Oscar Renda Contracting v. City of Lubbock, Tex.

577 F.3d 264, 2009 U.S. App. LEXIS 16100, 2009 WL 2154423
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 21, 2009
Docket08-10481
StatusPublished
Cited by3 cases

This text of 577 F.3d 264 (Oscar Renda Contracting v. City of Lubbock, Tex.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oscar Renda Contracting v. City of Lubbock, Tex., 577 F.3d 264, 2009 U.S. App. LEXIS 16100, 2009 WL 2154423 (5th Cir. 2009).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

The plaintiffs-appellants Oscar Renda Contracting, Inc., and John C. Beck, appeal the district court’s grant of summary judgment against their claims against the City of Lubbock, Texas. Renda claims that Lubbock violated its constitutional right of free speech in denying it a construction contract; Renda joins the claim of Beck, a Lubbock taxpayer, that Lubbock’s failure to award the contract to Renda unlawfully deprived taxpayers of the benefit of Renda’s lower bid in violation of the Texas Local Government Code.

I

The “South Lubbock Drainage Project— Package # 1 Main Trunk Line” involved the installation of approximately ten miles of pipe at depths of up to forty-five feet, improving the city’s storm water drainage. The Lubbock city council considered it a high profile project, requiring attention to safety as well as adroit coordination of construction activities with environmental and regulatory authorities, affected landowners, and the public. The council set a budget and solicited bids from contractors pursuant to Texas law. Under this law, the council was obliged to select a winning bid from the “lowest responsible bidder or ... the bidder who provides goods or services at the best value for the municipality,” basing the assessment on enumerated factors, including price, reputation, and quality. 1

Renda is a contractor based in Roanoke, Texas. Its bid on the South Lubbock Drainage Improvement Project of $23.5 million undercut the next lowest contractor, Utility Contractors of America, by $2.2 million.

In order to determine whether Lubbock should accept Renda’s offer, Lubbock’s City Utility Engineer Marsha Reed began an investigation into Renda, using information provided in its bid form as well as public records. She made inquiry with organizations that had dealt with Renda. They offered mixed reports on Renda’s performance. An August 13, 2004, memorandum to Lubbock’s mayor and city council discussed the issue and summarized the information she had received about Renda and the next-highest bidder, Utility Contractors of America. Utility Contractors fared much better in every category of concern that the inquiry forms addressed. Among other problems with Renda’s history, Reed specifically cited a contract dispute in Arlington, Texas, resulting in a lawsuit initiated by Renda, and an action brought by the Occupational Safety and Health Administration against Renda for alleged safety violations. Her memo mentioned no other litigation. She emphasized “serious safety and environmental concerns and public relations concerns,” noting that “there will be City employees down in these trenches and in the pipe not to mention the amount of public contact involved with this project.” By contrast, she pointed out that her research into Utility Contractors found “a much better track record in working with the public and there were no safety or environmental issues cites by any of their references.”

In a chart attached to her report, out of a total of forty-seven boxes with responses concerning Renda, many of them tepid at best, only one box referenced the lawsuit *267 against the El Paso Municipal Utility District that Renda now argues was the grounds for Lubbock’s unconstitutional retaliation against it. Reporting information apparently from El Paso officials, the box indicates that “[Renda was v]ery lawsuit happy — Sued water district for $4 mill on a $6 mill project.” Another box reports from a different Renda customer: “Has both positives and negatives about them. Owner has been threatened with lawsuits several times during job when things did not go their way.” Two other boxes, neither apparently reporting El Paso feedback, answer the questions “Were there any claims? Were they justified?” with “Differing conditions claim,” and “Yes— pending.” Only one out of four boxes with answer to these questions said “no.” By contrast, all four of Utility Contractors’ respondents answered “no” to this query about litigiousness and construction problem-solving. 2 As noted, this was only one of many areas of information sought about the project bidders, and only one area of concern about Renda that would naturally arise from a perusal of the feedback chart.

A follow-up memo from Reed reiterates safety and environmental concerns as well as “community concerns over traffic control and access.” The memo recounts a September 16, 2004, meeting in which Renda sought to reassure the city as to some of the safety concerns, but the memo notes that Lubbock’s research suggested that Renda was “not completely honest with us in our meeting when specifically asked about th[e] issue” of whether it bore some responsibility for fines issued by the Texas Commission on Environmental Quality on a project. Ultimately, Reed concludes that while she “still has reservations,” her “final recommendation” is that Renda should be awarded the contract. She conditions this finding on Renda’s executing an affidavit affirming its understanding of a number of the contractual terms and Lubbock’s expectations. The affidavit emphasizes the agreed-upon contingencies for cost overruns, the necessity of safety and regulatory compliance, and Renda’s performance of due diligence in preparing the project.

Despite the recommendation and the affidavit, the city council decided at its September 28 meeting to award the contract to Utility Contractors instead of Renda, by a narrow 4-3 majority. Discussion focused on reputation, safety, and reliability concerns, 3 and on whether doubts about Renda could justify spending over $2 million more on the project. Although not discussed in any detail, Renda’s possible litigiousness came up as well, 4 with the *268 council focused on the fact that it was already having to contend with a $2.5 million contract dispute on an unrelated project. 5

One month later, Renda was back before the council, attempting to convince it to change its mind. Its effort did not take a form likely to persuade that it was not litigious. Rather the opposite, as Renda made it a point to lift up the El Paso suit in a thinly disguised effort to infect the award decision. In the hearing, Renda’s representatives, including its lawyer Terry Salazar, attacked the council’s decision not to award the job to Renda and attempted to plant public seeds to aid a retaliation claim. A representative of Renda announced:

I want to just make sure this goes on the record, that we know the decision that was made by the majority was against the law. We know, we’ve been told and informed by the City staff, that the motivating factor was this lawsuit out in El Paso; but we gave you a copy of that. So you know that your motivating factor was a lawsuit that they filed to address a violation of their first amendment [sic]. You can’t use that to hold against them, and yet you do.

This was the first mention of the El Paso suit in the council’s proceedings and came after the council had awarded the contract to Renda’s competitor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
577 F.3d 264, 2009 U.S. App. LEXIS 16100, 2009 WL 2154423, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oscar-renda-contracting-v-city-of-lubbock-tex-ca5-2009.