Gennarini Construction Co. v. Messina Painting & Decorating Co.

496 A.2d 539, 5 Conn. App. 61, 1985 Conn. App. LEXIS 1099
CourtConnecticut Appellate Court
DecidedAugust 20, 1985
Docket3609
StatusPublished
Cited by15 cases

This text of 496 A.2d 539 (Gennarini Construction Co. v. Messina Painting & Decorating Co.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gennarini Construction Co. v. Messina Painting & Decorating Co., 496 A.2d 539, 5 Conn. App. 61, 1985 Conn. App. LEXIS 1099 (Colo. Ct. App. 1985).

Opinion

Borden, J.

The plaintiff appeals from the judgment of the trial court granting the defendant’s motion to *62 confirm an arbitration award and denying the plaintiffs application to vacate the award.

The trial court found the following facts: The plaintiff contractor entered into a subcontract with the defendant subcontractor to do painting work on a public project. A dispute arose because of the defendant’s use of nonunion painters. The defendant completed the subcontract in a timely fashion, and the architect and public authority accepted the project.

The defendant claimed that money was due it on the subcontract and the parties submitted the claim to arbitration. The submission encompassed two issues: (1) what money, if any, was owed to the defendant; and (2) whether General Statutes § 49-41a (b) 1 could be applied by the arbitrator in this case, and, if so, what remedy was to be awarded. 2

*63 The arbitrator found that the plaintiff owed the defendant $5142.42 on the subcontract. He also found that he had the authority to provide a remedy under General Statutes § 49-41a (b), and awarded the defendant interest and attorney’s fees under that statute.

The plaintiff filed an application to vacate the arbitration award and the defendant filed a motion to confirm it. The defendant also moved for an order awarding it supplemental interest and attorney’s fees which had accrued subsequent to the date of the arbitration award. In a detailed memorandum of decision, the trial court granted the defendant’s motion to confirm the award and denied the plaintiff’s application to vacate. It did not address the issue of the supplemental award of interest and attorney’s fees.

On appeal, the plaintiff claims that the trial court erred in upholding the arbitrator’s award because the arbitrator exceeded the scope of the submissions and his powers in interpreting the statute. The defendant, by way of a preliminary statement of issues; see Practice Book § 3012 (a); claims that the trial court erred in failing to award supplemental attorney’s fees and interest to the defendant. We find no error on either of the parties’ claims.

The plaintiffs claims that the arbitrator exceeded the scope of the submissions and his powers are unavailing. The two submissions to the arbitrator were broadly phrased and included questions involving the merits of the appeal as well as questions of arbitrability of damages under General Statutes § 49-41a (b). As the trial court found, the submissions were unrestricted. No conditional language was used by the parties binding the *64 court to strict rules of law. Bic Pen Corporation v. Local No. 134, 183 Conn. 579, 584-85, 440 A.2d 774 (1981); Chase Brass & Copper Co. v. Chase Brass & Copper Workers Union, 139 Conn. 591, 595-96, 96 A.2d 209 (1953). Where the submission is unrestricted, the award is final and binding and cannot be reviewed for errors of law or fact. Roraback v. Travelers Ins. Co., 4 Conn. App. 21, 23, 492 A.2d 208 (1985).

The first question submitted was plainly unrestricted by its terms. See footnote 2, supra. The parties are bound by the arbitrator’s decision on that question. Roraback v. Travelers Ins. Co., supra, 23-24.

The second question submitted embraced the issue of arbitrability under a certain statute and the applicability and availability of a remedy under that statute if found arbitrable. Neither party chose to compel a judicial determination of the issue of arbitrability prior to arbitration, although the option was available to them. Schwarzschild v. Martin, 191 Conn. 316, 323, 464 A.2d 774 (1983); New Britain v. Connecticut State Board of Mediation & Arbitration, 178 Conn. 557, 560, 424 A.2d 263 (1979); see also General Statutes § 52-415 (parties may request that arbitrators ask court’s advice on questions arising during hearing). The invocation of a specific statute under which to determine damages is not, in and of itself, sufficient to restrict the submission. Cf. Chase Brass & Copper Co. v. Chase Brass & Copper Workers Union, supra. The second question, therefore, was also unrestricted although it left the question of arbitrability to the arbitrator.

“[WJhere the issue of arbitrability is committed to an arbitrator for determination, ‘the court is bound by the arbitrator’s determination unless that determination clearly falls within the proscriptions of § 52-418 of the General Statutes, or procedurally violates the parties’ agreement.’ ” Waterbury Board of Education *65 v. Waterbury Teachers Assn., 168 Conn. 54, 63, 357 A.2d 466 (1975). The award in this case did not do so.

A challenge to an award on the ground that the arbitrator has exceeded his powers or so imperfectly executed them that a mutual, final and definitive award was not made upon the matter submitted; General Statutes § 52-418 (a) (4); is reviewed by comparing the award with the submission. Roraback v. Travelers Ins. Co., supra, 23. In making such a comparison, where the submission is unrestricted, the court will not review the evidence or the legal questions involved but is bound by the arbitrator’s legal and factual determinations. Game-A-Tron Corporation v. Gordon, 2 Conn. App. 692, 695, 483 A.2d 620 (1984). The terms of the award in this case tracked the language of the parties’ second submission and clearly conformed to it. The award, therefore, cannot be vacated pursuant to General Statutes § 52-418 (a) (4), as the plaintiff suggests.

There is no allegation here that the arbitrator’s determination procedurally violated the terms of the parties’ contract. The pertinent clauses of the contract indicate that the parties did not delineate any narrow procedural limits to govern arbitration which might arise between them. See Waterbury Board of Education v. Waterbury Teachers Assn., supra, 62. In addition, procedural irregularities may be waived. Id., 63. If any existed here, they are deemed waived by the parties’ failure to raise them in the trial court. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marshall v. Marshall
200 Conn. App. 688 (Connecticut Appellate Court, 2020)
Moasser v. Becker
946 A.2d 230 (Connecticut Appellate Court, 2008)
Locals 387, 391 v. Conn. Dept. of Corr., No. Cv 98-0579718 (Jun. 18, 2002)
2002 Conn. Super. Ct. 8203-cy (Connecticut Superior Court, 2002)
City of Hartford v. International Ass'n of Firefighters, Local 760
717 A.2d 258 (Connecticut Appellate Court, 1998)
R. G. Vadney, Inc. v. Teamsters, Local 443, No. Cv 95-0376587 (Dec. 9, 1996)
1996 Conn. Super. Ct. 7274 (Connecticut Superior Court, 1996)
Town of Wallingford v. Local 1570, No. Cv95-0378164 (Mar. 7, 1996)
1996 Conn. Super. Ct. 2491 (Connecticut Superior Court, 1996)
Pace Const. v. Cascella Son Const., No. Cv 94 0317925s (Nov. 25, 1994)
1994 Conn. Super. Ct. 11788 (Connecticut Superior Court, 1994)
Kenney v. Andrews, No. Cv91 0501207 (Apr. 13, 1994)
1994 Conn. Super. Ct. 3578 (Connecticut Superior Court, 1994)
State v. Council 4
608 A.2d 718 (Connecticut Appellate Court, 1992)
City of W. Haven v. Afscme, Local 681, No. Cv 91-0314371 (Dec. 31, 1991)
1991 Conn. Super. Ct. 10840 (Connecticut Superior Court, 1991)
Gennarini Construction Co. v. Messina Painting & Decorating Co.
545 A.2d 579 (Connecticut Appellate Court, 1988)
Town of East Hartford v. East Hartford Municipal Employees Union, Inc.
525 A.2d 112 (Connecticut Appellate Court, 1987)
Wolf v. Gould
522 A.2d 1240 (Connecticut Appellate Court, 1987)
City of Hartford v. Local 760, International Ass'n of Firefighters
502 A.2d 429 (Connecticut Appellate Court, 1986)
Orsini v. Manson
498 A.2d 114 (Connecticut Appellate Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
496 A.2d 539, 5 Conn. App. 61, 1985 Conn. App. LEXIS 1099, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gennarini-construction-co-v-messina-painting-decorating-co-connappct-1985.