Orion Marine Contractors, Inc. v. City of Seward
This text of Orion Marine Contractors, Inc. v. City of Seward (Orion Marine Contractors, Inc. v. City of Seward) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS AUG 29 2018 MOLLY C. DWYER, CLERK U.S. COURT OF APPEALS FOR THE NINTH CIRCUIT
ORION MARINE CONTRACTORS, INC., No. 16-35919
Plaintiff-Appellant, D.C. No. 3:15-cv-00151-SLG
v. MEMORANDUM* CITY OF SEWARD,
Defendant-Appellee.
Appeal from the United States District Court for the District of Alaska Sharon L. Gleason, District Judge, Presiding
Argued and Submitted June 11, 2018 Anchorage Old Federal Building, Alaska
Before: THOMAS, Chief Judge, and CALLAHAN and BEA, Circuit Judges.
Orion Marine Contractors, Inc. contracted with the City of Seward for a
breakwater rock production project (“the Project”) pursuant to a competitive bid
solicitation. Under the terms of the contract (“the Contract”), Orion had the option
of requesting early termination—an escape valve in case the Project turned out to
be uneconomical. Orion requested, and the City approved, early termination after
* This disposition is not appropriate for publication and is not precedent except as provided by Ninth Circuit Rule 36-3. Orion finished the Project’s first phase. In light of early termination, the City paid
Orion a fraction of its bid item for mobilization and demobilization
(“mob/demob”) costs. Orion brought this action seeking payment of the balance.
The district court granted summary judgment for the City, holding that Orion
was entitled to only the amortized payments it had received for mob/demob before
Orion invoked early termination. We review the district court’s determination de
novo. Oswalt v. Resolute Indus., Inc., 642 F.3d 856, 859 (9th Cir. 2011). Because
the early termination provision’s operation and the Contract’s text and structure
lead us to conclude that Orion is entitled to payment in full on its mob/demob bid
item, we vacate the district court’s judgment and remand for entry of judgment in
favor of Orion.1
I.
The Contract included four phases: a Base Bid phase and three Additive
Amounts. It also included a termination-for-convenience provision—Addendum
No. 3—that allowed Orion to request early termination after it completed the Base
Bid phase. Addendum No. 3 accounted for the economic uncertainty around rock
quarried from untested areas that were to be mined for the Project.
Orion won the Contract with a bid of $6,150,900, which included a Base Bid
amount of $1,520,000. Included in the Base Bid was $873,000 for mob/demob for
1 The City’s motion to strike (Dkt. No. 19) is GRANTED.
2 the entire Project.
Section 01505 Part 4 of the Contract addressed payments for mob/demob.
Part 4.1 had three sections: A, B, and C. Sections A and B provided for two
amortized payments for mob/demob, the first when 4% (Section A) of the Project
was completed, and the second when 8% (Section B) of the Project was completed.
§ 01505, pt. 4.1(A)–(B). Section C required payment of the remainder of the
mob/demob bid item if the following condition was met: “The remaining balance
of the amount bid for Mobilization and Demobilization will be paid after all
submittals required under the Contract are received and approved.” § 01505,
pt. 4.1(C).
The City paid Orion $492,072 for its two amortized submittals, or
approximately 56% of the $873,000 mob/demob bid item. Orion invoked early
termination before seeking payment of the balance under Section C. The City
accepted early termination, effective November 25, 2014.
II.
Termination-for-convenience releases a contractor from further performance
by “permit[ting] a party . . . to unilaterally cancel its contractual obligations.” 2
Philip L. Bruner and Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction
Law § 5:270 (1st ed. 2002) (“Bruner & O’Connor”). While early termination does
not release a contractor from all contractual obligations, it does alter the “scope of
3 th[o]se obligations.”2 Id. § 5:271. Thus, the parties’ required actions change when
early termination is invoked. See id. The upshot is that the party invoking early
termination “avoid[s] committing a breach of contract which would expose it to
damages.” Id. § 5:270.
With the operation of a termination-for-convenience provision in mind, we
consider how Addendum No. 3 interacts with the Contract’s other provisions. See
Monzingo v. Alaska Air Grp., Inc., 112 P.3d 655, 660–61 (Alaska 2005) (construing
contractual terms under Alaska law by assessing “the language of the contract as a
whole”); see also Rockstad v. Glob. Fin. & Inv. Co., 41 P.3d 583, 586–87 (Alaska
2002) (instructing courts to “interpret the terms of the [contract] harmoniously,
avoiding those interpretations that cause conflicts among the provisions”). Early
termination limited Orion’s performance obligations “under the Contract” to the
Base Bid phase. Section 01505 entitled Orion to full payment of its mob/demob
bid item upon remitting “all submittals required under the Contract” to the City.
§ 01505, pt. 4.1(C). Because early termination cancelled Orion’s obligations
beyond the Base Bid phase, the submittals “required” of it were correspondingly
limited. Accordingly, if Orion remitted all submittals required to close out the
2 The City concedes that early termination modified what was required of the parties under the Contract, acknowledging that a “termination for convenience clause changes what the contract requires by cutting off all post-termination obligations.”
4 Contract in light of early termination, it is entitled to full payment on its
mob/demob bid item.3
It is undisputed that after the City approved Orion’s request for early
termination, the City sent Orion a list of submittals that were, in the City’s words,
“required prior to final payment request.” It is also undisputed that Orion remitted
all of those “required” submittals and that the City accepted those submittals.
Thus, in light of the early termination’s effect on Orion’s performance obligations,
we find that Orion remitted to the City “all submittals required under the
Contract.” See § 01505, pt. 4.1(C). And because those submittals were “received
and approved” by the City, we hold that Orion satisfied the condition precedent to
receiving full payment on its mob/demob bid item. See id.
The City argues that another contractual provision, § 14.4, precludes full
payment under § 01505. We disagree. Section 14.4 addressed additional payments
3 The Alaska Supreme Court’s decision in Quality Asphalt Paving, Inc. v. Department of Transportation and Public Facilities, 71 P.3d 865 (Alaska 2003) is inapposite because it does not address the question presented here. There, the court rejected full mob/demob payment under early termination where payment was conditioned on the contractor “perform[ing] all the work and labor required in the construction project.” Id. at 870. The condition precedent was therefore completion of all work necessary to finish the project. Id. Here, by contrast, the condition precedent is “all submittals required under the Contract,” irrespective of whether the Project is completed.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Orion Marine Contractors, Inc. v. City of Seward, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orion-marine-contractors-inc-v-city-of-seward-ca9-2018.