Paul v. United States

21 Cl. Ct. 415, 1990 U.S. Claims LEXIS 341, 1990 WL 126157
United States Court of Claims·Decided August 30, 1990·No. No. 362-87L·Published·Cited by 3 cases

Opinion

OPINION

BRUGGINK, Judge.

This is an action claiming a fifth amendment taking of certain personal property. The property at issue was located on a third party’s land when the land was condemned by the United States. After consideration of the evidence adduced at trial, and for the reasons stated below, the court concludes that the United States took items of plaintiff’s personal property and is obligated to pay the value of that property, plus interest, and to reimburse plaintiff for reasonable attorneys’ fees and costs.

BACKGROUND

In January of 1974, plaintiff, doing business as Viking Petroleum Properties (“Paul” or “Viking”), obtained, by lease, oil and gas rights in property owned by William Wells in Lawrence County, Kentucky. Under the terms of the lease, plaintiff obtained a seven-eighths working interest. He obtained these rights from Homer Robinson, who originally had leases on the Wells tract and on an adjoining property known as the Short tract. Paul testified that when he took the lease, he was aware that the United States would eventually condemn Wells’ land in connection with a plan to dam a tributary of the Ohio River. Paul in fact stated that his primary purpose in taking the lease was to rework the wells and get production under way, thereby enhancing the value of his seven-eighths working interest prior to condemnation. He testified that he had also hoped to make a profit from the production of oil and gas.

The assignment of the oil and gas lease to plaintiff contained a “catch-all” clause providing for the sale of all personal prop[417]*417erty on the land to plaintiff. Paul testified that there was an old, inoperable pump jack1 on the property. Scattered near a barn on the property were a 60 barrel separator, rods and tubing, a pumping tee, a mound of old, two inch line pipe, and a mound of eleven and a half inch thread line pipe which “was probably junk.”

There were a total of seven oil and gas wells2 on the property when Paul acquired the lease. These wells, which were roughly 1,500 feet deep, had been drilled in the early and mid sixties. The wells had casing in them. On most of the wells one could see nine and five-eighths and seven inch casing protruding. As to the condition of the casing on the wells, Paul stated that data obtained from the Kentucky Geological Survey did not indicate whether any of the casing had been “pulled” or “soaked”3 and that “all we knew was there was some casing there that could be utilized, if possible, for surface or intermediate strength.” In any event, there were no heads on the wells, and, in Paul’s judgment, the wells were not ready to be fitted for operation. Paul therefore began the process of reconditioning, or “reworking,” the wells.

Paul did not attempt to rework two of the wells, however. One, designated No. 44 and located near the house of Alf Matney, a tenant who lived on the Wells tract, had on it an apparatus which Paul referred to as a “Christmas tree,” apparently a gauge. This well was supplying gas to Matney’s house when Paul acquired the lease. Several witnesses, including Paul, testified that Matney did not want Paul’s men working on this well and that to avoid trouble they left it alone.

The other well which was not reworked was designated No. 7. It had been abandoned before Paul acquired the lease because tools had been dropped down the well during drilling and attempts to recover them had been unsuccessful. Paul stated that this well could not be made operational. Ultimately, therefore, only five wells were potentially available for oil and gas production.5

Paul described the equipment and procedures he employed in reworking the wells on the property.6 First, a four and a half inch string of pipe was installed down the well hole. This was new “J-55 eight round casing.” He inserted this pipe into the well on a “hook wall packer.”7 Paul used between 1,200 and 1,400 feet of such tubing in each well. He testified that he also installed what he called two and three eighths inch “upset” through which the oil and gas would ultimately travel. This “upset” tubing went down the entire length of the well. The largest casing, the nine and three eighths inch casing which was already in place in the wells, did not need to be replaced.

After the new tubing was in place, a down hole pump with “spring-loaded, double cage balls and seats” was installed in the pump. The next step was to setup a pump jack, the apparatus which creates a [418]*418differential in pressure to force oil and gas out of the well. Because there was no electricity on the Wells tract, Paul installed gasoline engines, which he testified were all new, to operate the jacks. He also installed 30 gallon tanks for gasoline. The only equipment leftover from Robinson which could be used were the largest casings in the well bore.

Paul also constructed an elaborate system of flow lines to carry oil and gas from the wells to separators (which separate the oil from the gas) and to storage tanks. Paul described the flow line as “ten inch round thread line pipe.” He testified that it was all new and that 14,000 feet were installed. Paul brought three storage tanks onto the property, one 210 barrel and two new 100 barrel tanks. According to Paul, one 65 barrel storage tank was already on the property.8 There were two separators. There was also a deduct meter on the property, which measured the flow of gas from an adjacent tract.

In addition to the equipment which Paul used in reworking the wells, there was stored on the property a significant amount of supply equipment and spare parts, such as “easing, tubing, down hole pump, assemblies], spare balls and seat[s], caging, all types of items you would need.” Equipment was stored on site because there was no oil supply store nearby. Generally, larger equipment was stored around the barn or inside it, and smaller equipment was stored in a “corncrib” nearby. Paul stated that the equipment which he stored on the property was there “until the day we left.”

Plaintiff had numerous problems in getting the wells to run properly. He never succeeded in having all of the reworked wells run simultaneously. Viking never showed a profit. Paul’s involvement with the Wells tract ended on October 29, 1976 when the Lawrence County (Kentucky) Circuit Court entered a judgment terminating his lease, based on Wells’ assertion that there had been a breach. Paul was allowed ninety days to enter the property to remove his oil and gas drilling equipment. He did not remove the equipment within this time period. However, sometime afterwards, in the spring of that year, he removed his “rolling stock” which consisted of “rigs, dozers, tractors, those kind of things.” At that time he also removed “a couple hundred feet” of seven inch casing to be used on a nearby property.

Paul testified that his men later attempted to remove some additional equipment, but that they had difficulty with Mr. Wells who threatened some of Paul’s men with a pistol. According to Edgar Yates, one of Paul’s employees at the time, Paul’s men succeeded in removing approximately “fifteen joints” of pipe.

On May 16, 1977, Wells sought and obtained a restraining order to prevent Paul from entering the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Paul v. United States, 21 Cl. Ct. 415, 1990 U.S. Claims LEXIS 341, 1990 WL 126157 (cc 1990).

21 Cl. Ct. 415 (Paul v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Town of Grantwood Village v. United States
55 Fed. Cl. 481 (Federal Claims, 2003)
Preseault V. United States
52 Fed. Cl. 667 (Federal Claims, 2002)
NRG Co. v. United States
31 Fed. Cl. 659 (Federal Claims, 1994)