Expert Drywall, Inc. v. Ellis-Don Construction, Inc.

939 P.2d 1258, 86 Wash. App. 884, 1997 Wash. App. LEXIS 1172
CourtCourt of Appeals of Washington
DecidedJuly 21, 1997
Docket37774-4-I
StatusPublished
Cited by17 cases

This text of 939 P.2d 1258 (Expert Drywall, Inc. v. Ellis-Don Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Expert Drywall, Inc. v. Ellis-Don Construction, Inc., 939 P.2d 1258, 86 Wash. App. 884, 1997 Wash. App. LEXIS 1172 (Wash. Ct. App. 1997).

Opinions

Cox, J.

Expert Drywall, Inc., seeks review of the trial court’s order confirming an arbitrator’s award in its favor against Ellis-Don Construction, Inc. Expert claims that the trial court erred by failing to vacate the award and remand to the arbitrator for consideration of attorney fees. Alternatively, Expert claims the trial court should have modified the award to include attorney fees. Because Expert was not entitled to an award of attorney fees under RCW 60.28.030, we affirm.

Ellis-Don was the general contractor for the construction of Plateau Middle School in Issaquah School District No. 411. Expert was the drywall subcontractor for that project. Expert began its work in early 1994. During the drywall work, the parties got into disputes over scheduling, resulting delays, and other interference with Expert’s ability to perform efficiently under the subcontract. Expert and Ellis-Don agreed to submit their disputes to arbitration. The District was not a party to that arbitration.

The arbitrator conducted an arbitration hearing be[887]*887tween the two parties over the course of six days during early April 1995. One day before the end of the hearing, Expert filed a claim against the retainage held by the District. In early May, the arbitrator advised both parties that he intended to rule substantially in favor of Expert on the claim. Each party then submitted requests for reconsideration. Expert included a request for fees under RCW 60.28.030, the labor and materials lien foreclosure statute. In anticipation of the arbitrator’s issuance of his final award, Ellis-Don sent Expert checks totaling the amount of the anticipated award. On June 29, 1995, the arbitrator issued his final award. The arbitrator also determined that there was no contractual, equitable, or statutory basis for an attorney fee award.

On May 5, 1995, before the arbitrator issued his award, Expert commenced this action against Ellis-Don and the District to foreclose a lien against the retainage held by the District. The claim to funds was the same claim that Expert and Ellis-Don had submitted to the arbitrator. Expert sought damages in the amount of the arbitration award and a ruling that those damages constituted a lien against the retainage held by the District under the prime contract. Expert also sought attorney fees under RCW 60.28.030 and confirmation of the arbitration award. Expert asked the trial court to stay the litigation pending issuance of the arbitration award.

Ellis-Don moved for summary dismissal of the claim, and the trial court granted the motion because the parties had submitted all their disputes to the arbitrator. Ellis-Don subsequently filed a motion in the trial court to confirm the arbitration award. Expert moved for modification of the award to include attorney fees or, in the alternative, for vacation and remand for the arbitrator to award it attorney fees. The trial court confirmed the arbitration award without modification. Expert appeals.

Statutory Attorney Fees

Expert argues that the trial court erred by failing to [888]*888modify or vacate the arbitrator’s award because the arbitrator failed to determine whether Expert was entitled to attorney fees under RCW 60.28.030. We disagree.

Our review of an arbitrator’s award "is limited to that of the court which confirmed, vacated, modified or corrected that award.”1 The trial court’s review is confined to the question of whether any of the statutory grounds for vacation exists.2

RCW 7.04.160(4) provides that a trial court shall vacate an arbitration award if the arbitrator "exceeded [her] powers, or so imperfectly executed them that a final and definite award upon the subject matter submitted was not made.” Either an erroneous rule of law or mistaken application thereof is a ground for vacation or modification under the statute.3 But the appellant must demonstrate prejudice from the alleged misconduct to merit relief.4 The party challenging the award has the burden to show that grounds for modification or vacation exist.5 The basis for vacation must appear on the face of the award.6 The arbitrator’s reasons for the award are not part of the award itself, and we do not consider the evidence before the arbitrator.7

Here, the arbitrator issued an award in which he first disposed of the basic claims of the parties. In paragraph 11 of the award, he addressed the question of attorney fees as follows:

I do not find any contractual or equitable authority with [889]*889regard to attorney’s fees and costs. I specifically find, that I do not have authority to award attorney’s fees and costs pursuant to RCW 60.28, et seq., as such authority lies solely with the Superior Court.[8]

In "Washington, attorney fees are recoverable only on the basis of contract, recognized ground in equity, or statute.9 Expert’s claim here is based solely on the last of these grounds. Thus, the question before this court is whether, on the face of the award, the arbitrator’s resolution of the attorney fees issue met any of the statutory criteria for vacating or modifying the award.

The last sentence of paragraph 11 of the award indicates that the arbitrator denied Expert’s fee request under RCW 60.28.030 because he believed the authority to make such an award lies solely with the superior court. We agree with the arbitrator’s conclusion that he could not make an award of fees on the basis of what was before him. But we reach that result on different grounds than those the arbitrator stated.

Although the arbitrator expressed the belief that he could not award fees because only the superior court had that authority, we disagree with that reasoning. This state has a strong policy favoring the arbitration of disputes as a quick and inexpensive alternative to litigation.10 We know of no authority that would preclude an arbitrator from awarding fees under this statute in the proper circumstances.

But the matters that Expert and Ellis-Don submitted to the arbitrator did not constitute a lien foreclosure under RCW 60.28.030. Thus, there was no basis under this statute to give rise to a fee award.

On a public works project, the governmental owner of [890]*890the project withholds five percent of every payment owed the general contractor.11

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Loop, V. Lisa Loop
Court of Appeals of Washington, 2025
Viceroy Group, Llc, Et Ano v. Tok, Llc, Et Ano
Court of Appeals of Washington, 2021
Mainline Rock & Ballast, Inc. v. Barnes, Inc.
439 P.3d 662 (Court of Appeals of Washington, 2019)
Josephene Choi v. Nathan Choi
Court of Appeals of Washington, 2018
Karen M. Jones v. Perry Jay Jones, Iii
Court of Appeals of Washington, 2014
Saleemi v. Doctor's Associates, Inc.
269 P.3d 350 (Court of Appeals of Washington, 2012)
Diamaco, Inc. v. Mettler
145 P.3d 399 (Court of Appeals of Washington, 2006)
Kenneth W. Brooks Trust A. v. Pacific Media, L.L.C.
44 P.3d 938 (Court of Appeals of Washington, 2002)
Bongirno v. Moss
969 P.2d 1118 (Court of Appeals of Washington, 1999)
Davidson v. Hensen
135 Wash. 2d 112 (Washington Supreme Court, 1998)
Expert Drywall, Inc. v. Ellis-Don Construction, Inc.
939 P.2d 1258 (Court of Appeals of Washington, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
939 P.2d 1258, 86 Wash. App. 884, 1997 Wash. App. LEXIS 1172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/expert-drywall-inc-v-ellis-don-construction-inc-washctapp-1997.