Terracon Consultants, Inc. v. Northern Pride Communications, Inc.

CourtCourt of Appeals of Texas
DecidedMarch 2, 2023
Docket01-22-00755-CV
StatusPublished

This text of Terracon Consultants, Inc. v. Northern Pride Communications, Inc. (Terracon Consultants, Inc. v. Northern Pride Communications, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terracon Consultants, Inc. v. Northern Pride Communications, Inc., (Tex. Ct. App. 2023).

Opinion

Opinion issued March 2, 2023

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-22-00755-CV ——————————— TERRACON CONSULTANTS, INC., Appellant V. NORTHERN PRIDE COMMUNICATIONS, INC., Appellee

On Appeal from the 239th District Court Brazoria County, Texas Trial Court Case No. 114516-CV

MEMORANDUM OPINION

This is an interlocutory appeal from the trial court’s denial of a motion to

dismiss under section 150.002(e) of the Texas Civil Practice and Remedies Code.1

Appellee Northern Pride Communications, Inc. sued appellant Terracon

1 See TEX. CIV. PRAC. & REM. CODE § 150.002. Consultants, Inc., a professional engineering firm, for breach of contract and

negligence, asserting that Terracon breached its duties in providing materials testing

during a construction project. Terracon moved to dismiss Northern Pride’s suit,

asserting that it arose from Terracon’s provision of professional engineering services

and that Northern Pride failed to file a certificate of merit.2

The trial court denied the motion to dismiss. In its sole issue on appeal,

Terracon asserts that the trial court abused its discretion in denying its motion to

dismiss.3 We agree.

We reverse and remand.

Background

In early 2021, the United States Fish and Wildlife Service4 hired Northern

Pride to provide construction services on a project that included the replacement of

guy anchors on a communications tower in Brazoria County, Texas (the “Project”).

Northern Pride then contracted with Gulf Coast Concrete and Shell, Inc. (“Gulf”)5

to design and provide concrete for the Project. To ensure that the concrete met the

requisite quality standards, Northern Pride retained Terracon to provide construction

materials engineering and testing services.

2 See id. 3 See id. § 150.002(f) (authorizing interlocutory appeal). 4 The United States Fish and Wildlife Service is not a party to this appeal. 5 Gulf is a defendant in the trial court below, but not a party to this appeal. 2 In April 2021, Northern Pride and Terracon executed an “Authorization to

Proceed, Construction Materials Engineering and Testing Services” (the

“Contract”), which provided, in pertinent part, as follows:

Scope of Services. . . . This project involves the replacement of guy anchors for an existing communications tower. Approximately 6 cubic yards of concrete will be placed. Terracon understands that we will make 1 set of 6 cylinders and test the [sic] at 3, 7, 14, 28, 28-days [sic], with a 56-day hold as a spare. The mix used will be 5000 psi and the specified strength at 28-days is 4500 psi. .... 2. Cast-in-Place Concrete [Terracon will] [p]rovide an Engineering Technician to: .... ▪ Sample and test the fresh concrete for each mix. Perform tests for slump, air content, and concrete temperature only and cast test specimens. ▪ Perform compressive strength tests of concrete test cylinders in the field. .... Compensation. . . . . . . Please note that the number of tests and trips described in the Scope of Services does not constitute a minimum or maximum number of tests or trips that may be required for this project.

The Contract’s “Additional Terms and Conditions” included:

11. Sample Disposition, Affected Materials, and Indemnity. Samples are consumed in testing or disposed of upon completion of tests (unless stated otherwise in the Services).

3 Subsequently, Terracon obtained four cylinder samples of the concrete

provided by Gulf at the Project’s jobsite. Terracon’s testing revealed that the

compressive strength of the concrete did not comply with the quality standards that

Northern Pride had specified. In June 2021, Terracon issued an opinion letter to

Northern Pride, bearing an engineer’s seal, signature, and date,6 stating:

To the best of our knowledge, information, and belief, based upon observations and tests made by Terracon representatives, the concrete tested and observed by Terracon was NOT constructed in general accordance with the project plans and specifications provided to Terracon. The concrete did not meet the specified strength of 4,500 psi at 28 days. The concrete compressive strength was 1,380 psi at 28 days.

Northern Pride asserts that it “expressly advised” Terracon to retain a concrete

cylinder sample for further testing. However, Northern Pride later learned that,

although the Contract required Terracon to obtain six cylinder samples of fresh

concrete, Terracon had obtained only four cylinders. And all four of those cylinders

had been used in testing, so only a fractured piece of a cylinder remained. When

Northern Pride “asked that the sample be sent out for further testing,” Terracon

advised that it had been discarded in an office move.

6 See 22 TEX. ADMIN. CODE § 137.33(a) (Texas Bd. of Prof. Eng’g and Land Surveyors, Sealing Procedures) (“The purpose of the engineer’s seal is to assure the user of the engineering product that the work has been performed or directly supervised by the professional engineer named and to delineate the scope of the engineer’s work.”); id. § 137.33(b) (“License holders shall only seal work done by them, [or] performed under their direct supervision as defined in §131.2 of this title, relating to Definitions . . . . Upon sealing, engineers take full professional responsibility for that work.”). 4 Northern Pride notified Gulf about the faulty concrete and provided it with an

estimate of $63,457.00 to remobilize and to remove and replace the anchors. After

Gulf did not respond, Northern Pride filed the instant lawsuit against Gulf. When

Gulf learned that Northern Pride could not produce any of the concrete at issue, Gulf

moved for spoliation sanctions against Northern Pride. The trial court granted that

request and ordered that a “jury instruction regarding the spoliation of evidence will

be allowed” against Northern Pride.

Northern Pride then filed a First Amended Petition adding Terracon as a

defendant. It asserted claims against Terracon for breach of contract and negligence.

Northern Pride alleged that its Contract expressly required Terracon to obtain six

cylinder samples of the concrete provided by Gulf and that Terracon had materially

breached the Contract by only obtaining four such samples and by failing to retain a

concrete sample for further testing.

With respect to its negligence claim, Northern Pride alleged that Terracon

owed it a common-law duty to perform the Contract services with ordinary care and

skill and that Terracon breached that duty by failing to “obtain the number of

concrete cylinder samples required under the [Contract]” and by failing to “protect

and maintain the remaining sample.” Northern Pride further alleged that Terracon’s

breaches deprived it of an opportunity to further test and obtain information

regarding the concrete, thus subjecting Northern Pride to Gulf’s spoilation claim.

5 Terracon moved to dismiss Northern Pride’s suit, under section 150.002 of

the Civil Practice and Remedies Code, on the ground that it arose from the provision

of services by a licensed engineer and that Northern Pride was required to file a

certificate of merit with its petition—which it did not do.7

Northern Pride responded that its claims “focused only on the number of

cylinder samples collected and the failure to retain one cylinder,” and therefore a

certificate of merit “would not be relevant” and would not aid the trial court in

determining whether Northern Pride’s suit had merit. Northern Pride also claimed

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dunham Engineering, Incorporated v. the Sherwin-Williams Company
404 S.W.3d 785 (Court of Appeals of Texas, 2013)
TIC N. Central Dallas 3, L.L.C. v. Envirobusiness, Inc.
463 S.W.3d 71 (Court of Appeals of Texas, 2014)
CBM Engineers, Inc. v. Tellepsen Builders, L.P.
403 S.W.3d 339 (Court of Appeals of Texas, 2013)
Melden & Hunt, Inc. v. East Rio Hondo Water Supply Corporation
520 S.W.3d 887 (Texas Supreme Court, 2017)
Ruben Aleman, M.D. v. Texas Medical Board
573 S.W.3d 796 (Texas Supreme Court, 2019)
Pelco Construction, Inc. v. Dannenbaum Engineering Corp.
404 S.W.3d 48 (Court of Appeals of Texas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Terracon Consultants, Inc. v. Northern Pride Communications, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/terracon-consultants-inc-v-northern-pride-communications-inc-texapp-2023.