Tracy v. Capozzi

642 P.2d 591, 98 Nev. 120, 30 A.L.R. 4th 266, 1982 Nev. LEXIS 403
CourtNevada Supreme Court
DecidedMarch 29, 1982
Docket12825
StatusPublished
Cited by11 cases

This text of 642 P.2d 591 (Tracy v. Capozzi) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tracy v. Capozzi, 642 P.2d 591, 98 Nev. 120, 30 A.L.R. 4th 266, 1982 Nev. LEXIS 403 (Neb. 1982).

Opinion

*121 OPINION

By the Court,

Manoukian, J.:

This case is an appeal and cross-appeal from the trial court’s judgment dissolving a preliminary injunction and awarding damages to respondents and cross-appellants. Appellants and cross-respondents, theTracys (hereinafter “appellants”), contend that the trial court erred in its determination that appellants’ own violation of the relevant restrictive covenant precluded their obtaining equitable relief for a like breach by respondents and cross-appellants, the Capozzis (hereinafter “respondents”). Respondents, in their cross-appeal, assert that the trial court erred in limiting the award of damages to respondents to the amount of the security bond posted by appellants. Finding no error, we affirm the lower court’s decision in its entirety.

In October 1977, appellants filed a complaint seeking injunctive relief, alleging that respondents were about to build a home in the Frost Ranches Subdivision, in violation of the applicable Declaration of Covenants, Restrictions, Easements and Reservations. Appellants alleged, inter alia, that respondents had not obtained written approval of two of the three members of the subdivision’s Architectural Committee as required by the Declaration of Covenants, Paragraph 12(a).

The trial court, without notice, issued a temporary restraining order based on appellants’ verified complaint, restraining respondents from further excavation and construction and imposing a $1,000 security bond to be furnished by appellants. *122 Following a contested hearing in November 1977, a preliminary injunction was issued, and the court increased the security bond to $5,000. Respondents filed a Motion to Dissolve the Preliminary Injunction in December 1977, which was denied, after a hearing, in March 1978. At no time did respondents move for an additional increase in the security bond.

Following a trial on the merits, in June 1978, the trial judge entered an order dissolving the preliminary injunction. The court found that although only one Architectural Committee member signed the respondents’ building plans, the general practice,was to construct with only that one member’s written approval. In addition, the court found that another Committee member had orally approved the plan. The court noted that appellants had never received written approval for their house which had been moved, already constructed, to the subdivision, in violation of both Paragraph 12 and 15 1 of the Declaration of Covenants. The trial court concluded that such violations precluded the injunctive relief requested by appellants.

Respondents substantially completed construction in March of 1979 and in April filed a motion for damages of $128,632 resulting from increased construction and loan interest costs. The district court granted respondents’ motion only to the extent of the $5,000 security posted by appellants with the court, to apply to respondents’ court costs and attorney’s fees. This award was predicated on Paragraph 32 of the Declaration of Covenants, which provides that the prevailing party in an action to enforce the restrictions shall be entitled to recover attorney’s fees. Although the court recognized that respondents’ damages exceeded the bond, it refused an additional award because it determined that the preliminary injunction was obtained in good faith.

1. Breach of Covenants. 2

Paragraph 12(a) of the Declaration of Covenants, in relevant part, provides:

No .. . structure shall be commenced, erected, placed or altered on any lot . . . until . . . the building plans and specifications . . . have been submitted to and approved in *123 writing ... by an Architectural Committee composed of KARL S. BAKER, O. FRANK STOCK, and A REPRESENTATIVE OF MURRAY-McCORMICK ENVIRONMENTAL GROUP OF NEVADA, or any two of them or a committee of at least two persons appointed by them. . . .

It is uncontroverted that only one member of the Committee (Frank Stock) actually signed respondents’ plans. Appellants contend that the single signature was a clear violation of the covenant and an appropriate basis for granting injunctive relief. They claim that their own failure to procure signatures of two committee members before construction on their lot did not constitute a waiver of their right to enjoin respondents’ construction. 3 Several factors militate against appellants’ contentions. The decision below was not based on a theory of waiver, but on the well-established defense to equitable claims that litigants seeking equity must come with “clean hands.” Courts will usually deny injunctive relief if the complainant has violated the same restrictive covenant he seeks to enforce against a defendant. See Houston Petroleum Co. v. Automotive Products Credit, 87 A.2d 319 (N.J. 1952); Vandershoot v. Kocher, 72 N.Y.S.2d 121 (Supr.Ct. 1947); Reading v. Keller, 406 P.2d 634 (Wash. 1965); 5 R. Powell, The Law of Real Property, § 679 (1981); cf. Gladstone v. Gregory, 95 Nev. 474, 596 P.2d 491 (1979) (right to enforce one restrictive covenant not lost by acquiescence in the violation of another).

An exception to this rule is recognized if the complainant’s violation is insignificant, but defendant’s infraction is substantial. See Reading v. Keller, supra at 636, and Powell, supra. In the instant case, the violations of plaintiff's and defendants, relating to the procedure of obtaining building plan approval, were identical. We find no justification for applying the exception to the “unclean hands” doctrine under the circumstances of this case. Appellants cannot seek to enjoin respondents, based on a violation of the self-same covenant they previously violated. The trial court properly dissolved the preliminary injunction. 4

*124 2. Limitation of Damages.

The district court refused to award damages (other than attorney’s fees) to respondents because it found the preliminary injunction was obtained in good faith, and thus was not “wrongful” under NRCP 65(c). 5 Attorney’s fees to the extent of the bond were awarded, as required under the Declaration of Covenants. Appellants’ “good faith” in pursuing injunctive relief is not disputed by respondents, nor do appellants contest on appeal the propriety of the award below, assuming the dissolution of the injunction was proper.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chen v. Dist. Ct. (Chang)
Nevada Supreme Court, 2017
Koch v. Aupperle
763 N.W.2d 415 (Nebraska Supreme Court, 2009)
Fisher v. Parkview Properties, Inc.
859 P.2d 77 (Court of Appeals of Washington, 1993)
Howard H. Hazen v. Prudential Securities, Inc.
12 F.3d 1106 (Ninth Circuit, 1993)
Parker Tampa Two, Inc. v. Somerset Development Corp.
544 So. 2d 1018 (Supreme Court of Florida, 1989)
In Re Prichard Estate
425 N.W.2d 744 (Michigan Court of Appeals, 1988)
McAtee v. Faulkner Land & Livestock, Inc.
744 P.2d 121 (Idaho Court of Appeals, 1987)
Jensen v. Torr
721 P.2d 992 (Court of Appeals of Washington, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
642 P.2d 591, 98 Nev. 120, 30 A.L.R. 4th 266, 1982 Nev. LEXIS 403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tracy-v-capozzi-nev-1982.