Orion Drilling Co LLC v. EQT Production Co

CourtCourt of Appeals for the Third Circuit
DecidedAugust 28, 2020
Docket19-3307
StatusUnpublished

This text of Orion Drilling Co LLC v. EQT Production Co (Orion Drilling Co LLC v. EQT Production Co) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orion Drilling Co LLC v. EQT Production Co, (3d Cir. 2020).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _____________

No. 19-3307 _____________

ORION DRILLING COMPANY, LLC, Appellant

v.

EQT PRODUCTION COMPANY ______________

On Appeal from the United States District Court for the Western District of Pennsylvania (D.C. Civil No. 2-16-cv-01516) Chief Magistrate Judge: Honorable Maureen P. Kelly ______________

Argued July 2, 2020 ______________

Before: GREENAWAY, JR., SHWARTZ, and RENDELL, Circuit Judges.

(Opinion Filed: August 28, 2020) Andrew K. Fletcher [ARGUED] Richard M. Weibley Kevin M. Eddy Blank Rome LLP 501 Grant Street Suite 850 Pittsburgh, PA 15219 Attorneys for Appellant

Nicolle R. Snyder Bagnell [ARGUED] Colin E. Wrabley Lucas Liben Devin M. Misour Alex G. Mahfood Reed Smith LLP 225 Fifth Avenue Suite 1200 Pittsburgh, PA 15222 Attorneys for Appellee

______________

OPINION ∗ ______________

GREENAWAY, JR., Circuit Judge.

At the heart of this case is a contract dispute between two natural gas companies,

Plaintiff-Appellant Orion Drilling Company, LLC (“Orion”) and Defendant-Appellee

Equitable Production Company (“EQT”). In short, due to safety concerns, EQT

terminated two rig drilling contracts it had with Orion. As a result, EQT and Orion now

dispute whether liquidated damages are or are not due to Orion. Orion believes that

Exhibit A, section 7.3, found in both drilling contracts, sets forth the only method by

which EQT could terminate the drilling contracts early without paying liquidated

damages. EQT disagrees, claiming that per section 6.5, found in both drilling contracts,

it is entitled to terminate early due to Orion’s default and material breach. For example,

EQT argues that Orion’s failure to comply with industry standards or to meet safety

polices relieves it of any obligation to make liquidated damages payments. Orion sued

EQT for breach of contract, a jury found in favor of EQT, and the District Court upheld

∗ This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent.

2 that verdict. There are six issues on appeal, and for the reasons discussed below, we will

affirm in toto.

I. FACTUAL AND PROCEDURAL BACKGROUND

A. Factual Background 1

1. The Contracts

In 2014, Orion and EQT entered into four contracts regarding Orion’s building

and operation of two drilling rigs—Rig 17 and Rig 18—for EQT: a drilling contract for

each rig and a construction contract for each rig. The Rig 17 and Rig 18 drilling

contracts (collectively the “Drilling Contracts”), which are governed by Pennsylvania

law, are of primary relevance to this dispute.2 The Drilling Contracts each contain the

essential provisions that control this dispute—section 6.5 and Exhibit A, section 7.3. 3

1 We note at the outset that the District Court’s September 10, 2019 Opinion was very thorough, assiduously detailing the facts of this case, and we reference the opinion throughout. See Orion Drilling Co. v. EQT Prod. Co., No. CV 16-1516, 2019 WL 4273861, at *1 (W.D. Pa. Sept. 10, 2019). 2 Per the Drilling Contracts, using the rigs it would build and own, Orion would drill wells for EQT in exchange for specified payments per day. Also, per the Drilling Contracts, Orion had the sole obligation to ensure the safe operation of the rigs. 3 Two other provisions with ancillary relevance are section 6.1 and section 6.4. Section 6.1 details the duration of each contract (i.e., the respective terms for each rig), while section 6.4, which was amended, pertains to the “Early Termination Compensation” and directs one to “See ‘Exhibit A, Other Provisions’ Item 7.3.” JA346, 381 (emphasis in the original); see also Orion Drilling, 2019 WL 4273861, at *2–4 (showing the stricken former section 6.4, located above section 6.5, which had described early termination compensation and provided for liquidated damages but now directs one to Exhibit A, section 7.3).

3 Section 6.5 pertains to “TERMINATION” and has two subsections regarding: (1)

“Project Termination for Default,” and (2) the rights EQT has “[i]n the event of a

default by [Orion][.]” JA346, 381 (emphasis in the original); see also Orion Drilling,

2019 WL 4273861, at *3–4 (reproducing, for ease of reference, the Drilling Contracts’

relevant provisions). Exhibit A, section 7.3 pertains to “Early Termination” and details

how EQT can terminate the drilling contract early, for any reason, so long as liquidated

damages are paid, unless three conditions are met. 4 JA355, 390; see also Orion Drilling,

2019 WL 4273861, at *4–5.

2. Rig Failures and EQT’s Early Termination

In 2015, both Rig 17 and Rig 18 began drilling. Subsequently, there were four key

dropped block incidents on Rig 18.5 Three dropped blocks occurred on September 25,

4 These three conditions permit EQT to terminate early per Exhibit A, section 7.3 without “pay[ing] an early termination amount” if any one of the conditions can be satisfied, for example, the second condition is if: “(b) [Orion] suffers involuntary or voluntary bankruptcy, is insolvent or subject to receivership or similar insolvency proceedings.” JA355, 390; see also Orion Drilling, 2019 WL 4273861, at *4. 5 “A dropped block is an uncontrolled descent of approximately 50,000 pounds of the drill’s top drive, traveling block, and associated equipment in the mast[.]” Orion Drilling, 2019 WL 4273861, at *5 (citation and quotation marks omitted); see also id. at *5–6 (referencing evidence from trial detailing not only the “peril” of such incidents, which “raise significant safety concerns for the lives and well-being of any contractors or employees working on the drilling platform below,” but also the “rarity” of even a single incident). In addition to the dropped block incidents, there were also other safety concerns regarding both rigs—documented by EQT via letters to Orion—that EQT believed were “directly related to the [Integrated Drive Systems (“IDS”)] or [were] premature equipment failures of critical components necessary to efficiently and safely execute [the] drilling program.” JA3355; see also Orion Drilling, 2019 WL 4273861, at *6 (noting that each rig was equipped with the IDS control system); Appellee Br. 7 (explaining that 4 2015 (“Incident One”), October 10, 2015 (“Incident Two”), and June 7, 2016 (“Incident

Three”). The fourth key dropped block occurred after EQT terminated the Drilling

Contracts.

After each incident, there was correspondence between the two companies. See

generally Orion Drilling, 2019 WL 4273861, at *6–9 (providing a more detailed recount

of the parties’ communication). Of particular relevance are the following three

interactions:

First, after Incident One, EQT sent a notice of default letter to Orion referencing

section 6.5(1)(F) of the Rig 18 drilling contract, as well as the applicable cure period, and

stressing that Orion needed to cure the problem “to EQT’s satisfaction,” JA3343.

Second, after Incident Two, EQT sent Orion a letter noting in part that due to

Orion’s failure to timely cure the block malfunction pursuant to the first notice of

default—as evidenced by the occurrence of Incident Two—Orion was in default of the

Rig 18 Drilling Contract per section 6.5 of the drilling contract. 6

Third, after Incident Three, EQT sent Orion written notice that Rig 18 was to be

shut down for “environmental, health and safety protection and due to material unsafe

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Green
617 F.3d 233 (Third Circuit, 2010)
Bull v. United Parcel Service, Inc.
665 F.3d 68 (Third Circuit, 2012)
Abrams v. Lightolier Inc.
50 F.3d 1204 (Third Circuit, 1995)
United States v. Robert W. Lee, Sr.
359 F.3d 194 (Third Circuit, 2004)
Great American Insurance v. Norwin School District
544 F.3d 229 (Third Circuit, 2008)
Vasilis v. Bell of Pennsylvania
598 A.2d 52 (Superior Court of Pennsylvania, 1991)
LJL Transportation, Inc. v. Pilot Air Freight Corp.
962 A.2d 639 (Supreme Court of Pennsylvania, 2009)
Cimina v. Bronich
537 A.2d 1355 (Supreme Court of Pennsylvania, 1988)
Widmer Engineering, Inc. v. Dufalla
837 A.2d 459 (Superior Court of Pennsylvania, 2003)
Trizechahn Gateway LLC v. Titus
976 A.2d 474 (Supreme Court of Pennsylvania, 2009)
McShea v. City of Philadelphia
995 A.2d 334 (Supreme Court of Pennsylvania, 2010)
John B. Conomos, Inc. v. Sun Co., Inc.
831 A.2d 696 (Superior Court of Pennsylvania, 2003)
TruServ Corp. v. Morgan's Tool & Supply Co.
39 A.3d 253 (Supreme Court of Pennsylvania, 2012)
Biborosch v. Transamerica Insurance
603 A.2d 1050 (Superior Court of Pennsylvania, 1992)
Nikole, Inc. v. Klinger
603 A.2d 587 (Superior Court of Pennsylvania, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Orion Drilling Co LLC v. EQT Production Co, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orion-drilling-co-llc-v-eqt-production-co-ca3-2020.