Overlake Fund v. Shorelines Hearings Board

954 P.2d 304, 90 Wash. App. 746
CourtCourt of Appeals of Washington
DecidedApril 13, 1998
Docket37896-1-1, 38012-5-1
StatusPublished
Cited by5 cases

This text of 954 P.2d 304 (Overlake Fund v. Shorelines Hearings Board) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Overlake Fund v. Shorelines Hearings Board, 954 P.2d 304, 90 Wash. App. 746 (Wash. Ct. App. 1998).

Opinions

[750]*750Agid, J.

These are difficult times for property owners, community groups and municipalities, the triumvirate involved in every major land use issue. The manner in which one uses—or does not use—land is debated endlessly and has become a volatile emotional issue for all concerned. Peace may not be at hand, but the courts and the agencies charged with applying land use and environmental regulations have a responsibility to be evenhanded and balance the many competing concerns.

After five years and seven redesigns, the City of Bellevue (Bellevue) issued a conditional use permit, a shoreline height variance and a substantial development permit to the Overlake Fund to construct a hotel on the shore of Lake Washington. Bellevue imposed numerous conditions on the permits to protect the surrounding environment and comply with zoning, building, traffic and fire safety requirements. No one appealed the conditional use permit. Geoffrey Bidwell appealed the shoreline permits to the Shorelines Hearings Board (Board). After a hearing, the Board affirmed the height variance. It also “affirmed” the substantial development permit, but only after imposing additional conditions which prohibited Overlake from using any of the wetland on the site for any purpose. Over-lake and Bellevue appealed the substantial development permit decision to the superior court which affirmed the Board. Bellevue and Overlake appealed to this court. We conclude that the administrative board unnecessarily thwarted Bellevue’s careful, balanced permitting decisions by considering issues not before it and failing to recognize the importance of balancing competing interests. The Board ignored or did not inquire into the reasons for the municipal balancing act, considered only one of the many [751]*751competing values that contributed to Bellevue’s decision and substituted its judgment on the reasonableness of the use for that of local decision-makers. We hold that the decision of the Board redesigning the Overlake hotel project was arbitrary and capricious and not supported by substantial evidence. We therefore reverse and remand to reinstate the original permits issued by Bellevue. This will restore the balance Bellevue sought to achieve.1

FACTS

After years of negotiation and attempts to find an economically-viable plan that satisfied its myriad planning and environmental concerns, Bellevue issued a substantial development permit and shoreline variance to Overlake on October 21, 1993. As finally approved, the permits allowed Overlake to construct a 7-story, 238 room hotel with parking for 346 vehicles on a 6.9 acre parcel of land located between downtown Bellevue and the Lake Washington shoreline. The Department of Ecology (DOE) approved the permit and variance subject to certain conditions on November 29, 1993. As outlined above, these appeals followed.

Overlake has owned the property on which the hotel is to be built since 1980. It has been zoned for urban uses, Office and Limited Business, since 1981. Of the 6.99 acre site, 0.8 acre is dry land. The remaining 6.19 acres are wetland. The proposed construction would use 1.62 acres of the site and impact between .73 and 1 acre, or 13 percent of the site’s total wetland. If no further design review changes are authorized, the project will have some impact on .82 acre of the 6.19 acres of wetland, but 5.73 acres will remain untouched. The proposal was conditioned on the developer’s implementing a number of wetland mitigation [752]*752measures. The Corps of Engineers,2 the Department of Ecology and Bellevue have all issued permits and approved the project. It has gone through the process of developing an environmental impact statement and seven redesigns over five years. The original proposal would have covered 1.5 acres of wetland. That has been reduced to a little over half of the originally-proposed wetland coverage. Even though the Corps approved filling an acre of the property, Bellevue insisted on redesigns that put the structure as far upland as possible on the dry portion of the property and located the wetland development on pilings to minimize any impact on the wetland below.

The property is bisected by Sturtevant Creek which flows from the north through the wetland and connects to Mercer Slough and Lake Washington. The Board found that although road and building development had acted over time to isolate the wetland adjacent to the project from the larger Mercer Slough wetland, it remains a functioning part of the Mercer Slough system as a whole and is not an isolated wetland.3 The substantial development permit approved by Bellevue allowed the hotel to cover 52,274 square feet of the site, including 35,624 square feet on pilings over the wetland. The Board observed that, as approved, the hotel would cover all of the dry land on the site, except for the street setbacks required by Bellevue, and .82 acre of the wetland. It also found that, although there had been agricultural activities in portions of the wetland system, the site is in an essentially natural state. The Board concluded that the proposed development would intrude into and damage the wetland and that the proposed mitigation plan failed to adequately mitigate the impact of the hotel on it. The Board approved a height variance of 92.27 [753]*753feet because Bidwell failed to meet his burden of proof on that issue, but modified the substantial development permit to prohibit any use of the wetland on the site. It also imposed, sua sponte, view, public access and lighting conditions on the project.4

DISCUSSION

Standard of Review

All development on the shorelines of this state undertaken after June 1,1971, must conform to the Shoreline Management Act of 1971 (SMA), RCW 90.58. Buechel v. Department of Ecology, 125 Wn.2d 196, 203, 884 P.2d 910 (1994). The Shorelines Hearings Board reviews the issuance of a shoreline development permit de novo. Buechel, 125 Wn.2d at 202. Appellate review is of the Board’s decision, not that of either the local government or the superior court, and is based on the record before the Board. Buechel, 125 Wn.2d at 202.5 Courts review the Board’s decision to determine whether it is supported by substantial evidence [754]*754in light of the entire record, or is arbitrary and capricious.* ****6 RCW 34.05.570(3); Heinmiller v. Department of Health, 127 Wn.2d 595, 607, 903 P.2d 433, 909 P.2d 1294 (1995), cert. denied, 516 U.S. 1006, 116 S. Ct. 2526, 135 L. Ed. 2d 1051 (1996); Buechel, 125 Wn.2d at 202. “ ‘Substantial evidence is “evidence in sufficient quantum to persuade a fair-minded person of the truth of the declared premises”.’ ” Heinmiller, 127 Wn.2d at 607 (quoting Nghiem v. State, 73 Wn. App. 405, 412, 869 P.2d 1086 (1994)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Puyallup Tribe Of Indians, V City Of Tacoma
Court of Appeals of Washington, 2018
Bellevue Farm Owners Ass'n v. Shorelines Hearings Board
100 Wash. App. 341 (Court of Appeals of Washington, 2000)
Bellevue Farm Owners Association v. Shorelines Hearings Bd.
997 P.2d 380 (Court of Appeals of Washington, 2000)
Overlake Fund v. Shorelines Hearings Board
954 P.2d 304 (Court of Appeals of Washington, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
954 P.2d 304, 90 Wash. App. 746, Counsel Stack Legal Research, https://law.counselstack.com/opinion/overlake-fund-v-shorelines-hearings-board-washctapp-1998.