Palmolive Tower Condominiums v. Simon

CourtAppellate Court of Illinois
DecidedMay 16, 2011
Docket1-10-0427, 1-10-1348 cons. Rel
StatusPublished

This text of Palmolive Tower Condominiums v. Simon (Palmolive Tower Condominiums v. Simon) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmolive Tower Condominiums v. Simon, (Ill. Ct. App. 2011).

Opinion

FIRST DIVISION FILED: MAY 16, 2011

NOS. 1-10-0427 and 1-10-1348, cons.

_________________________________________________________________

IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT _________________________________________________________________

PALMOLIVE TOWER CONDOMINIUMS, LLC, a ) APPEAL FROM THE Delaware limited liability company, ) CIRCUIT COURT OF ) COOK COUNTY Plaintiff-Appellee ) ) v. ) No. 09 CH 01399 ) MARY SIMON, as Trustee of the Marcy ) Simon Revocable Trust dated September ) 19, 1991, and MARC SIMON ) HONORABLE ) STUART E. PALMER Defendants-Appellants. ) JUDGE PRESIDING. _________________________________________________________________

JUSTICE HOFFMAN delivered the judgment of the court, with opinion. Presiding Justice Hall and Justice Lampkin concurred in the judgment and opinion.

OPINION

The defendants, Mary and Marc Simon, appeal from the circuit

court judgments dismissing their counterclaims against the

plaintiff, Palmolive Tower Condominiums, LLC, and granting the plaintiff judgment on the pleadings on count I of its complaint.

For the reasons that follow, we affirm the trial court’s judgment

dismissing the defendants’ counterclaims, and we dismiss the

defendants’ appeal of the trial court’s judgment on count I of the

plaintiff’s complaint.

In its complaint, the plaintiff alleged that it and the

defendants entered into a condominium purchase agreement in July

2003, before the plaintiff had finished construction on the site. NOS. 1-10-0427 and 1-10-1348, cons. That agreement provided as follows:

"4(c)(i) If Seller fails to substantially complete the

Unit on or before December 31, 2005 ***, Purchaser, as its

sole remedy for such failure, shall have the right to

terminate this Agreement ***. In the event Purchaser

exercises its Right to Terminate hereunder, Purchaser shall be

only entitled to a refund of the Earnest Money and all

interest earned thereon and this Agreement shall terminate. ***

(ii) Notwithstanding the foregoing, if the Closing does

not occur by August 31, 2005, Seller shall, as compensation

for the delay, at Purchaser’s option, (A) pay to Purchaser

[$7,500] per month ***, or (B) provide to Purchaser [an

apartment and parking]. If Purchaser is entitled to receive

(A) or (B) under this paragraph ***, such shall be provided by

Seller from July 1, 2005[,] through and including the earlier

of *** the Closing Date *** or *** the effective date of the

Purchaser’s termination of [the Agreement]."

According to the plaintiff’s complaint, on January 17, 2006,

it and the defendants entered into a closing agreement, which

provided as follows, in relevant part:

"Whereas, Seller has not yet completed construction of

the *** Building ***; and

Whereas, *** purchaser is not obligated to close the

purchase of the Premises until such [construction] has been

2 NOS. 1-10-0427 and 1-10-1348, cons. completed; and

Whereas, the parties have agreed to close the purchase

and sale of the Premises in accordance with and in material

reliance upon the provisions of this Closing Agreement.

Now, therefore, the parties agree as follows:

* * *

2. At closing, [part of] the sales proceeds shall [be

deposited into escrow]. Seller represents and warrants to Purchaser that Seller has completed construction *** except

for construction to be performed on [two floors of the

building on which the plaintiffs’ condominium is not located]

***. The escrowed funds shall be held in escrow until [the

construction is completed, in which case the seller will

receive the funds, or until three years pass, in which case

the purchaser will receive the funds]. ***

3. Seller represents and warrants to Purchaser that

Seller has heretofore closed the sale of three *** condominium

units in the Building, has signed contracts with no less than

10% earnest money deposited for the sale of [83] condominium

units and there are no more than [15] condominium units

remaining unsold.

4. Seller represents and warrants to Purchaser that it is

Seller’s good faith belief that construction of no less than

25% of the condominium units in the Building will be completed

by March 1, 2006, 50% by June 1, 2006, 75% by September 1,

3 NOS. 1-10-0427 and 1-10-1348, cons. 2006[,] and 100% by December 1, 2006.

5. At closing, Purchaser will receive a credit of

[$25,000] ***."

The plaintiff alleged, and the defendants in their answer

admitted, that the defendants took possession of their condominium

on the date of the closing agreement and began residing there just

over one week later. However, according to the complaint, even

after the plaintiff obtained the required construction approval for the project, the defendants declined to release the escrow money to

the plaintiff. The plaintiff’s complaint contained three counts,

seeking a declaration of the plaintiff’s entitlement to the

escrowed funds, damages for breach of the parties’ agreements, and

specific performance of the parties’ agreements.

The defendants thereafter filed counterclaims against

plaintiff for breach of contract, negligence, and fraud. The

counter-complaint contained the following allegations:

"12. When informed by [the plaintiff] that the Unit was

habitable, the [defendants] agreed to close on January 17,

2006.

16. By closing on January 17, 2006, the [defendants] gave

up their rights to receive a payment of $7,500 per month ***.

20. On information and belief, the representation and

warranty [the plaintiff set out in the closing agreement,

4 NOS. 1-10-0427 and 1-10-1348, cons. regarding the construction and sales of other units] was

untrue and therefore breached."

The counter-claim then detailed the defendants’ reasons for

believing that sales and construction progress were not as the

plaintiff had warranted and setting forth the plaintiff’s

involvement with the sales and construction processes. According

to the counter-claim, construction on the project was not finally

finished until October 2008. In their count for breach of contract, the defendants alleged

that the plaintiff’s failure to honor the warranties made in the

closing agreement "[s]ubjected the [defendants] to the risk that

the project would fail," "[c]aused the [defendants] to be

inconvenienced by [the plaintiff’s] construction work including

lack of access to all elevators, dirt, dust and debris in their

Unit, on their deck and their cars, the cost of which was not less

than $10,000.00," caused the defendants to "give up what was

essentially a free option on [the property]" due to their right to

terminate the agreement, caused the defendants to "[give] up the

opportunity to earn interest on [the cost of the condominium] ***

and [begin] paying taxes and assessments," caused the defendants to

begin using a property tax freeze earlier than if they had waited

to close, and caused them to forgo their right to a monthly $7,500

credit.

In their fraud count, the defendants alleged that the

plaintiff knew the representations in the closing agreement to be

5 NOS. 1-10-0427 and 1-10-1348, cons. false but made them anyway in an attempt to induce the defendants’

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Com-Co Insurance Agency, Inc. v. Service Insurance Agency, Inc.
748 N.E.2d 298 (Appellate Court of Illinois, 2001)
Coryell v. Village of La Grange
614 N.E.2d 148 (Appellate Court of Illinois, 1993)
Mund v. Brown
913 N.E.2d 1225 (Appellate Court of Illinois, 2009)
Lurz v. Panek
519 N.E.2d 1110 (Appellate Court of Illinois, 1988)
BURNHAM MANAGEMENT CO. v. Davis
704 N.E.2d 974 (Appellate Court of Illinois, 1998)
Anderson v. Long Grove Country Club Estates, Inc.
249 N.E.2d 343 (Appellate Court of Illinois, 1969)
Hudlin v. City of East St. Louis
591 N.E.2d 541 (Appellate Court of Illinois, 1992)
Matson v. Department of Human Rights
750 N.E.2d 1273 (Appellate Court of Illinois, 2001)
Hamer v. Lentz
508 N.E.2d 324 (Appellate Court of Illinois, 1987)
Brown v. Broadway Perryville Lumber Co.
508 N.E.2d 1170 (Appellate Court of Illinois, 1987)
Davis v. City of Kokomo
919 N.E.2d 1213 (Indiana Court of Appeals, 2010)
Doe v. Northwestern University
682 N.E.2d 145 (Appellate Court of Illinois, 1997)
Application of Du Page County Collector
605 N.E.2d 567 (Illinois Supreme Court, 1992)
YPI 180 N. LaSalle Owner, LLC v. 180 N. LaSalle II, LLC
933 N.E.2d 860 (Appellate Court of Illinois, 2010)
Irizarry v. Illinois Central Railroad Company
879 N.E.2d 1007 (Appellate Court of Illinois, 2007)
Hopkins v. Illinois Masonic Medical Center
570 N.E.2d 575 (Appellate Court of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Palmolive Tower Condominiums v. Simon, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmolive-tower-condominiums-v-simon-illappct-2011.