Palmer v. Crews Lumber Co., Inc.

1973 OK 38, 510 P.2d 269, 82 A.L.R. 3d 1030, 1973 Okla. LEXIS 301
CourtSupreme Court of Oklahoma
DecidedApril 3, 1973
Docket45080
StatusPublished
Cited by18 cases

This text of 1973 OK 38 (Palmer v. Crews Lumber Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmer v. Crews Lumber Co., Inc., 1973 OK 38, 510 P.2d 269, 82 A.L.R. 3d 1030, 1973 Okla. LEXIS 301 (Okla. 1973).

Opinion

HODGES, Justice.

This is an appeal from a judgment in favor of Crews Lumber Company, a corporation (Crews) in an action to foreclose a mortgage and to determine priorities as between mortgagee and Kenneth K. Palmer (Palmer) concerning his alleged vendee’s and materialmen’s liens on the property in question.

On May 29, 1969, Palmer entered into a contract with Traditional Homes, Inc., for the construction of a house for Palmer. The written receipt and contract of sale between Palmer and Traditional provided for the construction of a house according to an approved set of plans for the price of $35,000.00. It also provided for a down payment of $3,500.00 which was paid by Palmer to Traditional. The contract contained the following pertinent clause:

“In the event this contract is breached by seller or terminated by buyer as provided above, seller will return the $3,500.00 part payment, for which purchaser is granted a lien on the subject property, to purchaser.”

Some time after the execution of this contract, Maddox, who had executed the contract for Traditional, informed Ira D. Crews, Jr., Manager of Crews Lumber Co., that Traditional had a contract for the purchase of a house to be built on the property in question. He requested Crews to purchase the lot and to assist in financing construction. Crews and Traditional had worked together under a similar arrangement on at least eight other houses. Crews never furnished construction money without a loan commitment. A note and mortgage to Crews Lumber Co., in the amount of $26,250.00, was executed by Traditional July 7, 1969.

Ira D. Crews, Jr. et ux., and W. R. Grimshaw, et ux. deeded the lot to Traditional July 15, 1969. The deed was recorded December 4, 1969, Palmer was approved by the mortgage company on July 18, 1969. The mortgage from traditional to Crews was recorded July 31, 1969, and assigned to Republic National Bank on the same date. The mortgage was subsequently reassigned to Crews.

Traditional defaulted in the contract by abandoning construction of the house prior to its completion. When Traditional ceased construction, Crews entered into an arrangement with a former employee of Traditional to continue construction of the house to the point that it would at least be protected from the weather. It was during this phase of construction that Palmer furnished additional funds.

This action arose when Crews sought to foreclose its mortgage on the property. Palmer filed counter claim contending that his vendee’s lien was prior and superior to the mortgage of Crews. He also alleged *271 that he had a superior lien to all parties because he had been induced to advance $1,204.20 in payment of construction bills for paint and texturing of the walls in the house after Traditional had abandoned the job, and while Crews was in charge of construction.

The Court of Appeals found that when Crews took over possession and construction of the house, it knew, because it was paying the bills, that the construction costs were running over the amount of money available in the permanent loan commitment. The Court also found that Crews knew that it did not intend to finish the house, and that it knowingly permitted Palmer to spend more money on this lost cause without saying anything about the facts as it knew them to be, and which were unknown to Palmer. The court held that the acts of conduct of Crews created an estoppel and it was therefore prevented and estopped from asserting the priority of its mortgage over Palmer’s materialmen’s lien.

Apex Siding & Roofing Co. v. First Federal Saving & Loan Assn., 301 P.2d 352, 353 (Okl.1956) was cited as authority for this holding. It states:

“It is the general rule that a recorded mortgage takes precedence over subsequent liens against the mortgaged property; but such a mortgage will be held subordinate to liens for improvements which are made after acts or conduct by the mortgagee that create an estoppel which prevents him from asserting his priority over the subsequent lien.”

Crews asserts that estoppel was not plead, and that it is an affirmative defense which must be plead and satisfactorily proven. We concur with Crews on this point. See Sellers v. Sellers, 428 P.2d 230 (Okl.1967). However, we find that the facts constituting estoppel, although not formally plead, were sufficiently plead and satisfactorily proven. The holding of this court in Palovik v. Absher, 198 Okl. 671, 181 P.2d 989, 990 (1947) is applicable to the present situation. The court held that:

“A party entitled to an estoppel or waiver need not in all cases formally plead them. If the facts constituting the es-toppel or waiver are in any way sufficiently pleaded, he is entitled to the benefit of the law arising therefrom.”

The portion of the Court of Appeals opinion which holds that Palmer’s materialmen’s lien in the amount of $1,-204.20 is a first and superior lien to Crews’ mortgage is affirmed.

The paramount issues to be determined by this court are whether Palmer’s vend-ee’s lien was prior to the mortgage, and if so, did Crews as mortgagee have actual or constructive notice of the lien.

There is no legal distinction under our statutes where the vendor contracts to sell land to which he already has title, and the case here where the vendor did not have title to the land at the time of the contract, but either misrepresented that he had title or represented that he could and would obtain it, and subsequently does obtain title.

The applicable statutes are:

42 O.S.1971 § 8 — Lien on future interest.
“An agreement may be made to create a lien upon property not yet acquired by the party agreeing to give the lien, or not yet in existence. In such case the lien agreed for attaches from the time when the party agreeing to give it acquires an interest in the thing to the extent of such interest.”

42 O.S.1971 § 30 — Lien of purchaser of real property.

“One who pays to the owner any part of the price of real property, under an agreement for the sale thereof, has a special lien upon the property, independent of possession, for such part of the amount paid as he may be entitled to recover back in case of a failure of consideration.”

Ira Crews, Jr., manager of Crews, and one of the grantors in the deed to Traditional, testified that Crews had dealt with Traditional in the loaning of construction money on at least eight different occasions. *272 He stated that Crews would not loan money to Traditional to build speculative homes, but that there must first be a loan commitment. Pertinent testimony of Ira Crews, Jr. follows:

“A. We took a mortgage with builders on the amount of the commitment that they got from the loan company or close to it, if I thought there was a variance there why we — -but we tried to stay right on the amount.
“Q. All right. Now, you wouldn’t consider furnishing any material to Mr. Maddox until you knew that somebody had bought that lot and gotten a lien commitment, that is correct, isn't it?
“A. That’s right.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Osage Energy Resources, LLC v. Pemco, LLC
2016 OK CIV APP 70 (Court of Civil Appeals of Oklahoma, 2016)
AMERICAN BANK OF OKLAHOMA v. Wagoner
2011 OK CIV APP 76 (Court of Civil Appeals of Oklahoma, 2010)
Gonzalez v. Citizens Security Bank & Trust Co.
2008 OK CIV APP 3 (Court of Civil Appeals of Oklahoma, 2007)
Cox v. RKA CORP.
753 A.2d 1112 (Supreme Court of New Jersey, 2000)
In Re First Penn Corporation
793 F.2d 270 (First Circuit, 1986)
Spears v. Federal Deposit Insurance
793 F.2d 270 (Tenth Circuit, 1986)
Ladd v. State Ex Rel. Oklahoma Tax Commission
1984 OK 60 (Supreme Court of Oklahoma, 1984)
Stahl v. Roulhac
438 A.2d 1366 (Court of Special Appeals of Maryland, 1982)
Tommerup v. Albertson's, Inc.
607 P.2d 1055 (Idaho Supreme Court, 1980)
Watson Construction Co. v. Amfac Mortgage Corp.
606 P.2d 421 (Court of Appeals of Arizona, 1979)
Poteau State Bank v. Denwalt
597 P.2d 756 (Supreme Court of Oklahoma, 1979)
Knudson v. Weeks
394 F. Supp. 963 (W.D. Oklahoma, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
1973 OK 38, 510 P.2d 269, 82 A.L.R. 3d 1030, 1973 Okla. LEXIS 301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmer-v-crews-lumber-co-inc-okla-1973.