Otis Elevator Co. v. Standard Construction Co.

10 F.R.D. 404, 1950 U.S. Dist. LEXIS 3675
CourtDistrict Court, D. Minnesota
DecidedJanuary 3, 1950
DocketNo. 3066 Civil
StatusPublished
Cited by7 cases

This text of 10 F.R.D. 404 (Otis Elevator Co. v. Standard Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Otis Elevator Co. v. Standard Construction Co., 10 F.R.D. 404, 1950 U.S. Dist. LEXIS 3675 (mnd 1950).

Opinion

NORDBYE, Chief Judge.

On or about January 26, 1946, the Swedish Hospital of Minneapolis, hereinafter sometimes called “Swedish”, and the Standard Construction Company, 'hereinafter sometimes called “Standard”, entered into a contract upon a cost plus a fee basis for the construction of certain new floors at the hospital and for certain alterations in the existing hospital structure. The total cost was estimated in the contract at $640,-€00 plus the fee to Standard of five per cent of the final construction figure. On February 16, 1946, Otis Elevator Company, hereinafter sometimes called “Otis”, and Standard Construction Company entered into a contract for installation of two elevators and three dumb waiters in the hospital. The amount of that contract was $76,842. The work both of Standard and Otis eventually was claimed to be completed, and Standard paid Otis approximately $59,215.51 of the elevator contract price. According to Otis, approximately $17,526.49 remains unpaid. This action is brought by Otis to recover that amount.

Standard’s answer alleges, among other things, that it acted as the agent of Swedish Hospital when it executed the elevator contract. Swedish Hospital has moved to intervene upon the premise that Standard acted as its agent when Standard executed the elevator contract and therefore that Swedish has an interest which entitles Swedish to intervene as a matter of right pursuant to Rule 24(a). Swedish contends that Standard’s representation of Swedish’s interest is or may be inadequate, that Swedish may be bound by a judgment in favor of Otis against Standard, and that Swed-dish’s interest and the action between Otis and Standard have common questions of law and fact involved. The intervention, Swedish argues, will not delay or prejudice the adjudication of the rights of Otis and Standard. Swedish also seeks to assert a counterclaim against Otis for approximately $250,000 damages.

Otis objects to the intervention principally upon the theory that as a matter of law no agency relationship existed between Standard and Swedish in view of their contract for construction of the additional floors and alterations, and that the Court must deny Swedish’s petition to intervene under Rule 24(b) in an action between an independent contractor (Standard) and Otis. Swedish contends that the question of agency cannot be determined on motion to intervene. The contracts between Swedish and Standard and Standard and Otis, together with other written exhibits, are annexed to the pleadings and are a part of the record of this case.

The contract between Swedish and Standard provides that Standard will do the construction work in accordance with the plans and specifications of the architects at an estimated cost of $640,000 plus $6,000 for boilers and generator equipment. A five per cent fee based upon the construction cost was to be paid to Standard. Sub-contracts exceeding $500 were to be submitted to the building committee before letting. Standard was to receive, audit, and approve all invoices and to pay them from a special bank account into which Swedish was required to deposit funds weekly in accordance with the rate of completed construction. The authorized signature' of an officer of Swedish Hospital was required, however, on the checks. Payrolls were to be handled by Standard and paid from funds deposited by Swed[406]*406ish. Standard’s compensation insurance policy and public liability and property damage insurance policy was to be operative for the job. Swedish was to be furnished with receipted invoices, etc., and they were subject to verification by Swedish. Materials, tools, and supplies which Standard furnished from its yard were to be figured at cost to Standard. A method for disposing of excess materials at termination of the work also was enunciated. A field office was to be maintained as a part of the construction cost.

The contract between Swedish and Standard does not mention elevators specifically. And the architects’ specifications to which the contract refers likewise omit elevators. In fact, they specifically declare that they do not cover elevator and certain other factors in building. Swedish contends, therefore, that the elevator matter was not intended to be included in the written contract with Standard and that the arrangement between Swedish and Standard regarding the elevators was one in parole which created an agency in Standard to contract with Otis on behalf of Swedish for the elevators and dumb waiters. Swedish contends that all the facts and attendant circumstances concerning the written contract and the arrangements for the elevators and the performance of the contract and the elevator arrangement must be considered in determining the existence of an agency between Swedish and Standard for the elevator transaction. Otis, on the other hand, contends that the written contract establishes that as a matter of law the relationship between Standard and Swedish was that of independent contractor and owner during the entire job and with respect to the entire job, including the elevators, and that that contract is exclusive and controlling.

The Minnesota law is clear that “The contracts themselves do not necessarily govern the question, and the relation of respondeat superior may depend entirely upon the conduct of the parties.” Anderson v. Foley Bros., 110 Minn. 151, 153, 124 N.W. 987, 988. See also Gill v. Northwest Airlines, 228 Minn. 164, 36 N.W.2d 785; Alansky v. Northwest Airlines, 224 Minn. 138, 28 N.W.2d 181, and cases cited therein. Consequently, it seems clear that the contracts between Standard and Swedish are not conclusive. The conduct of those parties and also of Otis may be considered in determining the existence of an agency relationship with respect to the elevator contract between Standard and Otis. The inquiry is not confined necessarily to the written contracts between Swedish and Standard, and Standard and Otis. All the facts and circumstances, including the conduct of the parties, may be recognized and considered.

As Swedish points out, the contract between itself and Standard declares that the work shall be done in accordance with the specifications contained in the architects’ plans for the building. Those plans and specifications specifically omit elevators. Consequently, the contract between Swedish and Standard, even if it seems to create an independent contractor situation with respect to what it covers, is at least sufficiently uncertain that the Court should not hold, on this showing, that the situation will not permit explanation to show what the intent of the parties to the contract actually was. Otis does cite several letters and also some cases in support of its contention that the reference to the specifications should cut no figure. But the effect to be given the letters really goes to the merits of the agency question. And although citations are helpful in many instances, the question here is what was the intention of the parties. To insert into their contract by general rules the terms which they may not have contemplated, violates the rule that every legal contract must be interpreted and enforced according to the intent of the parties in so far as that intent can be determined legally.

The question on a petition to intervene is whether a well-pleaded defense or claim is asserted. Its merits are not to be determined. The defense or claim is assumed to be true on motion to intervene, at,least in the absence of sham, frivolity, and other similar objections.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. N. Maisel & Associates v. Canden Corp.
398 N.E.2d 1366 (Indiana Court of Appeals, 1980)
State Ex Rel. Algonquin Golf Club v. Lewis
395 S.W.2d 522 (Missouri Court of Appeals, 1965)
Harry J. Stadin v. Union Electric Company
309 F.2d 912 (Eighth Circuit, 1962)
Ozark County School District R-V of Ozark County v. Lay
358 S.W.2d 77 (Missouri Court of Appeals, 1962)
Dalva v. Bailey
158 F. Supp. 204 (S.D. New York, 1957)
Hartley Pen Co. v. Lindy Pen Co.
16 F.R.D. 141 (S.D. California, 1954)
Clark v. Sandusky Appeal of De Rose
205 F.2d 915 (Seventh Circuit, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
10 F.R.D. 404, 1950 U.S. Dist. LEXIS 3675, Counsel Stack Legal Research, https://law.counselstack.com/opinion/otis-elevator-co-v-standard-construction-co-mnd-1950.