Rose Marine LLC v. Sottosanti

CourtDistrict Court, D. Oregon
DecidedJune 6, 2022
Docket3:21-cv-00523
StatusUnknown

This text of Rose Marine LLC v. Sottosanti (Rose Marine LLC v. Sottosanti) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rose Marine LLC v. Sottosanti, (D. Or. 2022).

Opinion

UNITED STATES DISTRICT COURT

DISTRICT OF OREGON

ROSE MARINE LLC, an Oregon Limited Ca se No. 3:21-cv-00523-AC Liability Company, OPINION AND ORDER Plaintiff, v.

ALLEN SOTTOSANTI and RENALYND SOTTOSANTI, husband and wife, AMERICAN BREAKWATER, LLC, an Alaska Limited Liability Company,

Defendants. _____________________________________

ACOSTA, Magistrate Judge:

On April 7, 2021, plaintiff Rose Marine LLC (“Plaintiff”) filed this action against defendants Allen and Reynalynd Sottosanti and against American Breakwater LLC, an Alaska limited liability company of which Mr. Sottosanti is the sole member (collectively, “Defendants”). (Compl. ¶¶ 3-5, ECF No. 1). On July 12, 2021, the parties entered into a settlement agreement. (Decl. of Chris M. MacMillan (“MacMillan Decl.”) ¶ 4, Ex. 1, ECF No. 10-2). Before the court

Page 1 – OPINION AND ORDER is Plaintiff’s motion to enforce that settlement agreement, which it contends Defendants have breached in the entirety. (Mot. to Enforce Settlement Agreement, ECF No. 10). For the reasons that follow, Plaintiff’s motion is granted in part and denied in part.1 Background Plaintiff is the owner of a 92-foot vessel known as the Golden Rose. (Comp. ¶ 1). In early 2020, Plaintiff—through its now deceased former manager—leased the Golden Rose to Defendants for a term of six months. (Id.). Plaintiff contends that, while in the possession the Golden Rose, Defendants breached the parties’ contract by failing to make installment payments, failing to maintain a standard maritime insurance policy, and negligently operating and damaging

the vessel. (Id. ¶¶ 1-14). In April 2021, Plaintiff filed this action to recover damages from Defendants. (Id., Prayer for Relief). Subsequently, the parties negotiated an agreement to settle all claims. (MacMillan Decl. ¶ 3, Ex. 2 at 5-7). Plaintiff was represented by counsel, Christopher MacMillan; Defendants were not represented. (Id. ¶ 1). On July 12, 2021, the parties entered a settlement agreement. (MacMillan Decl. ¶ 4, Ex. 1 at 1). Mr. Sottosanti signed the settlement agreement twice: once for himself and once for American Breakwater LLC. (Id.) Under the terms of the settlement agreement, the parties agreed to dismiss all claims with prejudice and without fees and costs. (Id. at 1). In exchange, Defendants promised they would: (1) pay $7,458.71, the remaining amount owed to Pacific Power Group, LLC, a third party

mechanic that had made repairs on the Golden Rose; and (2) “return all logbooks pertaining the

1 The parties have consented to jurisdiction by magistrate judge in accordance with 28 U.S.C. § 636(c)(1).

Page 2 – OPINION AND ORDER Golden Rose” to Plaintiff. (Id.). The settlement Agreement did not define the meaning of the term “logbooks.” The agreement, however, did contain a severability clause providing “in the event any provision . . . should be held to be void, voidable, or unenforceable, the remaining portions thereof shall remain in full force and effect.” (Id.). Additionally, the agreement provided that, should any party need to enforce the agreement, the prevailing party “shall recover all of the [breaching] party’s costs and reasonable attorney’s fees incurred.” (Id. at 2). Oregon law governs the agreement. (Id.). The deadline to comply with the terms of the settlement agreement was set for July 20, 2021, seven days after the parties executed the agreement. (Id. at 2). Defendants failed to meet

that deadline. (See MacMillan Decl. ¶ 6, Ex. 3). The next day, Plaintiff’s counsel notified Mr. Sottosanti that he was in breach of the settlement agreement and warned him that, if necessary, Plaintiff would move to enforce the agreement. (Id. at 27). Mr. Sottosanti responded that he had been searching through his storage, but needed more time to locate the vessel information. (Id. at 26). He also stated, “as for Pacific Power [Group], they know the circumstances of the litigation, [and] I’d like to think I could deal with them after I settle the vessel information issue.” (Id.). Plaintiff granted Defendants a few more weeks to comply with the term of the settlement agreement, but eventually moved to enforce the agreement on August 12, 2021. (Mot. to Enforce Settlement Agreement at 1). On February 8, 2022, the court held a hearing on that motion. (Minutes of Proceeding, ECF No. 16). Plaintiff’s counsel was present, but due to some confusion

about the time zone, Mr. Sottosanti was unable to attend, so the court reset the hearing for February 18, 2022. (Order Staying Ruling, ECF No. 17). The reset hearing is discussed more fully below. The court took Plaintiff’s motion under advisement that same day. (Id.).

Page 3 – OPINION AND ORDER Legal Standard A district court has the power to summarily enforce an agreement to settle a case pending before it. Callie v. Near, 829 F.3d 888, 890 (9th Cir. 1987). Summary enforcement, however, is inappropriate “where material facts concerning the existence or terms of a settlement agreement [a]re in dispute.” In re City Equities Anaheim, Ltd., 22 F.3d 954, 957 (9th Cir. 1994) (internal citations omitted). “The construction and enforcement of settlement agreements are governed by principles of local law which apply to interpretations of contracts generally.” Jeff. D. Andrus, 899 F.3d 753, 759 (9th Cir. 1989). Under Oregon law, the determination of whether a contract exists is a question of law. In

re Marriage of Baldwin, 215 Or. App. 203, 207 (2007). “In determining whether a contract exists and what its terms are, [the court] examine[s] the parties’ objective manifestations of intent, as evidenced by their communications and acts.” Ken Hood Constr. v. Pac. Coast Constr., 201 Or. App. 568, 578, adh'd to as modified on recons. by 203 Or. App. 768, rev. denied, 341 Or. 366 (2006). Thus, the determination of whether a contract exists “does not depend on whether the parties had the same subjective understanding of their agreement . . . it depends on whether the parties agreed to the same, express terms of the agreement, and on whether those terms constitute an enforceable agreement.” City of Canby v. Rinkes, 136 Or. App. 602, 611 (1995). The parties need only agree on the essential or material elements of the contract, not on every possible term. Pacificorp v. Lakeview Power Co., 131 Or. App. 301, 307 (1994). A

contractual term is material if it goes to “the substance of the contract and, if breached, defeat[s] the object of the parties in entering into the agreement.” Johnstone v. Zimmer, 191 Or. App. 26, 34 (2003). Additionally, where a contract contains a severability clause, the court may enforce

Page 4 – OPINION AND ORDER the remainder of the contract even where one material term is found to be unenforceable. See In re Marriage of McInnis, 199 Or. App. 223, 234 (2005) (holding trial court was correct to find provision of settlement agreement unlawful, but erred in concluding the entire agreement was unenforceable where the agreement contained a severability clause). Discussion Plaintiff requests that the court enforce the parties’ settlement agreement by issuing an order directing Defendants, jointly and severally, to: (1) pay the $7,458 owed to the Pacific Power Group; and (2) either return the Golden Rose “logbooks” to Plaintiff or pay $5,0002 in compensatory damages for failure to return that vessel information. (Mot. to Enforce at 7).

Plaintiff also requests the attorney fees and costs incurred in filing this motion. (Id.). The court finds no dispute with respect to Plaintiff’s first request, and therefore, orders Defendants, jointly and severally, to pay $7,458 to the Pacific Power Group as directed in the settlement agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Canby v. Rinkes
902 P.2d 605 (Court of Appeals of Oregon, 1995)
Johnstone v. Zimmer
81 P.3d 92 (Court of Appeals of Oregon, 2003)
Ken Hood Construction Co. v. Pacific Coast Construction, Inc.
120 P.3d 6 (Court of Appeals of Oregon, 2005)
Ken Hood Construction Co. v. Pacific Coast Construction, Inc.
126 P.3d 1254 (Court of Appeals of Oregon, 2006)
Pacificorp v. Lakeview Power Co.
884 P.2d 897 (Court of Appeals of Oregon, 1994)
In re the Marriage of Baldwin
168 P.3d 1233 (Court of Appeals of Oregon, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Rose Marine LLC v. Sottosanti, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rose-marine-llc-v-sottosanti-ord-2022.