Phelps v. Connellee

285 S.W. 1047
CourtTexas Commission of Appeals
DecidedJune 16, 1926
DocketNo. 676-4572
StatusPublished
Cited by15 cases

This text of 285 S.W. 1047 (Phelps v. Connellee) is published on Counsel Stack Legal Research, covering Texas Commission of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phelps v. Connellee, 285 S.W. 1047 (Tex. Super. Ct. 1926).

Opinion

POWELL, P. J.

Phelps was an architect for Connellee. He drew plans for two buildings, a hotel and a theater. A dispute arose as to the amount due Phelps, and this suit followed. In a trial before the district court, Phelps recovered judgment for $534. Upon appeal by Connellee. the Court of Civil Appeals entered the following judgment:

“From what has been said, it follows that the total compensation due appellant under the contract was $12,290, instead of $11,034, as found by the trial court, and that the amount which should have been recovered by appellant was the sum of $1,790, instead of $534. It therefore follows that the judgment of the trial court should be reformed so that, instead of allowing appellant a recovery of $534 as was done, appellant should recover of and from appellee the. sum of $1,790, together with all costs both in the trial court and in this court, and that the judgment of the trial court should be so reformed, and, as so reformed, it is affirmed.”

See 278 S. W. 939.

It will be observed that the Court of Civil Appeals increased the judgment in favor of Phelps by the sum of $1,256, which is 2 per cent, of the sum of $62,800, expended on the construction- of the theater building after Phelps was discharged without fault on his part. Upon this point, the Court of Civil Appeals held:

“It appearing from the court’s findings that the plans and specifications furnished by appellant were sufficient and were used by appellee in the construction of said theater building, and that appellant was discharged by appellee with[1048]*1048out any fault or negligence upon appellant’s part and that appellant was at all times ready, willing, and able to perform his part of said agreement, it is believed that appellant was entitled to recover 5 per cent, of the total cost of the theater building and that the court should not have denied him a recovery of 2 per cent, of the amount expended in the construction of said theater building after appellant was discharged.”

Phelps had been paid 3 per cent, on the cost of the theater building, but not the 5 per cent, called for in the contract.

On rehearing, the Court of Civil Appeals makes this holding:

“Appellee makes a point in his motion for rehearing that we were in error in reforming the judgment so as to allow appellant a recovery of $1,246 on the item of $62,300 expended in the constx-uction of the theater building after appellant’s discharge, claiming that this court applied an incorrect measure of damage, in that appellant did, not plead nor prove that he could [not] have saved himself from the consequences of the default of appellee by obtaining work elsewhere. There is no merit in this contention, as the authorities hold that this is a matter of defense and must at least be raised and the issue tendered by the defendant on the trial. Some of the authorities hold that the defendant must plead such issue.
“It has been concluded, however, that we were in error in awarding appellant a recovery for said sum, as the rule seems to be in such cases that while the complaining party may recover the natural and probable profits the contract would have 'yielded, when they are certain and not contingent, but he must not receive when the work is not done the same amount of money he would have received had the contract been fully executed, and it has been held that a further deduction should be made for the less time engaged and for release from care, trouble, risk, and responsibility attending a full execution of the contract. Porter v. Burkett, 65 Tex. 383.
“What amount should be allowed in such case is a question for the trial court or jury, as the case may be, and cannot be determined here. Being of the opinion that appellant is entitled to recover some damage on said item of $1,246 under the issues as presented on this appeal, the appellant’s motion is overruled, and for the reason indicated appellee’s motion for rehearing is granted in part. The judgment of the trial court is reversed and the cause remanded.”

See 278 S. W. 942.

Application for writ of error was filed by Phelps only.

The chief contention centers about this item of $1,246, being 2 per cent, on the sum of $62,300 spent on the theater building after Phelps was discharged and when his supervision of the construction thereof ceased. In its original opinion, the Court of Civil Appeals held that $62,800 was expended after the discharge of Phelps. That difference of $500 in the two opinions accounts for the $10 difference between the amounts of $1,256 and $1,246 used in the opinions. As Phelps did not object to this finding of fact by the Court of Civil Appeals on rehearing, we adopt the latter figure. Was the Court of Civil Appeals correct in its original opinion or in its opinion on rehearing? We think its original opinion correctly allowed this additional amount.

The contention is that, even though Connellee breached his contract, without cause, and discharged Phelps, the latter must show that he could not have mitigated his damages by seeking and finding employment elsewhere. Upon this point, the Court of Civil Appeals correctly holds that such an issue is a defensive matter. But, in spite of the fact that no such defense was pleaded, the Court of Civil Appeals remands the case just as though it had been pleaded. It is elementary that an appellate court will not reverse a case, which should otherwise be affirmed, on an issue which was not pleaded in the trial court.

The Court of Civil Appeals cites the case of Porter v. Burkett, 65 Tex. 383. In that case this defense was raised in the trial court by special exception. We have been unable to find any case where a defense will be considered for the first time in an appellate court.

In this connection, the first assignment of error in the application for writ of error reads as follows:

“The court erred in holding on rehearing that error had been committed by its former judgment in reforming the judgment of the trial court so as to allow plaintiff in error a recovery of twelve hundred and forty-six ($1,246) dollars, in addition to that allowed by the trial court, said twelve hundred and forty-six ($1,246) dollars being the amount at contract price to which plaintiff in error was entitled for supervision of the theater, and in setting aside the judgment which this court had rendered for said additional twelve hundred and forty-six ($1,246) dollars, and in reversing and remanding the case for a trial on the issue as to the amount of reduction which should be made from said twelve hundred and forty-six ($1,246) dollars.”

Under this assignment, three propositions are made, as follows:

First: “Plaintiff in error having sued upon a contract for personal and professional services which fixed the basis for his compensation, the burden was on defendant in error, if he desired to diminish the contract price, to plead and prove facts upon which to do so.”
Second: “Plaintiff in error having sued upon his contract, and the issue tendered by the pleadings being solely his right to recover or not recover upon the contract, and a right to recover having been established by both the trial court and by the Court of Civil Appeals, there was no basis in the pleading or proof for diminution of the contract amount, and the trial court should have entered judgment therefor.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Lake Dallas v. Lake Cities Municipal Utility Authority
555 S.W.2d 163 (Court of Appeals of Texas, 1977)
P. G. Lake, Inc. v. Sheffield
438 S.W.2d 952 (Court of Appeals of Texas, 1969)
Niles v. Parsons
239 S.W.2d 740 (Court of Appeals of Texas, 1951)
Smith v. Hamilton
237 S.W.2d 774 (Court of Appeals of Texas, 1951)
Wood Motor Co. v. Nebel
232 S.W.2d 772 (Court of Appeals of Texas, 1950)
Morgan v. Young
203 S.W.2d 837 (Court of Appeals of Texas, 1947)
City of Kirbyville v. Smith
104 S.W.2d 564 (Court of Appeals of Texas, 1937)
Penrod v. Von Wolff
90 S.W.2d 859 (Court of Appeals of Texas, 1936)
De Carli v. O'Brien
41 P.2d 411 (Oregon Supreme Court, 1934)
John Maynard Lumber Co. v. Brazell
28 S.W.2d 877 (Court of Appeals of Texas, 1930)
Page v. Harlingen Independent School Dist.
23 S.W.2d 829 (Court of Appeals of Texas, 1929)
Texas & N. O. R. v. Wolfson
23 S.W.2d 455 (Court of Appeals of Texas, 1929)
Smith v. Miller
300 S.W. 953 (Court of Appeals of Texas, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
285 S.W. 1047, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phelps-v-connellee-texcommnapp-1926.