Pax Christi Memorial Gardens, Inc. v. United States

52 Fed. Cl. 318, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20640, 54 ERC (BNA) 1464, 2002 U.S. Claims LEXIS 87, 2002 WL 562679
CourtUnited States Court of Federal Claims
DecidedApril 10, 2002
DocketNo. 00-717L
StatusPublished
Cited by3 cases

This text of 52 Fed. Cl. 318 (Pax Christi Memorial Gardens, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pax Christi Memorial Gardens, Inc. v. United States, 52 Fed. Cl. 318, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20640, 54 ERC (BNA) 1464, 2002 U.S. Claims LEXIS 87, 2002 WL 562679 (uscfc 2002).

Opinion

[319]*319OPINION

FIRESTONE, Judge.

This case is brought by plaintiffs Pax Christi Memorial Gardens, Inc. (“Pax Christi”) and Lake County Trust Company, as Trustee under Trust No. 213 (“Trust Company”). Plaintiffs allege that the delay and effective denial of a permit to dredge and fill wetlands under Section 404 of the Clean Water Act, 33 U.S.C. § 1344, (“ § 404”) by the United States Army Corps of Engineers (“Corps”) has resulted in a regulatory taking of their property in Lake County, Indiana, under the Fifth Amendment of the United States Constitution. Plaintiffs seek just compensation of at least $10,000,000 for a temporary or permanent taking of approximately fifty acres of wetlands that plaintiffs own as part of their cemetery property.1 In addition, plaintiffs charge that the Corps’ actions regarding their permit application amounted to denial of due process.

The United States (“government”) contends that the plaintiffs’ takings claims must be dismissed on the grounds that plaintiffs’ permit application was withdrawn, and thus there has not been a final permit decision. According to the government, until plaintiffs obtain a final permit decision, their takings claims are not ripe for review. In the alternative, the government argues that, to the extent plaintiffs contend that their permit has been effectively denied on the grounds that the Corps denied a nearly identical permit previously in 1983, their takings claims are time-barred by the six-year statute of limitations under 28 U.S.C. § 2501. The government explains that because the plaintiffs’ pending permit application seeks virtually the same permit terms that the Corps denied in 1983, any permanent taking occurred in 1983, when that first permit was denied, therefore starting the statute of limitations clock. Finally, the government argues that this court does not have jurisdietion to consider plaintiffs’ due process claims and that those due process claims should, therefore, also be dismissed.

For the reasons that follow, the court finds that the plaintiffs’ temporary and permanent takings claims are not ripe for review and must be dismissed. The court also finds that plaintiffs’ due process claims must be dismissed for lack of jurisdiction.

FACTS

A. Background Facts

The following facts are undisputed unless otherwise noted. In 1950, plaintiff Trust Company bought cemetery property, known as Evergreen Memorial Park (“EMP”), in Hobart Township, Lake County, Indiana. Pax Christi Memorial Gardens, Inc. is the beneficial owner of Trust No. 213. The Trust, in turn, is wholly owned by Jack Levine and his family.

According to the plaintiffs, the subject EMP property is part of a larger cemetery that was established in 1923. “The cemetery was established and platted in 1923, with subsequent plats of the cemetery in 1925, 1963, 1965, 1973, [and] 1995____ Review of historic aerial photographs clearly indicate [sic] the fill of wetlands for the purpose of creating usable cemetery plots as early as 1938.”

After the plaintiffs acquired the property, the State of Indiana built highway 1-64 along the cemetery boundary, sometime in 1965. Apparently, 1-64 caused periodic flooding of the subject property, but the flooded portion was not yet being used for burials. As in the past, however, the property adjacent to 1-64 would need to be filled in for the purpose of creating usable cemetery plots.

In 1973, plaintiffs decided to expand the cemetery to include the EMP’s fifty acres, and the area was platted for cemetery use on [320]*320March 23, 1973. Beginning in 1977, the plaintiffs began expanding the cemetery into the EMP. Shortly thereafter, in June 1980, the Corps informed plaintiffs that before they could fill in the fifty-acre area, they would need a permit under § 404 of the Clean Water Act, 33 U.S.C. § 1344.2 Under § 404, the Corps is authorized to grant dredge and fill permits for the purpose of filling wetlands under specified circumstances.

Thereafter, in June, 1983, the owner of the Trust applied for a § 404 permit to fill approximately 43.5 acres with dredged material from the additional 6.5 acres that make up the EMP. On September 23, 1983, the Corps denied the § 404 permit on the grounds that the fill would destroy rare and valuable wetlands and would be contrary to public interest. Specifically, the letter stated that:

[A] cemetery does not require siting in or proximity to the aquatic environment in order to achieve its basic purpose. The proposed discharge is therefore not permissible under the Section 404(b)(1) guidelines of the 1977 Clean Water Act, since you have not clearly demonstrated that there are no other feasible upland sites in the area for the establishment or expansion of a cemetery.

At the time, neither of the plaintiffs challenged the Corps’ denial. Nor did the plaintiffs file an action seeking compensation under the takings clause of the Fifth Amendment. Instead, plaintiffs apparently stopped using the EMP.

Several years later, in June, 1990, the plaintiffs sent the Corps a letter asking for a “wetlands determination” for the EMP. In keeping with its § 404 authority, the Corps examined the EMP area to determine the existence and scope of wetlands subject to permitting. After a site inspection, the Corps notified the plaintiffs, in a letter dated October 12, 1990, that the site contained wetlands subject to the Corps’ jurisdiction, and that the plaintiffs would need a permit in order to fill the wetlands. The Corps enclosed a permit application.

For several years nothing happened. Then, in February 1993, the Trust owner, Mr. Levine, met with the Corps to discuss the § 404 permit process. Notes from that meeting indicate that Mr. Levine was informed that “the submittal of any proposal that does not significantly differ from his previous proposal in 1983 will almost surely result in another denial.” The Corps then met with the plaintiffs’ consultant, Eric Ell-ingson, of Earth Source, in September 1993, to again discuss the permitting process.

In connection with the application process, Mr. Ellingson sent a copy of his Wetlands Delineation Report to the Corps, which identified a total of forty-seven acres of wetlands on the site. On October 12, 1993, the Corps confirmed Mr. Ellingson’s wetlands determination. Plaintiffs, however, did not submit another § 404 permit application for another two years.

B. This Litigation

The case currently before this court deals with the plaintiffs’ second § 404 permit application. In particular, this court’s decision focuses on two letters that were sent by the Corps to the plaintiffs in response to their application; these letters were sent on July 9, 1997, and August 12, 1997. First, a brief description of the procedure to date is appropriate.

On October 31, 1995, Michael Muenich, plaintiffs’ attorney at the time, submitted a § 404 permit application seeking to fill approximately forty-one acres of wetlands and to dredge an additional six acres for fill material. Plaintiffs further proposed to use the dredged six-acre area for a detention pond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bassett, New Mexico LLC v. United States
55 Fed. Cl. 63 (Federal Claims, 2002)
Beekwilder v. United States
55 Fed. Cl. 54 (Federal Claims, 2002)
Hunt v. United States
52 Fed. Cl. 810 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
52 Fed. Cl. 318, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20640, 54 ERC (BNA) 1464, 2002 U.S. Claims LEXIS 87, 2002 WL 562679, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pax-christi-memorial-gardens-inc-v-united-states-uscfc-2002.