Orbas & Associates v. Secretary of the Navy

863 F. Supp. 1186, 40 Cont. Cas. Fed. 76,740, 1994 U.S. Dist. LEXIS 13156, 1994 WL 506713
CourtDistrict Court, E.D. California
DecidedJune 8, 1994
DocketCIV-S-94-0377-DFL-JFM
StatusPublished
Cited by1 cases

This text of 863 F. Supp. 1186 (Orbas & Associates v. Secretary of the Navy) is published on Counsel Stack Legal Research, covering District Court, E.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orbas & Associates v. Secretary of the Navy, 863 F. Supp. 1186, 40 Cont. Cas. Fed. 76,740, 1994 U.S. Dist. LEXIS 13156, 1994 WL 506713 (E.D. Cal. 1994).

Opinion

MEMORANDUM OF DECISION AND ORDER

LEVI, District Judge.

An evidentiary hearing was held in this case on April 28, 1994. At the close of the hearing, both parties agreed that the hearing shall constitute the trial on the merits of this action. See Fed.R.Civ.P. 65(a)(2). This memorandum of decision constitutes the court’s findings of fact and conclusions of law pursuant to Fed.R.Civ.P. 52(a).

I

On August 11,1993, Naval Facilities issued an Invitation for Bids in the construction of a Child Development Center at Travis Air Force Base. 1 The submitted bids were to include prices for the base bid and three options. Potential bidders were instructed that the Navy would evaluate the bids for award purposes based on the sum of the base bid and the three options, but that the Navy would not necessarily exercise any of the *1188 options. The bids were received and publicly opened on September 14, 1993.

Plaintiff Orbas submitted the lowest total bid, $2,750,000. This bid was $345,000 lower than the Navy’s estimate, and $542,582 lower than the bid from Arntz General Construction (“Arntz”), to whom the contract was eventually awarded. 2 When the bids were compared, it was revealed that Orbas’ bid was 11% lower than the Navy’s estimate and 17% lower than Arntz’s bid. At the same time, Orbas’ bids on options 1 and 3 were significantly higher than the Navy’s estimate and the rest of the bids. These disparities led the contracting officer, Barbara-Ann Bycsek, to question the accuracy of Orbas’ bids. Following the procedure provided at 48 C.F.R. § 14.406-1, Bycsek contacted Orbas and requested that Orbas review its worksheets for possible errors or omissions. (Ex. 8.) If Orbas determined its bid price to be correct as submitted, Orbas was to provide written confirmation of its bid and provide a cost breakdown of the bid by specification sections. The contracting officer emphasized the importance of receiving Orbas’ response by September 17, 1993. No response was received, so Bycsek telephoned Orbas on September 17 and again on September 20. Each time Bycsek was told that Orbas was waiting for confirmation from its bonding company before confirming its bid. During the September 20 conversation, Mrs. Orbas inquired whether all of the options would be awarded. Bycsek informed her that no decision had been made concerning the options. Mrs. Orbas then informed Bycsek that an error had been made in its bid, because certain costs, in the amount of “approximately” $120,000, had been allocated to option 3 instead of to the base bid. Mrs. Orbas ended the conversation with a promise to provide a definitive answer by the early morning of September 21, 1993.

Orbas did not respond by its own deadline. On September 23, 1993, Orbas sent a letter by facsimile to the contracting officer stating simply:

At this point in time, upon review of Orbas & Associates’ bid for this contract, it does not appear that a mistake has been made. However, the bonding company is reviewing the job and it is expected that their response will be forthcoming this afternoon or at the latest tomorrow.

(Ex. 9.)

Bycsek replied to this letter by facsimile alerting Orbas that its response did not adequately address the Navy’s concerns. (Ex. 10.) Bycsek established a deadline of 12:00 p.m., September 24, 1993, for a proper response “including bid confirmation, bid breakdown, worksheets and a list of references with telephone numbers.” Orbas confirmed its bid by facsimile at 11:48 a.m., September 24, 1993. Attached to the letter were “summary worksheets, contract history and references.” (Ex. 11.) The facsimile did not include the requested bid breakdown and original, pre-bid worksheets.

A bid verification meeting was scheduled for September 28, 1993, between Orbas and the contracting officer and her staff. In the confirmation letter, Orbas was reminded that its representative must bring “the originals and copies of all worksheets/data used in the development” of the bid. (Ex. 12.) The parties differ as to what occurred at the verification meeting. Defendant contends that Orbas’ representative, Richard Legere, was not able to adequately respond to the Navy’s questions and did not have the appropriate original worksheets and other materials with him at the meeting. Legere testified that he answered all of the Navy’s questions; clarified Orbas’ intent to confirm its bid, whether or not the Navy allowed Orbas to correct its misalloeation of $120,000 to option 3 rather than to the base bid; and brought the original worksheets and other *1189 materials with him, but no one ever asked to see them.

Based on this meeting, Bycsek found that a mistake had been made in Orbas’ bid and rejected the bid. (Ex. 18.) The rejection was based upon Orbas’ “failure to provide adequate documentation, namely original worksheets to support the basis of [its] bid, as well as [Orbas’] inability to adequately demonstrate, when questioned during the bid verification meeting, how [Orbas] would perform the work within the price bid.” (Id.) In light of the large disparity between Orbas’ bid and the government estimate and other bids, the contracting officer determined that acceptance of Orbas’ bid would be unreasonable and unfair to other bidders. (Id.) The contract, consisting of the base bid and options 1 and 2, was awarded to the next lowest bidder, Arntz General Construction, on September 29, 1993.

Orbas filed a protest with the Comptroller General, and a stop work order was issued to Arntz until the General Accounting Office (“GAO”) made its decision denying the protest on February 25, 1994. In its decision, the GAO found that the contracting officer had acted reasonably in light of unexplained disparities between Orbas’ “worksheet” and its bid, the unexplained disparities between its bid and the government’s estimates, and the unsubstantiated claim of error concerning option 3. The Acting General Counsel particularly stressed Orbas’ failure to substantiate its bid:

A bid may be rejected as mistaken where there is a price disparity between the bid and the other bids received and the government estimate, and where the bidder has failed to furnish sufficient documentation to substantiate its bid calculations when so requested____ Despite several opportunities to explain the price disparities, Orbas elected to submit only a “worksheet” that was created after bid opening and thus not relied upon for the preparation of the bid, whose limited information did not enable the agency to determine why the significant price disparities existed or whether the bid included all the cost elements required under the solicitation. Further, Orbas chose to ignore the agency’s requests for an explanation of its bid calculations, and was unable to substantiate these calculations at the bid verification meeting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Virgin Islands Paving, Inc. v. United States
103 Fed. Cl. 292 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
863 F. Supp. 1186, 40 Cont. Cas. Fed. 76,740, 1994 U.S. Dist. LEXIS 13156, 1994 WL 506713, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orbas-associates-v-secretary-of-the-navy-caed-1994.