Page v. Harlingen Independent School Dist.

23 S.W.2d 829
CourtCourt of Appeals of Texas
DecidedDecember 4, 1929
DocketNo. 8280.
StatusPublished
Cited by2 cases

This text of 23 S.W.2d 829 (Page v. Harlingen Independent School Dist.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Page v. Harlingen Independent School Dist., 23 S.W.2d 829 (Tex. Ct. App. 1929).

Opinion

COBBS, J.

Appellants sued appellee for damages growing out of the breach of a‘ contract, under the terms of which appellants allege they were employed by appellee, as architects, to prepare plans and specifications for, and to superintend the proper construction of, three buildings, one known as the high school building, one as the north side school building, and the other as the south side school building.

Harlingen independent school district, contemplating a school building program, ordered an election' to be held in the district for the purpose of determining whether or not bonds of said district could be issued for the purpose of raising funds with which to construct the three school buildings aforesaid. The election resulted in favor of the issuance of the school bonds in a sufficient amount to erect said buildings. Said election authorized the district to issue 1400,000 worth of bonds, and soon thereafter they were issued and sold toy the district. Prior to the election, the appellee entered into an agreement with appellants employing them as architects to prepare the plans and specifications, and superintend the proper construction, of said buildings at an agreed price of 5 per cent, of the cost of said buildings, in the event the election carried and the money was available for that building program. After the bonds were issued and sold, appellants were instructed to prepare the plans and specifications for the north and south side school buildings, which they did, and then began the preparation of the plans and specifications for the high school building.

As the north and south side school buildings were constructed in accordance with ap *830 pellants’ plans and specifications, and the fees therefore were paid by appellee, with the exception of four hundred and some odd dollars, we will not refer further to these two buildings. At the time the contract was entered into between appellants and appellee, it was stated that the board might not undertake the building of the high school building for another year.

Appellants alleged that, just before the completion of the plans and specifications for the high school building, for the construction of which $225,000 ,of said bonds had been reserved, and just Ibefore these bondsi were sold, the district wrongfully and unlawfully repudiated its contract with appellants, and would not allow them to proceed further with the work, though appellants insisted upon their right to complete the same under their contract. And appellants alleged that they had spent approximately $2,500 in the preparation of said plans and specifications for the high school building. Appellants then pleaded what it would cost them to complete the plans and specifications for said building, and sued for the difference between what had been paid them on their contract and what it woul'd cost them to carry to completion their contract, and asked for a judgment for this difference in the sum of $8,231.64. Appellants pleaded estoppel, and in the alternative pleaded that the reasonable value of their services for which they had not been paid was the sum of $8,231.64.

Appellee admitted the making of the contract, but denied that it included the high school building, and tendered $426.24, as being the balance due under the contract. And appellee defended against the legality of the contract upon the ground that it was void because the district had no money available on October 10, 1027, with which it could pay said appellants for their services under the terms of their contract, and that by reason thereof the contract was unenforceable.

The case was tried by the court without a jury, and the court rendered judgment for the sum of $426.24, in favor of appellants, and in addition thereto $2,000, being the amount appellants spent in the preparation of the plans and specifications for the high school building.

Obviously, there was but one contract entered into between the district and appellants, fQr drawing the plans and specifications for,, and superintending the construction of, said three school buildings, and, if it was valid as to the north side building and the south side building, why was it not valid as to the third, the high school building?

The questions for us to decide, as presented by both parties, are whether appellants’ alleged contract became a binding obligation, and whether appellants are entitled to recover as their damages the difference between the contract price, less what appellee district has paid them, and less the sum It would cost appellants to carry out the contract. However, if the contract be held to be invalid, then the judgment of the trial court for $2,426.24 is a correct recovery upon the quantum meruit.

Contracts for the construction of school buildings from bond sales by an independent school district can only be made after the bonds have been sold and the money placed in the treasury. We here copy the statement made by appellants:

“Appellants alleged the passage of an order on October 10, 1927, by said Appellee District’s Board of Trustees, in which they designated Appellants as their architects, and that the same was passed in pursuance of a proposition made by Appellants to Appellee District that in the event said bond election carried and the bonds were issued and sold and the money became available, that on the happening of this contingency, the agreement was to become a binding contract between the parties, under the terms of which Appellants were to perform the services of preparing plans and specifications, and superintend the construction of the High School Building and the two ward school buildings known as the North and the South Side School Buildings; that after said money became available from the sale of said bonds, the plans and specifications for the two ward school buildings were prepared by Appellants, and said buildings were constructed under the supervision of Appellants ; that while this work was going on, what is known as the Mexican School Building, and also, what is known as the Combes School Building were brought into the project under the same terms, and that specifications and plans were prepared for these buildings, and they were constructed under the supervision of Appellants, and from time to time as the plans and specifications were being prepared and submitted for the buildings that were actually constructed, the plans and specifications and sketches of the High School Building were being prepared, and different sketches and floor plans were submitted by Appellants to the Defendant District, changes were made in the different plans at Appellee District’s suggestion, as to said floor plans and sketches of said High School Building, and in this and many other ways specifically alleged, the conditional contract has been ratified and confirmed by the Appellee District, acting by its Board of Trustees, and that Appellants had been at a reasonable expense of $2,500.00 in the preparation of the plans and sketches for -the High School Building before they were unlawfully discharged. According to said plans and specifications of said High School Building, said building cost approximately $225,000.00. Appellants then alleged the cost of completing their plans and specifications for said High School Building to be the sum of $2,225.00, and that the cost *831

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Land, Timber & Pulp Corp. v. Davis & Floyd Engineers, Inc.
135 S.E.2d 454 (Court of Appeals of Georgia, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
23 S.W.2d 829, Counsel Stack Legal Research, https://law.counselstack.com/opinion/page-v-harlingen-independent-school-dist-texapp-1929.