Pace Const. v. Cascella Son Const., No. Cv 94 0317925s (Nov. 25, 1994)

1994 Conn. Super. Ct. 11788, 13 Conn. L. Rptr. 33
CourtConnecticut Superior Court
DecidedNovember 25, 1994
DocketNo. CV 94 0317925S
StatusUnpublished
Cited by1 cases

This text of 1994 Conn. Super. Ct. 11788 (Pace Const. v. Cascella Son Const., No. Cv 94 0317925s (Nov. 25, 1994)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pace Const. v. Cascella Son Const., No. Cv 94 0317925s (Nov. 25, 1994), 1994 Conn. Super. Ct. 11788, 13 Conn. L. Rptr. 33 (Colo. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION The plaintiff has made application to the court for an order vacating an arbitration award pursuant to General Statutes § 52-4201 on the grounds that the award is against public policy.

The plaintiff general contractor and the defendant subcontractor entered into an American Institute of Architects' "Standard Form of Agreement Between Contractor and Subcontractor." The plaintiff presented the contract to the defendant for its signature. There is no dispute that both parties are signatories to the contract.

Article thirteen of the contract provides that "[a]ll claims, disputes and other matters in question arising out of, or relating to, this Subcontract, or the breach thereof, shall be decided by arbitration . . . in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise." On or about October 11, 1991, the defendant made a demand for arbitration with the American Arbitration Association on a form provided for by that association. Under "nature of dispute" the defendant stated: "Balance due and owing under subcontract." The "claim or relied sought" was stated to be $180,000.

On August 24, 1994, the arbitrator rendered an award for the defendant. Specifically, the arbitrator awarded "Cascella Son Construction, Inc. the sum of $60,732.00 to be paid by Pace Construction, Inc. This is the amount determined by the Arbitrator to be awarded after the application by him of (a) setoffs agreed on by the parties during the proceedings, and (b) application of the setoffs claimed by the Respondent (Pace Construction, Inc.) in his counterclaim which were disputed by the Claimant (Cascella Son Construction, Inc.). In addition, Pace Construction, Inc., is directed to make payment of the total sum of $8,675.00 for labor and materials as previously agreed to by the parties."

The plaintiff timely made application to vacate the award claiming that "[t]he claim of Cascella and the award of the arbitrator is made pursuant to § 14.2.1 of the subcontract . . . a termination clause which is unenforceable because it is against public policy."

Section 14.2.1 of the subcontract provides:

If the Subcontractor persistently or repeatedly fails or neglects CT Page 11790 to carry out the Work in accordance with the Contract Documents or otherwise to perform in accordance with this Agreement and fails within seven days after receipt of written notice to commence and continue correction of such default or neglect with diligence and promptness, the Contractor may, after seven days following receipt by the Subcontractor of an additional written notice and without prejudice to any other remedy he may have, terminate the Subcontract and finish the Work by whatever method he may deem expedient. If theunpaid balance of the Contract Sum exceeds the expense of finishingthe Work, such excess shall be paid to the Subcontractor, but if such expense exceeds such unpaid balance, the Subcontractor shall pay the difference to the Contractor."

(Emphasis added.)

In Saxon Construction Management Corp. v. Masterclean ofNorth Carolina, Inc., 273 N.J. Super. 231, 641 A.2d 1056 (App.Div. 199 4), cert. denied, 137 N.J. 3 —, 645 A.2d 142 (1994), the Appellate Division of the Superior Court of the State of New Jersey affirmed a Superior Court decision which held that a provision identical to § 14.2.1 was void as against public policy. The plaintiff here rests his entire case on the decision in Saxon.

In Saxon, the plaintiff general contractor instituted a civil action alleging that the defendant Masterclean, a subcontractor, breached its subcontract for asbestos abatement and removal in four hospital buildings. After Masterclean had completed work on two buildings, it failed to do the work on the remaining two buildings. After repeatedly requesting that Masterclean perform its contract, Saxon declared Masterclean in default. After terminating its contract with Masterclean, Saxon entered into a new contract with another subcontractor. Id., 273 N.J. Super. 233-234. "It is undisputed that Saxon paid the new subcontractor approximately $200,000 less than it would have been required to pay Masterclean had the defendant performed its obligation." Id., 234-235.

The trial court held that Masterclean had breached the subcontract but that Saxon had suffered no damages. At issue on appeal was Masterclean's counterclaim, based on a contract provision similar to § 14.2.1 in which it sought the $200,000 difference between what it would have been entitled to charge under its subcontract with Saxon and what Saxon had to pay to complete the job. Id., 273 N.J. Super. 234-235. The trial court had denied the counterclaim but awarded Masterclaim damages based on quantum meruit for the work it had performed. CT Page 11791

The question presented on appeal was whether the termination clause "violates public policy because it permits a defaulting party to profit by its breach of the agreement and discourages the innocent party from minimizing its losses." Id., 273 N.J. Super. 235 . The Appellate Division observed that in New Jersey, the sources of public policy "`include federal and state legislationand judicial decisions.'" (Emphasis added.) Id., 237. That court held that the termination clause violated public policy because it promoted economic waste. That clause, said the court,

encourages the subcontractor to breach its agreement where it knows that its services can be purchased at an amount less than the contract price. It provides the defaulting subcontractor with a windfall despite the express language sanctioning the subcontractor's termination for `repeated fail[ure] . . . to carry out [its contractual duty].' And it discourages the contractor from affirmatively seeking to minimize its losses by obtaining a substitute contractor at a lesser cost." Id., 237-238. The court did not rely on any statutory basis for its decision but, rather, observed that "[t]he economic waste doctrine has its origin in compelling considerations of equity and justice." Id., 238.

The procedural posture in which the present case arises is significant. Saxon was a civil action for breach of contract. This case is an application to vacate an arbitration award. "An application to vacate an arbitration award triggers special statutory proceedings that are not civil actions." Middletown v.Police Local, No. 1361, 187 Conn. 228, 231, 445 A.2d 322 (1982). "General Statutes 52-418 (a) provides in pertinent part: `Upon the application of any party to an arbitration, the superior court . . . shall make an order vacating the award if it finds any of the following defects . . . (4) if the arbitrators have exceeded their powers . . . .' The trial court's analysis under this provision ordinarily is limited to whether the arbitration award conformed to the submission.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Haven Crossing Ltd. v. C C Inc., No. Cvnh 9707-8350 (Sep. 29, 1997)
1997 Conn. Super. Ct. 8462 (Connecticut Superior Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
1994 Conn. Super. Ct. 11788, 13 Conn. L. Rptr. 33, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pace-const-v-cascella-son-const-no-cv-94-0317925s-nov-25-1994-connsuperct-1994.