judgment movant must conclusively establish its right to

judgment as a matter of law. See MMP, Ltd. v. Jones, 710 S.W.2d 59, 60 (Tex.

1986). Because summary judgment is a question of law, we review a trial court’s

summary judgment decision de novo. See Mann Frankfort Stein & Lipp Advisors,

Inc. v. Fielding, 289 S.W.3d 844, 848 (Tex. 2009).

To prevail on a “traditional” summary-judgment motion asserted under Rule

166a(c), a movant must prove that there is no genuine issue regarding any material

fact and that it is entitled to judgment as a matter of law. See TEX. R. CIV. P.

166a(c); Little v. Tex. Dep’t of Criminal Justice, 148 S.W.3d 374, 381 (Tex. 2004).

A matter is conclusively established if reasonable people could not differ as to the

conclusion to be drawn from the evidence. See City of Keller v. Wilson, 168

S.W.3d 802, 816 (Tex. 2005).

5 When it moves for summary judgment on a claim for which it bears the

burden of proof, a party must show that it is entitled to prevail on each element of

its cause of action. See Parker v. Dodge, 98 S.W.3d 297, 299 (Tex. App.—

Houston [1st Dist.] 2003, no pet.). The party meets this burden if it produces

evidence that would be sufficient to support an instructed verdict at trial. Id.

In contrast, a party moving for traditional summary judgment on a claim for

which it does not bear the burden of proof must either (1) disprove at least one

element of the plaintiff’s cause of action or (2) plead and conclusively establish

each essential element of an affirmative defense to rebut the plaintiff’s cause. See

Am. Tobacco Co., Inc. v. Grinnell, 951 S.W.2d 420, 425 (Tex. 1997). If the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Little v. Texas Department of Criminal Justice
148 S.W.3d 374 (Texas Supreme Court, 2004)
Seagull Energy E & P, Inc. v. Eland Energy, Inc.
207 S.W.3d 342 (Texas Supreme Court, 2006)
MacK Trucks, Inc. v. Tamez
206 S.W.3d 572 (Texas Supreme Court, 2006)
Hamilton v. Wilson
249 S.W.3d 425 (Texas Supreme Court, 2008)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
Timpte Industries, Inc. v. Gish
286 S.W.3d 306 (Texas Supreme Court, 2009)
Deep Nines, Inc. v. McAfee, Inc.
246 S.W.3d 842 (Court of Appeals of Texas, 2008)
Bank of Texas v. VR Electric, Inc.
276 S.W.3d 671 (Court of Appeals of Texas, 2008)
Centeq Realty, Inc. v. Siegler
899 S.W.2d 195 (Texas Supreme Court, 1995)
Swank v. Sverdlin
121 S.W.3d 785 (Court of Appeals of Texas, 2003)
MBM Financial Corp. v. Woodlands Operating Co.
292 S.W.3d 660 (Texas Supreme Court, 2009)
Spoljaric v. Percival Tours, Inc.
708 S.W.2d 432 (Texas Supreme Court, 1986)
Parker v. Dodge
98 S.W.3d 297 (Court of Appeals of Texas, 2003)
Allied Capital Partners, LP v. Proceed Technical Resources, Inc.
313 S.W.3d 460 (Court of Appeals of Texas, 2010)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Wohlfahrt v. Holloway
172 S.W.3d 630 (Court of Appeals of Texas, 2005)
Southwestern Electric Power Co. v. Grant
73 S.W.3d 211 (Texas Supreme Court, 2002)
Henry v. Masson
333 S.W.3d 825 (Court of Appeals of Texas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Pelco Construction Company v. Chambers County, Texas, Kurt Amundson, and Amundson Consulting, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/pelco-construction-company-v-chambers-county-texas-texapp-2015.