Pacificorp v. Lakeview Power Co.

884 P.2d 897, 131 Or. App. 301, 1994 Ore. App. LEXIS 1638
CourtCourt of Appeals of Oregon
DecidedNovember 16, 1994
DocketL91-0074CV; CA A76524
StatusPublished
Cited by8 cases

This text of 884 P.2d 897 (Pacificorp v. Lakeview Power Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacificorp v. Lakeview Power Co., 884 P.2d 897, 131 Or. App. 301, 1994 Ore. App. LEXIS 1638 (Or. Ct. App. 1994).

Opinion

DEITS, P. J.

In 1984, plaintiff Pacificorp and defendant Lakeview Power Company entered into a contract whereby plaintiff agreed to purchase the electric power that would eventually be produced at defendant’s planned cogeneration plant. In 1988, defendant sued plaintiff, claiming that plaintiff had wrongfully repudiated the contract and prevented the completion of the project. That lawsuit was settled and, in January and February, 1989, the parties entered into four written agreements. One of those instruments, the Power Purchase Agreement (PPA), provided that the contractual relationship would automatically terminate, unless plaintiff gave notice otherwise in writing, if various events did not occur by specified dates. The earliest of those events was for defendant to “obtain an irrevocable commitment for long-term and construction financing” by January 1, 1991. According to plaintiff, defendant failed to meet that condition. Plaintiff therefore ceased its performance and treated the contract as terminated.

In February, 1991, plaintiff brought this declaratory judgment action, contending that it had no further obligation to perform under the agreements because of defendant’s alleged default. Defendant counterclaimed, alleging breach of contract and violations of ORS chapter 758, the Oregon analog of the federal Public Utilities Regulatory Policy Act (PURPA). 16 USC § 824a-3. The case was tried to a jury, which found by a general verdict in favor of plaintiff. Defendant appeals, and we reverse and remand.

We turn first to plaintiffs cross-assignment, in which it contends that the trial court erred by denying its motion for a directed verdict. It argues that the agreements terminated as a matter of law as a result of defendant’s failure to obtain an irrevocable financing commitment, and that there was no evidence that defendant did obtain such a commitment. We disagree. The testimony of defendant’s principal that he did have a commitment could support a finding for defendant on that issue.

The first three of defendant’s 19 assignments challenge, along with related rulings, the court’s giving of the following instructions:

[304]*304“Pacific contends that defendant did not obtain an irrevocable financing commitment by January 1,1991 and that the defendant missed all of the other contractual deadlines so that the contract has ended.
% ‡ #
“Defendant was required to meet certain deadlines for the construction and operation of the plant in order for the contracts to remain in effect. Specifically, the defendant was required to meet the following contractual deadlines:
“1. By January 1,1991, defendant was to have obtained an irrevocable commitment for long term and construction financing of the project;
“2. By March 1, 1991, defendant must have obtained fuel supply contracts;
“3. By July 1, 1991, defendant must have obtained all required government permits and authorizations;
“4. By July 1, 1991, defendant must have begun construction of the project; and
“5. By July 1,1994, the project must be operational.
^ j}t # %
“The contracts provided that if defendant failed to meet any of these contractual deadlines, that the defendant violated or breached the parties’ contracts and that those contracts terminated automatically, including Pacific’s obligation to continue making payments to the defendant and to buy electricity from the defendant’s plant. Pacific was entitled to insist on strict compliance with the contractual deadlines and was not required to extend or waive them.
<(>]« % & # H*
“If you find by a preponderance of the evidence that the defendant failed to meet one or more of the contractual deadlines for construction and operation of the plant that was not excused, then your verdict must be for Pacific, unless you also find that the defendant’s failure to meet the contractual deadline was excused.
<<* * * Hs ❖
“If you find that defendant accepted [a contractually required] payment at a time when it believed Pacific had violated any written or oral contracts between the parties, those violations would not excuse any later failure by the defendant to meet the contractual deadlines.”

[305]*305Defendant argues that, under plaintiffs theory, the agreements terminated as a result of the alleged failure to obtain a financing commitment by January 1, 1991. Consequently, no performance of the other conditions due at later times was possible or required, and the court erred by instructing the jury that defendant could have breached the contract by failing to perform the conditions that did not fall due until after the alleged January 1, 1991, default. Defendant argues that the error was compounded by the further instruction that defendant had the burden of showing that its performance of the later conditions was excused:

“Defendant contends that if it failed to meet one or more of the contractual deadlines that failure was excused. In order to prevail on its claim of excuse the defendant must prove that Pacific violated a provision of the parties’ contract andPacific’s action substantially interfered with defendant’s ability to meet the contractual deadlines.”

Plaintiff attaches the opposite significance to that instruction. It maintains:

“ [I]t was undisputed in this case that Pacific declared the PPA terminated in January 1991. If the jury found that Pacific’s actions constituted an improper repudiation of the PPA and that [defendant] failed to perform [its] subsequent obligations under the PPA, the jury must be presumed to also have found such performance to be excused. [Defendant’s] argument assumes that the jury disregarded the instructions concerning excused performance and, accordingly, should be rejected.”

We do not agree with plaintiffs view of the impact of this instruction. Both parties ceased performing after plaintiff declared the agreement terminated in response to defendant’s alleged failure to meet the financing condition by January 1, 1991. As plaintiff appears to agree, the case was presented and tried on the theory that one party or the other was in violation of the agreement as of January, 1991: defendant if it had not obtained the irrevocable commitment for financing, and plaintiff if defendant had done so and plaintiff had nonetheless terminated the agreement. More fundamentally, if defendant had not procured the financing, and its performance was therefore necessarily not excused under the instruction, no later performance would have been possible, because the agreement would have terminated automatically [306]*306by its terms on January 1. In sum, no performance that was due after January 1 was of any relevance, under the theories that the parties presented. Nevertheless, as defendant contends, the instructions appeared to allow the jury to find for plaintiff if it concluded that defendant had not performed any of those later conditions and had not proved specifically that their nonperformance was excused by a breach on plaintiffs part.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
884 P.2d 897, 131 Or. App. 301, 1994 Ore. App. LEXIS 1638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacificorp-v-lakeview-power-co-orctapp-1994.