OR-OSHA v. Loy Clark Pipeline, Co.

514 P.3d 544, 320 Or. App. 205
CourtCourt of Appeals of Oregon
DecidedJune 8, 2022
DocketA171747
StatusPublished
Cited by6 cases

This text of 514 P.3d 544 (OR-OSHA v. Loy Clark Pipeline, Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
OR-OSHA v. Loy Clark Pipeline, Co., 514 P.3d 544, 320 Or. App. 205 (Or. Ct. App. 2022).

Opinion

Argued and submitted April 1, reversed and remanded June 8, petition for review denied November 23, 2022 (370 Or 471)

OCCUPATIONAL SAFETY & HEALTH DIVISION, Petitioner, v. LOY CLARK PIPELINE, CO., Respondent. Workers’ Compensation Board 1700028SH; A171747 514 P3d 544

In this review from a decision of the Workers’ Compensation Board, the agency contests the board’s determination that employer did not violate certain workplace safety rules related to an excavation in northwest Portland. About 30 days before the scheduled hearing, the administrative law judge (ALJ) rejected the agency’s amendment to the workplace safety citation by concluding that the amendment would delay the hearing and that the amendment amounted to a new violation under applicable administrative rules. Among other things, the agency assigns error to the ALJ’s decision to reject the amendment to the citation. Held: The ALJ erroneously interpreted the applicable rule related to the timing of amendments. Although an ALJ may set a schedule for a contested case, includ- ing limiting the timing of amendments, such limit must be communicated to the parties before an amendment is filed. Absent a different schedule communicated to the parties, an ALJ is without discretion to reject an amendment on timing grounds. As the agency’s amendment in this case merely clarified the factual allegations it intended to prove at the hearing and did not change the time or place of the alleged violation, nor allege a violation of a different safety rule, the amendment did not constitute a new violation within the meaning of the rules. Reversed and remanded.

Erin K. Galli, Assistant Attorney General, argued the cause for petitioner. Also on the briefs were Ellen F. Rosenblum, Attorney General, and Benjamin Gutman, Solicitor General. James S. Anderson argued the cause for respondent. Also on the brief were George W. Goodman and Cummins, Goodman, Denley & Vickers, P. C. Before Shorr, Presiding Judge, and Mooney, Judge, and Pagán, Judge. PAGÁN, J. Reversed and remanded. 206 OR-OSHA v. Loy Clark Pipeline, Co.

PAGÁN, J. Petitioner, Oregon Occupational Safety and Health Administration (OR-OSHA) seeks review of a Workers’ Compensation Board (WCB) order, following a hearing before an administrative law judge (ALJ), which concluded that OR-OSHA failed to establish a violation arising from an excavation in northwest Portland. OR-OSHA alleged that employer, Loy Clark Pipeline Company, failed to obtain “locates” for underground utilities prior to digging at a work site.1 In October 2016, employer’s workers struck an under- ground natural gas line, causing a leak and, eventually, a series of explosions. OR-OSHA advances a number of arguments on review; however, as we conclude that OR-OSHA is correct that the ALJ erred by not allowing OR-OSHA’s amendment to the citation prior to hearing, we write only to address that assignment of error. Our resolution of that issue obviates the need to address OR-OSHA’s arguments related to the ALJ’s order on reconsideration and the ALJ’s determination that employer had complied with the applicable safety rules. We reverse and remand. Although the relevant facts are largely procedural, to provide context, we briefly summarize the background facts giving rise to this review. BACKGROUND In 2016, employer was performing excavation and utility work at a construction site in northwest Portland, near the intersection of NW 23rd Avenue and NW Glisan Street, including installation of an underground conduit and a new power pole on the north side of NW Glisan. Employer obtained “locate” marks for the underground utilities in that area on July 12, 2016. A photograph in the appellate record taken around July 12 depicts a yellow dashed paint marking from the street, crossing the north sidewalk of NW 1 “Locate” marks are color-coded marks that depict the approximate surface location for underground utilities. See generally OAR 952-001-0010(12) (defining “marks” to include “stakes, paint or other clearly identifiable material, to show the field location or absence of underground facilities at a proposed work site”); OAR 952-001-0070 (explaining marking for underground facilities). Cite as 320 Or App 205 (2022) 207

Glisan, and ending at a natural gas meter on the side of a building. On July 19, employer’s crew removed a portion of the sidewalk, excavated, and installed several power con- duits, before later covering the opening with a temporary asphalt patch. Notably, the marks that were on the portion of sidewalk that was removed were lost and no new marks were made on the asphalt patch. In September 2016, employer had a separate project on the south side of NW Glisan Street; that project was not related to the July project. Employer obtained locate marks for the south side project before excavation. On October 19, 2016, employer started work on another project on the north side of the street—this time to install a junction box for a Comcast line—in the same area as the July excavation. The foreman for the October job had not been on the July job, so, although he was aware of pre- vious excavations in the area, he did not know the specific details. No new locate marks were made for the October job. When the crew arrived, the marks from the July 12 utility locate were faint and faded, in particular the yellow marks that indicated natural gas lines. The foreman observed the work site, saw some of the locate marks, and thought he could see “what was going where.” All three of employer’s workers saw markings for underground gas lines near the excavation site, but none of them thought the line was run- ning through the area to be excavated. Using saws and a backhoe, the workers removed a portion of the asphalt patch and concrete sidewalk. As the foreman was using the back- hoe to remove gravel underneath the sidewalk, the backhoe caught a natural gas line, causing a leak. A number of explo- sions occurred as a result, injuring eight people and causing more than $17 million in property damage. Afterward, the foreman and another worker saw a yellow locate mark on the street curb and another yellow mark on the street that indicated a one-inch natural gas line near the excavation. The foreman had parked the back- hoe over the locates from the July 2016 job, and so he had not seen them that morning. He testified that, had he seen those marks, he would have known there was a natural gas line in the work area. 208 OR-OSHA v. Loy Clark Pipeline, Co.

OR-OSHA investigated the incident and noted that after the locate marks were placed in July, employer exca- vated in the area, installed conduit, and closed the excavation with temporary asphalt. One OR-OSHA officer noted that part of the July locate marks had been removed during the July job and had not been replaced. An OR-OSHA manager noted that the yellow natural gas mark on the curb was faint. After the investigation, OR-OSHA issued employer a citation for violating 29 CFR § 1926.651(b)(1), which requires: “The estimated location of utility installations, such as sewer, telephone, fuel, electric, water lines, or any other underground installations that reasonably may be expected to be encountered during excavation work, shall be determined prior to opening an excavation.” Under the statutory and regulatory authority cre- ated by the Oregon Safe Employment Act (OSEA), OR-OSHA “has promulgated rules setting safety and health standards for a vast range of workplaces and occupational activities.”2 OR-OSHA v. United Parcel Service, Inc., 312 Or App 424, 432, 494 P3d 959 (2021). OAR 437-003-0001(16)(b) adopts 29 CFR § 1926.651 in full.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Answorth, Inc. v. OLCC
344 Or. App. 470 (Court of Appeals of Oregon, 2025)
Clardy v. Gangitano
556 P.3d 642 (Court of Appeals of Oregon, 2024)
Rinne v. PSRB
Court of Appeals of Oregon, 2023

Cite This Page — Counsel Stack

Bluebook (online)
514 P.3d 544, 320 Or. App. 205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/or-osha-v-loy-clark-pipeline-co-orctapp-2022.