Orion Drilling Co LLC v. EQT Production Co

Court of Appeals for the Third Circuit·Decided August 28, 2020·No. 19-3307·Unpublished

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

No. 19-3307

ORION DRILLING COMPANY, LLC, Appellant

v.

EQT PRODUCTION COMPANY

On Appeal from the United States District Court for the Western District of Pennsylvania (D.C. Civil No. 2-16-cv-01516)

Chief Magistrate Judge: Honorable Maureen P. Kelly

Argued July 2, 2020

Before: GREENAWAY, JR., SHWARTZ, and RENDELL, Circuit Judges.

(Opinion Filed: August 28, 2020)

Andrew K. Fletcher [ARGUED] Richard M. Weibley Kevin M. Eddy Blank Rome LLP 501 Grant Street Suite 850 Pittsburgh, PA 15219 Attorneys for Appellant

Nicolle R. Snyder Bagnell [ARGUED] Colin E. Wrabley Lucas Liben Devin M. Misour Alex G. Mahfood

Reed Smith LLP 225 Fifth Avenue Suite 1200 Pittsburgh, PA 15222 Attorneys for Appellee

OPINION ∗

GREENAWAY, JR., Circuit Judge.

At the heart of this case is a contract dispute between two natural gas companies, Plaintiff-Appellant Orion Drilling Company, LLC (“Orion”) and Defendant-Appellee Equitable Production Company (“EQT”). In short, due to safety concerns, EQT terminated two rig drilling contracts it had with Orion. As a result, EQT and Orion now dispute whether liquidated damages are or are not due to Orion. Orion believes that Exhibit A, section 7.3, found in both drilling contracts, sets forth the only method by which EQT could terminate the drilling contracts early without paying liquidated damages. EQT disagrees, claiming that per section 6.5, found in both drilling contracts, it is entitled to terminate early due to Orion’s default and material breach. For example, EQT argues that Orion’s failure to comply with industry standards or to meet safety polices relieves it of any obligation to make liquidated damages payments. Orion sued EQT for breach of contract, a jury found in favor of EQT, and the District Court upheld

This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent.

that verdict. There are six issues on appeal, and for the reasons discussed below, we will affirm in toto.

I. FACTUAL AND PROCEDURAL BACKGROUND A. Factual Background 1 1. The Contracts

In 2014, Orion and EQT entered into four contracts regarding Orion’s building and operation of two drilling rigs—Rig 17 and Rig 18—for EQT: a drilling contract for each rig and a construction contract for each rig. The Rig 17 and Rig 18 drilling contracts (collectively the “Drilling Contracts”), which are governed by Pennsylvania law, are of primary relevance to this dispute.2 The Drilling Contracts each contain the essential provisions that control this dispute—section 6.5 and Exhibit A, section 7.3. 3

Section 6.5 pertains to “TERMINATION” and has two subsections regarding: (1)

“Project Termination for Default,” and (2) the rights EQT has “[i]n the event of a default by [Orion][.]” JA346, 381 (emphasis in the original); see also Orion Drilling, 2019 WL 4273861, at *3–4 (reproducing, for ease of reference, the Drilling Contracts’ relevant provisions). Exhibit A, section 7.3 pertains to “Early Termination” and details how EQT can terminate the drilling contract early, for any reason, so long as liquidated damages are paid, unless three conditions are met. 4 JA355, 390; see also Orion Drilling, 2019 WL 4273861, at *4–5.

2. Rig Failures and EQT’s Early Termination In 2015, both Rig 17 and Rig 18 began drilling. Subsequently, there were four key dropped block incidents on Rig 18.5 Three dropped blocks occurred on September 25, 2015

(“Incident One”), October 10, 2015 (“Incident Two”), and June 7, 2016 (“Incident Three”). The fourth key dropped block occurred after EQT terminated the Drilling Contracts.

After each incident, there was correspondence between the two companies. See generally Orion Drilling, 2019 WL 4273861, at *6–9 (providing a more detailed recount of the parties’ communication). Of particular relevance are the following three interactions:

First, after Incident One, EQT sent a notice of default letter to Orion referencing section 6.5(1)(F) of the Rig 18 drilling contract, as well as the applicable cure period, and stressing that Orion needed to cure the problem “to EQT’s satisfaction,” JA3343.

Second, after Incident Two, EQT sent Orion a letter noting in part that due to Orion’s failure to timely cure the block malfunction pursuant to the first notice of default—as evidenced by the occurrence of Incident Two—Orion was in default of the Rig 18 Drilling Contract per section 6.5 of the drilling contract. 6 Third, after Incident Three, EQT sent Orion written notice that Rig 18 was to be shut down for “environmental, health and safety protection and due to material unsafe conditions,” JA3396, after a “third party contractor on the drilling floor when the Rig faile

d was nearly killed when the blocks landed inches away,” id., and noting that Orion was in default per subsections 6.5(1)(F) and 6.5(1)(H) of the Rig 18 drilling contract. 7 The parties engaged in extensive communication regarding rig issues after each incident in an attempt to resolve these problems. See, e.g., Orion Drilling, 2019 WL 4273861, at *6–9 (recounting in greater detail the parties’ interactions). Relevant to this appeal, and in addition to EQT’s three letters just discussed, is a letter agreement the parties’ reached on June 16, 2016 (herein the “Letter Agreement”), after Incident Three occurred and EQT sent a shutdown letter.

In the Letter Agreement, the parties agreed to various conditions which “document[ed] the steps to be taken by Orion to address EQT’s stated concerns for the safety of its employees and contractors.” Id. at *8.8 One of the conditions was that an independent safety engineering firm, Aberdeen Drilling Consultants, Ltd. (“ADC”), would conduct an investigation. After ADC investigated Rig 18 and “identified 11 nonco

nformance issues and made several key conclusions that raised serious concerns with the safety of the hardware and software of the IDS control system,” id. at *9, EQT proceeded to send four additional crucial letters to Orion. See id. (noting that ADC’s report indicated that “even if [Orion did] everything” that ADC prescribed, there was still uncertainty regarding whether “the rig could operate safely” (alteration in the original) (citation and quotation marks omitted)).

First, EQT sent a letter to Orion shutting down Rig 17—as that rig relied on the same IDS control system as Rig 18. Next, EQT sent Orion a notice of default and breach letter for Rig 17 pursuant to both section 6.5 and Exhibit A, section 7.3 of the Rig 17 drilling contract. See also id. at *10 (detailing how this “notice identified 16 serious safety incidents on Rig 17, including erratic brake operation and at least one instance where the brakes did not engage, resulting in a dropped block.”). Then, EQT sent Orion a termination letter for Rig 18. 9 And finally, EQT sent Orion a termination letter for Rig 17. 10 B. Procedural Background Orion brought a two-count breach of contract complaint against EQT for the early termination of the Drilling Contracts in an attempt to recover liquidated damages payments. Orion asserted that EQT could not “terminate the contract before the end of the contra

ct term unless it [paid] the early termination payment as calculated under [Exhibit A, section 7.3.]” JA320, 321. 11 Prior to trial, the District Court ruled that section 6.5 and Exhibit A, section 7.3 of the Drilling Contracts were unambiguous, alternative methods for terminating the Drilling Contracts. 12 See, e.g., JA27 (explaining that the identical provisions in both Drilling Contracts “unambiguously allow EQT to terminate pursuant either to 6.5 or 7.3 of Exhibit A without the payment of any liquidated damages, and this is the plain meaning as set forth on that issue.”). The District Court also ruled that Orion spoliated evidence, and accordingly gave an adverse inference spoliation instruction to the jury during trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Orion Drilling Co LLC v. EQT Production Co, (3d Cir. 2020).

Orion Drilling Co LLC v. EQT Production Co (Orion Drilling Co LLC v. EQT Production Co) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Green
617 F.3d 233 (Third Circuit, 2010)
Bull v. United Parcel Service, Inc.
665 F.3d 68 (Third Circuit, 2012)
Abrams v. Lightolier Inc.
50 F.3d 1204 (Third Circuit, 1995)
United States v. Robert W. Lee, Sr.
359 F.3d 194 (Third Circuit, 2004)
Great American Insurance v. Norwin School District
544 F.3d 229 (Third Circuit, 2008)
Vasilis v. Bell of Pennsylvania
598 A.2d 52 (Superior Court of Pennsylvania, 1991)
LJL Transportation, Inc. v. Pilot Air Freight Corp.
962 A.2d 639 (Supreme Court of Pennsylvania, 2009)
Cimina v. Bronich
537 A.2d 1355 (Supreme Court of Pennsylvania, 1988)
Widmer Engineering, Inc. v. Dufalla
837 A.2d 459 (Superior Court of Pennsylvania, 2003)
Trizechahn Gateway LLC v. Titus
976 A.2d 474 (Supreme Court of Pennsylvania, 2009)
McShea v. City of Philadelphia
995 A.2d 334 (Supreme Court of Pennsylvania, 2010)
John B. Conomos, Inc. v. Sun Co., Inc.
831 A.2d 696 (Superior Court of Pennsylvania, 2003)
TruServ Corp. v. Morgan's Tool & Supply Co.
39 A.3d 253 (Supreme Court of Pennsylvania, 2012)
Biborosch v. Transamerica Insurance
603 A.2d 1050 (Superior Court of Pennsylvania, 1992)
Nikole, Inc. v. Klinger
603 A.2d 587 (Superior Court of Pennsylvania, 1992)