Liberty National Bank & Trust Company of Oklahoma City v. Kaibab Industries, Inc.

1978 OK 162, 591 P.2d 692, 1978 Okla. LEXIS 567
CourtSupreme Court of Oklahoma
DecidedDecember 19, 1978
Docket49017
StatusPublished
Cited by8 cases

This text of 1978 OK 162 (Liberty National Bank & Trust Company of Oklahoma City v. Kaibab Industries, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liberty National Bank & Trust Company of Oklahoma City v. Kaibab Industries, Inc., 1978 OK 162, 591 P.2d 692, 1978 Okla. LEXIS 567 (Okla. 1978).

Opinion

LAVENDER, Vice Chief Justice:

The Liberty National Bank & Trust Company of Oklahoma City (lender) was the interim construction lender on an apartment complex at Sapulpa, Oklahoma. Principal documentation consisted of promissory note, real estate mortgage covering the project, and a loan agreement. Lender sought to foreclose its mortgage lien. Trial court entered judgment determining lender’s mortgage lien to be superior to materi-almen’s liens. Those materialmen’s lien claimants appeal (lien claimants). 1

Lien claimants argue the mortgage lien priority fails as to them for (1) construction commenced before the filing of the mortgage lien, (2) construction loan advances were optional rather than obligatory, (3) lender estopped to assert the priority of its lien, and (4) lender subject to a construction fund trust, either by statute or equity. Reversible error also contended in the trial court’s exclusion from the evidence a moving permit on a dozer and an invoice as to labor performed showing dates said to establish the commencement of construction.

Parties agree if construction commenced prior to filing of the mortgage lien, then the mortgagee lender is charged with full notice of lien claims of contractors, and *694 subcontractors, that could include material-men. American-First Title & Trust Company v. Ewing, Okl, 403 P.2d 488 (1965). See also Thompson v. Smith, Okl, 420 P.2d 526 (1966). Oral findings of the trial court determined construction did not commence prior to recording the lender’s mortgage lien. Lien claimants believe that finding is against the weight of the evidence. Individuals performing the dirt work on the site preparation, or observing that work, testified usually with some uncertainty as to the exact date, but would place the commencement at a time prior to the recording date of January 29,1974. The building inspector for the City of Sapulpa observed construction activities on the site prior to the issuing of the building permit dated February 5, 1974. He could not name a date of the construction activity but suggested probably ten days prior to the issuing of the building permit. Trial court weighed this and other evidence. Greater weight was given to the testimony of the licensed engineer making a site inspection for the lender and certifying under date of January 30, 1974, construction had not commenced. He indicated his inspection that date found the site in the same condition as previously in December 1973, when he examined in conjunction with a topographical survey. His pre-construction inspection on January 30, 1974, consisted of walking over the property, making a visual examination over a period of some fifteen or twenty minutes, and finding no evidence of previous construction. He saw no bulldozer on location and found the site overgrown with grass and weeds.

“In cases of equitable cognizance, there is a presumption in favor of the findings and judgment of the trial court, and same will not be set aside unless clearly against the weight of the evidence.” Thompson, supra. We have reviewed the record including the testimonial conflict on the fact issue as to when work commenced. The presumption favors the trial court’s findings. That finding is not clearly against the weight of the evidence.

For the mortgage lien to be superior to the lien claimants, the advance’s under the mortgage lien must be obligatory on the lender rather than permissive. Tulsa Ready-Mix Concrete Co. v. Dale Carter Lbr. Co., Okl., 381 P.2d 849 (1963). Case law of this jurisdiction relating to this problem is discussed in Thompson, supra, p. 528 including holdings in Antrim, Davidson, and Sullivan opinions. 2 In Thompson, we said:

“In a more recent decision, Tulsa Ready-Mix Concrete Co. v. Dale Carter Lumber Co., Okl., 381 P.2d 849, the principle of priority based upon the obligatory or optional nature of the advances of a mortgage loan, as above set out, was reaffirmed. We held in that case that where the mortgagee was ‘obligated to distribute proceeds of the loan upon stated conditions being complied with ’ the prior recorded mortgage was to be given priority over subsequent liens of materi-almen.” (Emphasis added.)

Thus Oklahoma permits conditions upon advances, compliance with which may make the advances obligatory upon the mortgagee. A word of warning. Although it is not true here, lenders’ conditions upon advances under some circumstances may be so burdensome as to in effect allow the lender to have an option in the matter.

In present case, conditions controlling the making of advances are principally found in the loan agreement. 3 Lien claimants argue *695 the similarity of conditions with those considered in National Bank of Washington v. Equity Investors, 81 Wash.2d 886, 506 P.2d 20 (1978) that were held to be such a reservation of discretionary authority as to make the advances in law optional. We do not agree, for in National Bank of Washington the opinion notes, using its own emphasis, the following:

“The construction loan agreement left the loan moneys largely under the control and dominion of the bank, ‘to be advanced at such times and in such amounts as the Lender shall determine.’ It provided, too, that ‘No advance shall be due unless, in the judgment of the Lender ’ all work for which the advance had been made had been done in a good and workmanlike manner, and unless the construction be approved by the architect.”

Here, form of advance request, proof of invoice payment, and bank’s own inspection were to be “satisfactory to the Bank.” There is no option to pay the proceeds of the loan as the lender sees fit as pointed to in Thompson, supra, p. 528, in reference to Antrim, 4 and other authority. 5 As said in National Bank of Washington, supra, “(i)f the bank, however, under the construction loan agreement could have been compelled in the courts to advance the moneys on the loan, then its lien is totally superior and prior * * Satisfaction *696 of the bank under the present loan agreement could not be made so unreasonable as to be strictly discretionary with the bank and defeat the compelling of the advancements in the courts. There is no reservation of discretionary authority for the advancements to be made at such times and in such amounts as the lender shall determine. The advances on the present loan were obligatory, and not optional, in nature. This allows the lender’s mortgage lien to be superior to the lien claimants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Mustang State Bank v. Garland Bloodworth, Inc.
825 P.2d 254 (Supreme Court of Oklahoma, 1992)
Wooden v. First Security Bank of Idaho
822 P.2d 995 (Idaho Supreme Court, 1991)
Karen Myers, Ltd. v. the Law Co.
1990 OK CIV APP 17 (Court of Civil Appeals of Oklahoma, 1990)
First National Bank & Trust Co. of Ardmore v. Worthley
1985 OK CIV APP 36 (Court of Civil Appeals of Oklahoma, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
1978 OK 162, 591 P.2d 692, 1978 Okla. LEXIS 567, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liberty-national-bank-trust-company-of-oklahoma-city-v-kaibab-okla-1978.