Pegasus Construction Corp. v. Turner Construction Co.

929 P.2d 1200, 84 Wash. App. 744, 1997 Wash. App. LEXIS 131
CourtCourt of Appeals of Washington
DecidedJanuary 27, 1997
Docket38163-6-I
StatusPublished
Cited by14 cases

This text of 929 P.2d 1200 (Pegasus Construction Corp. v. Turner Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pegasus Construction Corp. v. Turner Construction Co., 929 P.2d 1200, 84 Wash. App. 744, 1997 Wash. App. LEXIS 131 (Wash. Ct. App. 1997).

Opinion

*746 Cox, J.

While this action was stayed pending arbitration, the arbitrator to whom the principal parties in this case had submitted their construction claims heard Turner Construction Company’s motion to dismiss. After considering all written and oral submissions of Turner and Pegasus Construction Corporation, the arbitrator ruled that neither party had complied with the terms in the prime contract for making claims. Accordingly, he did not award either party any damages. Pegasus moved in the trial court to vacate the award, arguing that the arbitrator had committed misconduct by failing to hear evidence on the merits of its claims. The trial court denied Pegasus’ motion, and the company appeals. We affirm.

In July 1992, Pegasus, as subcontractor, entered into a written agreement to perform concrete form work and placement for Turner. Turner was the prime contractor on the Bellevue Community College (BCC) bookstore project. The subcontract incorporated by reference the terms of the prime contract between Turner and BCC.

In early November 1992, Pegasus ceased work on the subcontract. Nearly four months later, Pegasus filed a claim against the bond and the retained percentage on the project. In March 1993, Pegasus commenced this action, claiming that Turner had breached the subcontract by failing to pay amounts due for labor and materials supplied to the project. Turner counterclaimed, seeking damages for Pegasus’ failure to perform under the subcontract. One year later, the trial court granted Turner’s motion to stay this action pending arbitration under the dispute resolution provision of the prime contract. Approximately one year later, Pegasus filed its demand for arbitration under the American Arbitration Association (AAA) Construction Industry Arbitration Rules.

In May 1995, Turner moved for summary judgment in *747 this action. It claimed that Pegasus’ failure to comply with the contractual claims procedure of the prime contract warranted dismissal of its claims. The trial court denied Turner’s motion. In its oral decision, the court made clear that it was denying the motion because it was inappropriate to lift the stay and enter judgment while the arbitration was pending.

Turner then renewed its motion to dismiss by presenting it to the arbitrator. After reviewing all written declarations and hearing oral argument from both parties, the arbitrator ruled that Pegasus was not entitled to an award of damages because it had failed to comply with the claims procedure of the prime contract. Because Turner had also failed to comply with the claims procedure, the arbitrator ruled that Turner’s counterclaims could not be the basis for a damages award.

Turner then returned to the trial court and moved for dismissal of this action based on the arbitrator’s decision. Pegasus moved to vacate the arbitrator’s award. The trial court granted Turner’s motion and denied Pegasus’. Thereafter, the trial court denied Pegasus’ motion for reconsideration. Pegasus appeals.

Arbitrator Misconduct

Pegasus argues that the arbitrator committed misconduct under RCW 7.04.160(3) by dismissing its claim on the basis of its failure to comply with the claims procedure in the prime contract. Pegasus contends that the arbitrator was required to hear evidence regarding the merits of the claim. We disagree.

Our review of an arbitrator’s award "is limited to that of the court which confirmed, vacated, modified or corrected that award.” 1 The trial court’s review is confined to the question of whether any of the statutory grounds *748 for vacation exist. 2 The burden of showing that such grounds exist is on the party seeking to vacate the award. 3

RCW 7.04.160(3) provides in part that a trial court shall vacate an arbitration award if the arbitrator is "guilty of misconduct, in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence, pertinent and material to the controversy; or of any other misbehavior, by which the rights of any party have been prejudiced.” 4

We have found only one published decision that addresses the evidentiary portion of RCW 7.04.160(3). In Groves v. Progressive Cas., 5 Groves was injured in a motorcycle-automobile collision. He settled with the automobile driver’s liability carrier for an amount substantially less than that driver’s liability limit. Groves’ entitlement to underinsured (UIM) benefits from his insurer depended entirely on a comparison between his damages and the liability limit on the automobile driver’s insurance policy. It did not depend on the amount or reasonableness of the settlement. 6 A panel of arbitrators denied Groves’ claim for UIM benefits from his insurer because he had settled for less than the at-fault driver’s liability limits. 7 On review, this court concluded that the trial court did not err by failing to vacate an award based on the arbitrator’s failure to hear evidence regarding the reasonableness of Groves’ settlement and his insurer’s bad faith. 8 The court reasoned that the evidence in question was irrelevant. 9

Groves is directly on point. Here, Pegasus’ appeal is *749 based solely on the failure of the arbitrator to hear evidence on issues other than the company’s compliance with the contractual claims procedure. Both parties submitted declarations to the arbitrator regarding the factual issue of whether Pegasus had received a copy of the prime contract. The arbitrator also heard oral argument from the parties. Pegasus asserts in its brief that "[e]xcept, possibly, for reading the written declarations, the arbitrator heard no witnesses and received no evidence.” But that argument fails to demonstrate that the arbitrator refused to hear any evidence that it submitted regarding the dis-positive issue, compliance with the claims procedure. Moreover, Pegasus made no written objection to any claimed failure by the arbitrator to hear evidence on the issue of compliance with the claims procedure. 10

Our Supreme Court recently reaffirmed that an agreement to submit disputes to arbitration makes the arbitrator the judge of both the law and the facts. 11 Here, the arbitrator concluded that Pegasus’ unpaid invoices became claims for the purposes of the dispute resolution provisions of the prime contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cummings v. Budget Tank Removal & Environmental Services, LLC
260 P.3d 220 (Court of Appeals of Washington, 2011)
S & S Const., Inc. v. Adc Properties LLC
211 P.3d 415 (Court of Appeals of Washington, 2009)
S&S Construction, Inc. v. ADC Properties, LLC
151 Wash. App. 247 (Court of Appeals of Washington, 2009)
Morrell v. WEDBUSH MORGAN SECURITIES INC.
178 P.3d 387 (Court of Appeals of Washington, 2008)
Godfrey v. Hartford Casualty Insurance
993 P.2d 281 (Court of Appeals of Washington, 2000)
Davidson v. Hensen
135 Wash. 2d 112 (Washington Supreme Court, 1998)
Expert Drywall, Inc. v. Ellis-Don Construction, Inc.
939 P.2d 1258 (Court of Appeals of Washington, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
929 P.2d 1200, 84 Wash. App. 744, 1997 Wash. App. LEXIS 131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pegasus-construction-corp-v-turner-construction-co-washctapp-1997.