The Puyallup Tribe Of Indians, V City Of Tacoma

Court of Appeals of Washington·Decided May 14, 2018·No. 77748-3·Unpublished

Opinion

•• tILED

COURT OF APPEALS OW I

STATE OF WAStiltIGTON

2010 MAY 14 Ali 9; 1

IN THE COURT OF APPEALS FOR THE STATE OF WASHINGTON

THE PUYALLUP TRIBE OF INDIANS, ) a Federally Recognized Indian Tribe, )

) No. 77748-3-1 Appellant, )

) DIVISION ONE v. )

)

WASHINGTON STATE SHORELINES ) HEARINGS BOARD, CITY OF ) TACOMA,a Washington Municipal ) Corporation, PUGET SOUND ENERGY,) INC., a Washington Corporation, PORT OF TACOMA, a Washington ) Special Purpose District and ) WASHINGTON STATE ) DEPARTMENT OF ECOLOGY, ) UNPUBLISHED OPINION )

Respondents. ) FILED: May 14, 2018

SPEARMAN, J. — We review decisions of the Shorelines Hearings Board to determine if the Board's factual findings are supported by substantial evidence and if these findings, in turn, support the Board's conclusions of law. The Puyallup Tribe of Indians appeals the Shorelines Hearings Board's decision to affirm a shoreline substantial development permit. But because the Board's decision is supported by substantial evidence, we affirm.1

1 Shortly before oral argument, Puget Sound Energy(PSE)filed, as supplemental authority, a decision of the Shorelines Hearing Board in a separate appeal of a Department of Ecology permit. PSE directed the court's attention to the background facts. The Tribe filed a motion to strike on the grounds that the background facts recited in the decision are not authority. We agree with the Tribe and grant the motion.

No. 77748-3-1/2 FACTS

Puget Sound Energy(PSE) proposes to build a liquefied natural gas (LNG)facility near the Blair and Hylebos Waterways in Tacoma. The Blair and Hylebos are man-made inlets excavated from Commencement Bay. The Puyallup Tribe of Indians owns property along both waterways. The Tribe also has treaty rights to fish and shellfish in the Blair and Hylebos.

The land around the Blair and Hylebos Waterways has long been used for heavy industry. This industrial use has degraded conditions in the waterways. In 1983, the Environmental Protection Agency(EPA) listed the Blair and Hylebos Waterways as national priorities (superfund sites). The Blair Waterway was dredged to remove contaminated sediment between 1993 and 1995. Following this action, the EPA removed the Blair from the national priorities list. The Hylebos remains a national priority.

The PSE project involves a land-based LNG processing facility connected by a pipeline to a fueling station in the Blair Waterway. Originally, the project also involved a barge-loading dock on the Hylebos Waterway. As originally planned, the project entailed removing a number of old, creosote-treated piles in both waterways and replacing a dock and bulkhead on the Hylebos. The Environmental Impact Statement Under the State Environmental Policy Act, the project required an Environmental Impact Statement (EIS). The City of Tacoma prepared a draft EIS, notified the public, and sought comments. The Department of Ecology and the EPA both submitted comments. Ecology noted that removing existing piles will release sediment into the water. Ecology recommended that PSE consult with

No. 77748-3-1/3 the Department of Natural Resources and the EPA to determine the best approach for this work. Ecology further commented that, "[i]n general, EPA should be consulted about all in-water construction in the Hylebos Waterway problem area." Administrative Record (AR)at 1074.

In its comments, the EPA expressed concern with the proposed work on the Hylebos. EPA stated that some areas of the Hylebos had been designated "monitored natural recovery" areas. AR at 1832. These areas were expected to remain undisturbed so that clean sediment could settle over and contain contaminated sediment. The EPA stated that it had asked PSE to summarize the existing data, identify data gaps, and develop a draft sampling and analysis plan to characterize sediment quality at the Hylebos project site. The EPA recommended that the final EIS should describe the uncertainty about sediment quality in the Hylebos, state that construction sequencing and design depend upon sediment and soil quality, and, in some places, sediment and/or soil removal may need to precede construction. The EPA did not express concerns about sediment in the Blair.

The City issued a final EIS evaluating the impact of the project in several categories. The EIS concludes that, in the long term, replacing creosote-treated piles will improve water quality. While removing the piles may temporarily disturb sediment and re-suspend contaminates, this effect is short term and will last about two tide cycles. The project will also result in a long term benefit to aquatic

No. 77748-3-1/4 life by reducing the total number of piles, decreasing the total area of over water coverage, and increasing benthic habitat.2 The EIS recommends employing best management practices(BMPs)to avoid or minimize the impact of sediment disturbance. BMPs include using a vibratory hammer to remove piles without disturbing sediment; cutting any broken piles two feet below the mud line and filling the hole with clean fill; limiting in- water construction to a window when the fewest fish are present; installing a silt curtain around the pile removal area to prevent sediment from migrating beyond the project footprint; and containing all removed sediment and creosote-treated wood. The EIS concludes that, with these BMPs, the project is likely to improve water quality and unlikely to have an adverse effect on aquatic life. PSE's JARPA application In addition to the EIS, the project requires shoreline and development permits from the City of Tacoma. CP at 29-30, 34. The project also requires permits from the Washington State Department of Ecology, the Washington State Department of Fish and Wildlife, and the Army Corps of Engineers. CP at 33-34. While the EIS process was taking place, PSE submitted a master application (Joint Aquatic Resources Permit Application or JARPA)for these permits. Id. Each entity began its own review.

The Army Corps of Engineers reviewed the project for compliance with federal environmental acts. The Army Corps received input from a number of other agencies, including the EPA. The EPA did not express concerns about in-

2 The benthic zone is the lowest level of a body of water. WEBSTER'S THIRD NEW INTERNATIONAL DICTIONARY 204(2002).

No. 77748-3-1/5 water work in the Blair but commented that in-water work in the Hylebos should not occur without sediment testing. The EPA stated that the results of this testing may result in changes to the design of the project or the sequence of work. The Army Corps adopted the EPA's conditions.

The City reviewed PSE's application to determine if the project complied with Tacoma's Shorelines Master Program (TSMP). Under the TSMP, development on the shoreline must result in no net loss of ecological function. The City concluded that, if PSE adheres to BMPs and conditions imposed by other agencies, the project will meet this standard. The City issued a shoreline substantial development permit(SSDP).

The Tribe asked the City to reconsider, asserting that the City failed to adequately consider impacts to ecological function. In particular, the Tribe argued that the City had not considered the risk of spreading contaminated sediment in the Hylebos.

The City granted the Tribe's motion in part. The City stated that the SSDP erroneously omitted the standard condition that the applicant must obtain all other agency permits and comply with any conditions imposed before the City will issue development(construction or demolition) permits. The City noted that both the Department of Ecology and the EPA had identified a risk from disturbing contaminated sediment in the Hylebos and sediment testing would be required prior to federal and state permitting. The City modified the SSDP to require PSE to (1) secure all required agency permits before seeking development permits from the City;(2) demonstrate that sediment testing has been completed and

Free access — add to your briefcase to read the full text and ask questions with AI

The Puyallup Tribe Of Indians, V City Of Tacoma, (Wash. Ct. App. 2018).

The Puyallup Tribe Of Indians, V City Of Tacoma (The Puyallup Tribe Of Indians, V City Of Tacoma) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Overlake Fund v. Shorelines Hearings Board
954 P.2d 304 (Court of Appeals of Washington, 1998)
Hayes v. Yount
552 P.2d 1038 (Washington Supreme Court, 1976)
Buechel v. Department of Ecology
884 P.2d 910 (Washington Supreme Court, 1994)
Hightower v. Kansas City Southern Railway Co.
2003 OK 45 (Supreme Court of Oklahoma, 2003)
Darrell De Tienne, V Shorelines Hearings Board
391 P.3d 458 (Court of Appeals of Washington, 2016)
City of Redmond v. Arroyo-Murillo
70 P.3d 947 (Washington Supreme Court, 2003)
Watch v. Skagit County
120 P.3d 56 (Washington Supreme Court, 2005)