Pelco Construction Company v. Chambers County, Texas, Kurt Amundson, and Amundson Consulting, Inc.

Court of Appeals of Texas·Decided September 3, 2015·No. 01-14-00317-CV·Published

Opinion

Opinion issued September 3, 2015

In The

Court of Appeals

For The

First District of Texas

the suit. The parties then proceeded to trial on Chambers County’s damages for its breach of contract claim. The jury awarded Chambers County $151,879.50. The trial court granted Chambers County’s motion for judgment notwithstanding the verdict and rendered a verdict of $404,179.31 in damages. In five issues on appeal, Pelco argues the trial court erred by (1) granting summary judgment in favor of Chambers County on both parties’ breach of contract claims, (2) granting the judgment notwithstanding the verdict, (3) refusing to include a proper mitigation question in the jury charge, (4) granting summary judgment on Pelco’s claims against Amundson Consulting, and (5) awarding attorneys’ fees.

We reverse and remand for a new trial.

Background

In 2008, Hurricane Ike landed on the Texas coast. Among the damage, the Oak Island firehouse was destroyed. Chambers County developed plans to rebuild the firehouse based on funding from the Federal Emergency Management Agency (“FEMA”). Chambers County solicited bids. As a part of that process, officials from Chambers County along with representatives of its architect, Dannenbaum Engineering Corp., and representatives of Amundson Consulting met with representatives of Pelco to discuss the project. Pelco alleges that, during that meeting, Amundson represented that FEMA had approved funding for the construction project.

Pelco bid on the project and was awarded the contract. During construction of the firehouse, Pelco submitted two applications for payment based on money it had already expended and earned. More than two months after Pelco submitted the first application for payment, Dannenbaum certified 90% of the application for payment. Chambers County paid the certified amount three days before certification. Over one month after Pelco submitted the second application for payment, Dannenbaum certified 90% of the application for payment. Chambers County paid the certified amount seven days after certification.

On October 28, 2010, Amundson called Pelco, instructing them to stop work on the project. According to Pelco, Amundson stated that FEMA had ordered the work to stop due to the project plans not being approved for funding. That same day, Dannenbaum sent a letter to Pelco instructing Pelco to stop work on the project. Dannenbaum explained in the letter that “[t]he ceasing of the construction operation is required while required administrative paper work for the construction of the project is reviewed and approved by FEMA.” Dannenbaum said it would inform Pelco when work could resume.

Forty days later, Dannenbaum sent Pelco a letter instructing it to resume construction on the project. Pelco sent Dannenbaum a letter in response giving notice of its termination of the contract based on a certain provision of the contract.

Pelco subsequently filed suit against Chambers County, Dannenbaum, Amundson Consulting, and Amundson. The trial court dismissed Dannenbaum from the suit based on Pelco’s failure to file a certificate of merit, and we affirmed. 1 Pelco asserted, among other things, a breach of contract claim against Chambers County. Pelco asserted fraudulent misrepresentation and negligent misrepresentation claims against Amundson and Amundson Consulting. Chambers County asserted a breach of contract counter-claim against Pelco.

In the course of litigation, the parties filed multiple motions for summary judgment. Ultimately, the trial court granted summary judgment against Pelco on its breach of contract claim. It also granted summary judgment on liability in favor of Chambers County on its breach of contract claim. Subsequently, the trial court granted summary judgment in favor of Amundson and Amundson Consulting on Pelco’s fraudulent misrepresentation and negligent misrepresentation claims.

After all of the motions for summary judgment, the only issue remaining was Chambers County’s damages on its breach of contract claim. After a jury trial, the trial court granted a motion notwithstanding the verdict and awarded Chambers County its full claim for damages and attorneys’ fees.

1 See Pelco Constr., Inc. v. Dannenbaum Eng’g Corp., 404 S.W.3d 48, 57 (Tex.

App.—Houston [1st Dist.] 2013, no pet.).

Summary Judgment

In its first issue, Pelco asserts that the trial court erred by granting summary judgment on liability against Pelco and in favor of Chambers County on both parties’ breach of contract claims. In its fourth issue, Pelco asserts that the trial court erred by granting summary judgment against Pelco on its fraudulent misrepresentation and negligent misrepresentation claims against Amundson and Amundson Consulting. A. Standard of Review The summary-judgment movant must conclusively establish its right to judgment as a matter of law. See MMP, Ltd. v. Jones, 710 S.W.2d 59, 60 (Tex. 1986). Because summary judgment is a question of law, we review a trial court’s summary judgment decision de novo. See Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding, 289 S.W.3d 844, 848 (Tex. 2009).

To prevail on a “traditional” summary-judgment motion asserted under Rule 166a(c), a movant must prove that there is no genuine issue regarding any material fact and that it is entitled to judgment as a matter of law. See TEX. R. CIV. P. 166a(c); Little v. Tex. Dep’t of Criminal Justice, 148 S.W.3d 374, 381 (Tex. 2004). A matter is conclusively established if reasonable people could not differ as to the conclusion to be drawn from the evidence. See City of Keller v. Wilson, 168 S.W.3d 802, 816 (Tex. 2005).

When it moves for summary judgment on a claim for which it bears the burden of proof, a party must show that it is entitled to prevail on each element of its cause of action. See Parker v. Dodge, 98 S.W.3d 297, 299 (Tex. App.— Houston [1st Dist.] 2003, no pet.). The party meets this burden if it produces evidence that would be sufficient to support an instructed verdict at trial. Id.

In contrast, a party moving for traditional summary judgment on a claim for which it does not bear the burden of proof must either (1) disprove at least one element of the plaintiff’s cause of action or (2) plead and conclusively establish each essential element of an affirmative defense to rebut the plaintiff’s cause. See Am. Tobacco Co., Inc. v. Grinnell, 951 S.W.2d 420, 425 (Tex. 1997). If the movant meets its burden, the burden then shifts to the nonmovant to raise a genuine issue of material fact precluding summary judgment. See Centeq Realty, Inc. v. Siegler, 899 S.W.2d 195, 197 (Tex. 1995).

After an adequate time for discovery, the party without the burden of proof may move for a no-evidence summary judgment on the basis that there is no evidence to support an essential element of the non-moving party’s claim. TEX. R. CIV. P. 166a(i); Hamilton v. Wilson, 249 S.W.3d 425, 426 (Tex. 2008). Summary judgment must be granted unless the non-movant produces competent summary judgment evidence raising a genuine issue of material fact on the challenged elements. TEX. R. CIV. P. 166a(i); Hamilton, 249 S.W.3d at 426. A non-moving

party is “not required to marshal its proof; its response need only point out evidence that raises a fact issue on the challenged elements.” TEX. R. CIV. P. 166a (Notes & Comments 1997).

Free access — add to your briefcase to read the full text and ask questions with AI

Pelco Construction Company v. Chambers County, Texas, Kurt Amundson, and Amundson Consulting, Inc., (Tex. Ct. App. 2015).

Pelco Construction Company v. Chambers County, Texas, Kurt Amundson, and Amundson Consulting, Inc. (Pelco Construction Company v. Chambers County, Texas, Kurt Amundson, and Amundson Consulting, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Little v. Texas Department of Criminal Justice
148 S.W.3d 374 (Texas Supreme Court, 2004)
Seagull Energy E & P, Inc. v. Eland Energy, Inc.
207 S.W.3d 342 (Texas Supreme Court, 2006)
MacK Trucks, Inc. v. Tamez
206 S.W.3d 572 (Texas Supreme Court, 2006)
Hamilton v. Wilson
249 S.W.3d 425 (Texas Supreme Court, 2008)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
Timpte Industries, Inc. v. Gish
286 S.W.3d 306 (Texas Supreme Court, 2009)
Deep Nines, Inc. v. McAfee, Inc.
246 S.W.3d 842 (Court of Appeals of Texas, 2008)
Bank of Texas v. VR Electric, Inc.
276 S.W.3d 671 (Court of Appeals of Texas, 2008)
Centeq Realty, Inc. v. Siegler
899 S.W.2d 195 (Texas Supreme Court, 1995)
Swank v. Sverdlin
121 S.W.3d 785 (Court of Appeals of Texas, 2003)
MBM Financial Corp. v. Woodlands Operating Co.
292 S.W.3d 660 (Texas Supreme Court, 2009)
Spoljaric v. Percival Tours, Inc.
708 S.W.2d 432 (Texas Supreme Court, 1986)
Parker v. Dodge
98 S.W.3d 297 (Court of Appeals of Texas, 2003)
Allied Capital Partners, LP v. Proceed Technical Resources, Inc.
313 S.W.3d 460 (Court of Appeals of Texas, 2010)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Wohlfahrt v. Holloway
172 S.W.3d 630 (Court of Appeals of Texas, 2005)
Southwestern Electric Power Co. v. Grant
73 S.W.3d 211 (Texas Supreme Court, 2002)
Henry v. Masson
333 S.W.3d 825 (Court of Appeals of Texas, 2010)