Terracon Consultants, Inc. v. Northern Pride Communications, Inc.

Court of Appeals of Texas·Decided March 2, 2023·No. 01-22-00755-CV·Published

Opinion

Opinion issued March 2, 2023

In The

Court of Appeals

For The

First District of Texas

Consultants, Inc., a professional engineering firm, for breach of contract and negligence, asserting that Terracon breached its duties in providing materials testing during a construction project. Terracon moved to dismiss Northern Pride’s suit, asserting that it arose from Terracon’s provision of professional engineering services and that Northern Pride failed to file a certificate of merit.2 The trial court denied the motion to dismiss. In its sole issue on appeal, Terracon asserts that the trial court abused its discretion in denying its motion to dismiss.3 We agree.

We reverse and remand.

Background

In early 2021, the United States Fish and Wildlife Service4 hired Northern Pride to provide construction services on a project that included the replacement of guy anchors on a communications tower in Brazoria County, Texas (the “Project”). Northern Pride then contracted with Gulf Coast Concrete and Shell, Inc. (“Gulf”)5 to design and provide concrete for the Project. To ensure that the concrete met the requisite quality standards, Northern Pride retained Terracon to provide construction materials engineering and testing services.

2 See id.

3 See id. § 150.002(f) (authorizing interlocutory appeal).

4 The United States Fish and Wildlife Service is not a party to this appeal.

5 Gulf is a defendant in the trial court below, but not a party to this appeal.

In April 2021, Northern Pride and Terracon executed an “Authorization to Proceed, Construction Materials Engineering and Testing Services” (the “Contract”), which provided, in pertinent part, as follows:

Scope of Services. . . .

This project involves the replacement of guy anchors for an existing communications tower. Approximately 6 cubic yards of concrete will be placed. Terracon understands that we will make 1 set of 6 cylinders and test the [sic] at 3, 7, 14, 28, 28-days [sic], with a 56-day hold as a spare. The mix used will be 5000 psi and the specified strength at 28-days is 4500 psi.

....

2. Cast-in-Place Concrete [Terracon will] [p]rovide an Engineering Technician to:

....

▪ Sample and test the fresh concrete for each mix. Perform tests for slump, air content, and concrete temperature only and cast test specimens.

▪ Perform compressive strength tests of concrete test cylinders in the field.

....

Compensation. . . .

. . . Please note that the number of tests and trips described in the Scope of Services does not constitute a minimum or maximum number of tests or trips that may be required for this project.

The Contract’s “Additional Terms and Conditions” included:

11. Sample Disposition, Affected Materials, and Indemnity.

Samples are consumed in testing or disposed of upon completion of tests (unless stated otherwise in the Services).

Subsequently, Terracon obtained four cylinder samples of the concrete provided by Gulf at the Project’s jobsite. Terracon’s testing revealed that the compressive strength of the concrete did not comply with the quality standards that Northern Pride had specified. In June 2021, Terracon issued an opinion letter to Northern Pride, bearing an engineer’s seal, signature, and date,6 stating:

To the best of our knowledge, information, and belief, based upon observations and tests made by Terracon representatives, the concrete tested and observed by Terracon was NOT constructed in general accordance with the project plans and specifications provided to Terracon. The concrete did not meet the specified strength of 4,500 psi at 28 days. The concrete compressive strength was 1,380 psi at 28 days.

Northern Pride asserts that it “expressly advised” Terracon to retain a concrete cylinder sample for further testing. However, Northern Pride later learned that, although the Contract required Terracon to obtain six cylinder samples of fresh concrete, Terracon had obtained only four cylinders. And all four of those cylinders had been used in testing, so only a fractured piece of a cylinder remained. When Northern Pride “asked that the sample be sent out for further testing,” Terracon advised that it had been discarded in an office move.

6 See 22 TEX. ADMIN. CODE § 137.33(a) (Texas Bd. of Prof. Eng’g and Land Surveyors, Sealing Procedures) (“The purpose of the engineer’s seal is to assure the user of the engineering product that the work has been performed or directly supervised by the professional engineer named and to delineate the scope of the engineer’s work.”); id. § 137.33(b) (“License holders shall only seal work done by them, [or] performed under their direct supervision as defined in §131.2 of this title, relating to Definitions . . . . Upon sealing, engineers take full professional responsibility for that work.”).

Northern Pride notified Gulf about the faulty concrete and provided it with an estimate of $63,457.00 to remobilize and to remove and replace the anchors. After Gulf did not respond, Northern Pride filed the instant lawsuit against Gulf. When Gulf learned that Northern Pride could not produce any of the concrete at issue, Gulf moved for spoliation sanctions against Northern Pride. The trial court granted that request and ordered that a “jury instruction regarding the spoliation of evidence will be allowed” against Northern Pride.

Northern Pride then filed a First Amended Petition adding Terracon as a defendant. It asserted claims against Terracon for breach of contract and negligence. Northern Pride alleged that its Contract expressly required Terracon to obtain six cylinder samples of the concrete provided by Gulf and that Terracon had materially breached the Contract by only obtaining four such samples and by failing to retain a concrete sample for further testing.

With respect to its negligence claim, Northern Pride alleged that Terracon owed it a common-law duty to perform the Contract services with ordinary care and skill and that Terracon breached that duty by failing to “obtain the number of concrete cylinder samples required under the [Contract]” and by failing to “protect and maintain the remaining sample.” Northern Pride further alleged that Terracon’s breaches deprived it of an opportunity to further test and obtain information regarding the concrete, thus subjecting Northern Pride to Gulf’s spoilation claim.

Terracon moved to dismiss Northern Pride’s suit, under section 150.002 of the Civil Practice and Remedies Code, on the ground that it arose from the provision of services by a licensed engineer and that Northern Pride was required to file a certificate of merit with its petition—which it did not do.7 Northern Pride responded that its claims “focused only on the number of cylinder samples collected and the failure to retain one cylinder,” and therefore a certificate of merit “would not be relevant” and would not aid the trial court in determining whether Northern Pride’s suit had merit. Northern Pride also claimed that “[n]either the contractual requirement specifying the number of cylinder samples to be obtained nor the agreement to retain the remaining sample for further testing ‘implicate a professional engineer’s education, training, and experience in applying special knowledge or judgment.’”

The trial court denied the motion to dismiss. Terracon now appeals.

Certificate of Merit

In a single issue, Terracon argues that the trial court reversibly erred in denying its motion to dismiss because Northern Pride failed to file a statutorily required certificate of merit with its First Amended Petition. See TEX. CIV. PRAC. & REM. CODE § 150.002(a).

7 See TEX. CIV. PRAC. & REM. CODE § 150.002(a, e).

Free access — add to your briefcase to read the full text and ask questions with AI

Terracon Consultants, Inc. v. Northern Pride Communications, Inc., (Tex. Ct. App. 2023).

Terracon Consultants, Inc. v. Northern Pride Communications, Inc. (Terracon Consultants, Inc. v. Northern Pride Communications, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dunham Engineering, Incorporated v. the Sherwin-Williams Company
404 S.W.3d 785 (Court of Appeals of Texas, 2013)
TIC N. Central Dallas 3, L.L.C. v. Envirobusiness, Inc.
463 S.W.3d 71 (Court of Appeals of Texas, 2014)
CBM Engineers, Inc. v. Tellepsen Builders, L.P.
403 S.W.3d 339 (Court of Appeals of Texas, 2013)
Melden & Hunt, Inc. v. East Rio Hondo Water Supply Corporation
520 S.W.3d 887 (Texas Supreme Court, 2017)
Ruben Aleman, M.D. v. Texas Medical Board
573 S.W.3d 796 (Texas Supreme Court, 2019)
Pelco Construction, Inc. v. Dannenbaum Engineering Corp.
404 S.W.3d 48 (Court of Appeals of Texas, 2013)