Orion Marine Contractors, Inc. v. City of Seward

CourtCourt of Appeals for the Ninth Circuit
DecidedAugust 29, 2018
Docket16-35919
StatusUnpublished

This text of Orion Marine Contractors, Inc. v. City of Seward (Orion Marine Contractors, Inc. v. City of Seward) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orion Marine Contractors, Inc. v. City of Seward, (9th Cir. 2018).

Opinion

NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS AUG 29 2018 MOLLY C. DWYER, CLERK U.S. COURT OF APPEALS FOR THE NINTH CIRCUIT

ORION MARINE CONTRACTORS, INC., No. 16-35919

Plaintiff-Appellant, D.C. No. 3:15-cv-00151-SLG

v. MEMORANDUM* CITY OF SEWARD,

Defendant-Appellee.

Appeal from the United States District Court for the District of Alaska Sharon L. Gleason, District Judge, Presiding

Argued and Submitted June 11, 2018 Anchorage Old Federal Building, Alaska

Before: THOMAS, Chief Judge, and CALLAHAN and BEA, Circuit Judges.

Orion Marine Contractors, Inc. contracted with the City of Seward for a

breakwater rock production project (“the Project”) pursuant to a competitive bid

solicitation. Under the terms of the contract (“the Contract”), Orion had the option

of requesting early termination—an escape valve in case the Project turned out to

be uneconomical. Orion requested, and the City approved, early termination after

* This disposition is not appropriate for publication and is not precedent except as provided by Ninth Circuit Rule 36-3. Orion finished the Project’s first phase. In light of early termination, the City paid

Orion a fraction of its bid item for mobilization and demobilization

(“mob/demob”) costs. Orion brought this action seeking payment of the balance.

The district court granted summary judgment for the City, holding that Orion

was entitled to only the amortized payments it had received for mob/demob before

Orion invoked early termination. We review the district court’s determination de

novo. Oswalt v. Resolute Indus., Inc., 642 F.3d 856, 859 (9th Cir. 2011). Because

the early termination provision’s operation and the Contract’s text and structure

lead us to conclude that Orion is entitled to payment in full on its mob/demob bid

item, we vacate the district court’s judgment and remand for entry of judgment in

favor of Orion.1

I.

The Contract included four phases: a Base Bid phase and three Additive

Amounts. It also included a termination-for-convenience provision—Addendum

No. 3—that allowed Orion to request early termination after it completed the Base

Bid phase. Addendum No. 3 accounted for the economic uncertainty around rock

quarried from untested areas that were to be mined for the Project.

Orion won the Contract with a bid of $6,150,900, which included a Base Bid

amount of $1,520,000. Included in the Base Bid was $873,000 for mob/demob for

1 The City’s motion to strike (Dkt. No. 19) is GRANTED.

2 the entire Project.

Section 01505 Part 4 of the Contract addressed payments for mob/demob.

Part 4.1 had three sections: A, B, and C. Sections A and B provided for two

amortized payments for mob/demob, the first when 4% (Section A) of the Project

was completed, and the second when 8% (Section B) of the Project was completed.

§ 01505, pt. 4.1(A)–(B). Section C required payment of the remainder of the

mob/demob bid item if the following condition was met: “The remaining balance

of the amount bid for Mobilization and Demobilization will be paid after all

submittals required under the Contract are received and approved.” § 01505,

pt. 4.1(C).

The City paid Orion $492,072 for its two amortized submittals, or

approximately 56% of the $873,000 mob/demob bid item. Orion invoked early

termination before seeking payment of the balance under Section C. The City

accepted early termination, effective November 25, 2014.

II.

Termination-for-convenience releases a contractor from further performance

by “permit[ting] a party . . . to unilaterally cancel its contractual obligations.” 2

Philip L. Bruner and Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction

Law § 5:270 (1st ed. 2002) (“Bruner & O’Connor”). While early termination does

not release a contractor from all contractual obligations, it does alter the “scope of

3 th[o]se obligations.”2 Id. § 5:271. Thus, the parties’ required actions change when

early termination is invoked. See id. The upshot is that the party invoking early

termination “avoid[s] committing a breach of contract which would expose it to

damages.” Id. § 5:270.

With the operation of a termination-for-convenience provision in mind, we

consider how Addendum No. 3 interacts with the Contract’s other provisions. See

Monzingo v. Alaska Air Grp., Inc., 112 P.3d 655, 660–61 (Alaska 2005) (construing

contractual terms under Alaska law by assessing “the language of the contract as a

whole”); see also Rockstad v. Glob. Fin. & Inv. Co., 41 P.3d 583, 586–87 (Alaska

2002) (instructing courts to “interpret the terms of the [contract] harmoniously,

avoiding those interpretations that cause conflicts among the provisions”). Early

termination limited Orion’s performance obligations “under the Contract” to the

Base Bid phase. Section 01505 entitled Orion to full payment of its mob/demob

bid item upon remitting “all submittals required under the Contract” to the City.

§ 01505, pt. 4.1(C). Because early termination cancelled Orion’s obligations

beyond the Base Bid phase, the submittals “required” of it were correspondingly

limited. Accordingly, if Orion remitted all submittals required to close out the

2 The City concedes that early termination modified what was required of the parties under the Contract, acknowledging that a “termination for convenience clause changes what the contract requires by cutting off all post-termination obligations.”

4 Contract in light of early termination, it is entitled to full payment on its

mob/demob bid item.3

It is undisputed that after the City approved Orion’s request for early

termination, the City sent Orion a list of submittals that were, in the City’s words,

“required prior to final payment request.” It is also undisputed that Orion remitted

all of those “required” submittals and that the City accepted those submittals.

Thus, in light of the early termination’s effect on Orion’s performance obligations,

we find that Orion remitted to the City “all submittals required under the

Contract.” See § 01505, pt. 4.1(C). And because those submittals were “received

and approved” by the City, we hold that Orion satisfied the condition precedent to

receiving full payment on its mob/demob bid item. See id.

The City argues that another contractual provision, § 14.4, precludes full

payment under § 01505. We disagree. Section 14.4 addressed additional payments

3 The Alaska Supreme Court’s decision in Quality Asphalt Paving, Inc. v. Department of Transportation and Public Facilities, 71 P.3d 865 (Alaska 2003) is inapposite because it does not address the question presented here. There, the court rejected full mob/demob payment under early termination where payment was conditioned on the contractor “perform[ing] all the work and labor required in the construction project.” Id. at 870. The condition precedent was therefore completion of all work necessary to finish the project. Id. Here, by contrast, the condition precedent is “all submittals required under the Contract,” irrespective of whether the Project is completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oswalt v. RESOLUTE INDUSTRIES, INC.
642 F.3d 856 (Ninth Circuit, 2011)
Monzingo v. Alaska Air Group, Inc.
112 P.3d 655 (Alaska Supreme Court, 2005)
Rockstad v. Global Finance & Investment Co.
41 P.3d 583 (Alaska Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Orion Marine Contractors, Inc. v. City of Seward, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orion-marine-contractors-inc-v-city-of-seward-ca9-2018.