Parker Tampa Two, Inc. v. Somerset Development Corp.
This text of 544 So. 2d 1018 (Parker Tampa Two, Inc. v. Somerset Development Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
PARKER TAMPA TWO, INC., Petitioner, Cross-Respondent,
v.
SOMERSET DEVELOPMENT CORPORATION, Respondent, Cross-Petitioner.
Supreme Court of Florida.
*1019 John H. Rains, III of Annis, Mitchell, Cockey, Edwards & Toehn, P.A., Tampa, for petitioner, cross-respondent.
Samuel R. Mandelbaum of Smith & Williams, P.A., Tampa, for respondent, cross-petitioner.
Glen Rafkin and Andrew S. Berman of Young, Stern & Tannenbaum, P.A., North Miami Beach, amicus curiae, for Donald Soffer, Aventura Country Club, Eberhart Linke, Robert James and Darlene Marten.
Arthur J. England, Jr. of Fine, Jacobson, Schwartz, Nash, Block & England, Miami, amicus curiae, for Centrust Sav. Bank.
SHAW, Justice.
We have for review Parker Tampa Two, Inc. v. Somerset Development Corp., 522 So.2d 502, 503 (Fla. 2d DCA 1988), to answer the following certified question:
ARE THE DAMAGES WHICH ARE RECOVERABLE FOR WRONGFULLY OBTAINING AN INJUNCTION LIMITED TO THE AMOUNT OF THE INJUNCTION BOND?
We have jurisdiction. Art. V, § 3(b)(4), Fla. Const. We answer the question in the affirmative and approve the district court decision.
Somerset Development Corporation (Somerset) filed a complaint against Hillsborough County seeking injunctive relief based upon the county's alleged breach of a sewer connection agreement whereby the county guaranteed that a certain number of sewer connections for Somerset's projects would be held available at the River Oaks Wastewater Treatment Plant. According to the complaint, the county denied Somerset's requests for sewer connections because it had granted service to so many third parties that the treatment plant was "experiencing intermittent capacity problems." After obtaining an answer from the county and conducting an evidentiary hearing, the trial court attempted to restrict additional third-party connections to River Oaks by issuing a temporary injunction which prohibited the county from issuing building permits to any applicant that held an unused sewer permit for the plant. Somerset, which was exempted from the prohibition, posted a $10,000 injunction bond.
Parker Tampa Two, Inc. (Parker), which was in the process of constructing a residential development, held unused sewer permits for River Oaks and was denied building permits under the injunction. Parker filed a motion to intervene in Somerset's suit against the county and a motion to increase the bond, both of which were denied following a hearing. The court subsequently granted Parker's second motion to intervene. At the hearing on the motion, Roger Stewart, director of the county commission that issues the sewer permits, testified that because the River Oaks treatment plant was then operating over capacity, no developer under any circumstances would be issued a sewer permit:
*1020 Q. If a developer went to the Hillsborough County Environmental Protection Commission and asked for a general permit to hook into that plant today, would you grant that permit?
A. It would not be technically grantable because the facility is not meeting the standards required of sewage treatment plants.
Q. Is that because there's no capacity there?
A. There is no capacity. It's in violation of several standards by which sewage treatment plants are evaluated.
Q. If a developer came to you with this factual situation and said that we have obtained a temporary, not a final injunction but a temporary injunction against developers who have permits that are not connected to the River Oaks Plant, would you, based on the capacity of the plant today, grant that developer a general permit?
... .
A. Would I grant one in the case today of River Oaks?
Q. Yes, sir.
A. No.
Parker filed a cross-claim against Somerset alleging wrongful injunction. Several weeks later, the court dissolved the injunction based on Stewart's earlier testimony. The court granted partial summary judgment in favor of Somerset on the cross-claim, limiting the amount Parker could recover to the $10,000 bond. After Somerset stipulated that Parker's damages exceeded $10,000, the court issued final judgment in favor of Parker in the amount of the bond. Parker appealed; Somerset cross-appealed. The DCA affirmed, certifying the above question. Parker sought review before this Court and Somerset cross-petitioned.
Parker contends that its damages should not be limited to the bond amount. It asserts that to do so is to deny it due process since it had no opportunity to contest the amount. It claims that the amount of such bonds is largely guesswork and that it would be unfair to limit recovery to such a speculative amount. This issue has been addressed by numerous courts throughout the country. See Annotation, Recovery of Damages Resulting From Wrongful Issuance of Injunction as Limited to Amount of Bond, 30 A.L.R. 4th 273 (1984). The minority view, which is followed in five states,[1] holds that liability is not limited to the amount of the bond since the amount is often set in an ex parte proceeding and is at best a court estimate based upon opinion or ex parte representations. The majority view, on the other hand, limits liability to the bond amount and is followed in the overwhelming majority of states and by the federal courts.[2] Under both the majority and minority views, the bond amount does not serve as a limit where the injunction is obtained maliciously or in bad faith.
In Florida, injunction bonds are addressed by Florida Rule of Civil Procedure 1.610 and section 60.07, Florida Statutes (1987). Rule 1.610 provides:
(b) Bond. No temporary injunction shall be entered unless a bond is given by the movant in an amount the court deems proper, conditioned for the payment of costs and damages sustained by the adverse party if the adverse party is wrongfully enjoined. When any injunction is issued on the pleading of a municipality or the state or any officer, agency, or political subdivision thereof, the court may require or dispense with a bond, with or without surety, and conditioned in the same manner, having due regard for the public interest. No bond shall be required for issuance of a temporary injunction *1021 issued solely to prevent physical injury or abuse of a natural person.
Section 60.07 provides:
60.07 Assessment of damages after dissolution. In injunction actions, on dissolution, the court may hear evidence and assess damages to which a defendant may be entitled under any injunction bond, eliminating the necessity for an action on the injunction bond if no party has requested a jury trial on damages.
Though the rule and statute are silent as to whether liability is limited to the bond amount, two state district courts have addressed the issue and both have followed the majority view. City Nat'l Bank v. Centrust Savings Bank, 530 So.2d 317 (Fla. 3d DCA 1988); Parker Tampa Two. We too adopt the majority view and limit liability to the bond amount where the injunction is obtained in good faith.
When a court initially sets an injunction bond, this constitutes the court's determination of foreseeable damages based on the good faith representations that are before it. Fla.R.Civ.P. 1.610(b). Should this amount prove insufficient or excessive, an affected party is free to move for modification.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
544 So. 2d 1018, 14 Fla. L. Weekly 266, 1989 Fla. LEXIS 502, 1989 WL 57951, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parker-tampa-two-inc-v-somerset-development-corp-fla-1989.